The data centres are here.
The power is not.

2,281 MW of proposed IT capacity, all of it on grids below the 44.5% national renewable share

Australia's AI data centres are not being built where the renewable electricity is. Operators have proposed 2,281 MW of new IT capacity, the only figure they all define the same way. Every megawatt sits on a grid running below the 44.5% national renewable share. This report maps the 65 campuses against the seven grids that would supply them. It asks who is buying their power and which networks have said how much new demand they can take. Then it follows the undersea internet cables and screens 23 coastal sites for a factory to build wave-powered floating data centres and send them out to the power.

All the proposed load is queuing on grids that run below the national share, and winter pulls them further under

Renewable share of generation and fuel mix by grid and month, November 2024 to September 2026; proposed built IT capacity by gridSource: Open Electricity v4 API, monthly energy by region and fuel; consolidated data-centre inventory. NTESMO for the Darwin-Katherine system, which has no monthly series, carries 6 MW and enters the national line at its annual share

  1. New South Wales 41.0% over 12 months · below national in 23 of 23 months 849 MW
  2. Queensland 36.8% over 12 months · below national in 23 of 23 months 12 MW
  3. Victoria 43.3% over 12 months · below national in 12 of 23 months 1,414 MW
  4. South Australia 79.0% over 12 months · below national in 0 of 23 months None
  5. Tasmania 97.7% over 12 months · below national in 0 of 23 months None
  6. Western Australia 40.1% over 12 months · below national in 18 of 23 months None

National share

Winter Winter 2024 2025 2026 N N D D J J F F M M A A M M J J J J A A S S O O N N D D J J F F M M A A M M J J J J A A S S 0% 25% 50% 75% 100% Renewable share of generation Each grid, monthly Sep 2026 TAS 91.9% SA 84.1% National 48.3% VIC 47.6% NSW 46.1% WA 41.3% QLD 40.5% Jun 2025 Queensland falls to 27%; Victoria, where 1,414 MW of theproposed load would sit, to 37%.The country runs 35% Jun 2025 South Australia's low: 63% Aug 2026 Tasmania's low: 91% Fuel mix, month by month Proposed IT capacity, MW New South Wales 41.0% over 12 months Below national 23 of 23 849 Queensland 36.8% over 12 months Below national 23 of 23 12 Victoria 43.3% over 12 months Below national 12 of 23 1,414 South Australia 79.0% over 12 months Below national 0 of 23 None Tasmania 97.7% over 12 months Below national 0 of 23 None Western Australia 40.1% over 12 months Below national 18 of 23 None

Fuel mix strips HydroWindSolarRooftopBioenergy BatteryGasCoalOther

Renewable share of generation by grid and month
Month New South WalesQueenslandVictoriaSouth AustraliaTasmaniaWestern Australia National
Nov 2024 43.3%32.7%44.1%78.5%99.7%47.3% 44.8%
Dec 2024 42.8%31.3%46.8%82.5%99.8%45.4% 44.8%
Jan 2025 41.9%32.1%45.2%83.4%99.5%40.5% 43.6%
Feb 2025 41.1%30.9%47.6%80.6%99.0%41.6% 43.5%
Mar 2025 37.7%26.8%41.4%80.7%98.6%42.2% 40.1%
Apr 2025 38.0%29.8%36.8%71.6%98.6%39.0% 39.1%
May 2025 32.9%28.3%37.2%70.0%97.7%35.4% 37.2%
Jun 2025 28.8%26.6%36.7%62.7%97.7%27.7% 34.6%
Jul 2025 30.7%30.2%38.9%68.6%98.3%27.8% 37.2%
Aug 2025 33.8%30.6%39.8%72.4%91.3%34.9% 39.1%
Sep 2025 42.9%35.2%52.1%80.7%99.9%41.7% 47.7%
Oct 2025 47.5%37.3%51.2%81.0%100.0%44.8% 49.2%
Nov 2025 49.4%36.8%48.6%89.2%100.0%53.4% 50.1%
Dec 2025 48.8%38.0%48.5%86.6%100.0%51.4% 49.6%
Jan 2026 46.6%38.2%48.2%85.4%99.9%48.2% 48.8%
Feb 2026 41.5%37.3%46.5%84.7%100.0%46.1% 46.1%
Mar 2026 37.6%37.5%38.8%80.0%100.0%41.8% 42.4%
Apr 2026 40.4%38.8%40.2%80.7%100.0%36.2% 43.8%
May 2026 33.3%34.6%37.0%69.6%99.3%33.1% 39.1%
Jun 2026 32.0%33.7%37.8%70.9%99.3%25.0% 38.4%
Jul 2026 33.6%32.8%38.9%63.8%93.9%28.4% 38.7%
Aug 2026 36.0%35.7%38.9%71.5%91.0%32.0% 40.7%
Sep 2026 46.1%40.5%47.6%84.1%91.9%41.3% 48.3%
  1. NEXTDC 1H26 Results Announcement (ASX Release, 25 February 2026) , NEXTDC Limited, 2026-02-25.

    Operational IT capacity across the 65 campuses I tracked. It measures the electricity their servers can draw once fitted and switched on, before cooling. I leave out figures given only as a floor. The proposed pipeline is nearly ten times larger. Chapter 2

  2. FY26 Results Presentation , NEXTDC Limited (ASX: NXT), 2026-08-27.

    Proposed built IT capacity, meaning the power operators have fitted or plan to fit for servers. It is the only measure every operator defines the same way. Another 13,050 MW stays out of the total because it is published under other measures, such as whole-facility power or grid requests. Chapter 2

  3. Open Electricity API: NEM monthly energy by region and fuel technology, October 2025 to September 2026 , Open Electricity, 2026-10-01.

    Share of proposed IT capacity on grids below the 44.5% national renewable share, weighted by the electricity each grid generates. South Australia and Tasmania, the two grids with the highest renewable shares, have none of this capacity. Chapter 3

  4. CDC Data Centres update, Infratil Investor Day presentation (ASX release) , Infratil Limited (ASX), 2026-03-26.

    Large campuses of 50 MW or more that publish no electricity supply arrangement, such as a power purchase agreement or certificates surrendered for their load. None of the 41 publishes a renewable share for its own load. Chapter 4

  5. International submarine cables landing in Australia , Australian Communications and Media Authority, 2026-09-17.

    Submarine cable systems landing in Australia with a service year published by their owner. Of these, 16 are live and 8 are announced; one of the live systems is the domestic SMAP. Six of the eight announced systems land in Sydney. Chapter 7

  6. 2026 Transmission Annual Planning Report , Transgrid, 2026-09-23.

    Data-centre load seeking connection in New South Wales, about twice the state's peak demand. In Western Sydney, Transgrid will have no room for more data-centre load in 2032/33 unless new transmission is built. Chapter 5

  7. Minister for Defence, release of the RAND Corporation report , Australian Government Department of Defence, 2015-04-16.

    Estimated extra capital cost of building a series of 20 Panthalassa nodes in Australia instead of at an established Asian yard. That assumes the conditions RAND found for halving the premium hold. Chapter 8

Skip the map tour

Generation

Brown emits, blue does not.

  • coal
  • hydro
  • gas
  • wind
  • battery
  • solar

Data centres

  • live
  • under construction
  • approved or committed
  • announced or applied for
  • funded: public money committed
  • not an IT measure
  • suburb location

Cables

  • in service
  • announced
  • landing station

Candidate sites

  • screened for the factory

1 · The generation fleet

Three of Australia's seven grids still get more than half their electricity from coal: 56% in New South Wales, 57% in Queensland and 54% in Victoria over the twelve months to September 2026. South Australia gets 79% of its generation from wind and sun. Tasmania gets 93% from hydro and wind, and rooftop solar takes that to 97.7%. Weighted by how much each grid generates, renewables come to 44.5% nationally. The rest of this report is measured against that number.

2 · The build-out

This map shows 65 data-centre campuses, drawn by status and sized by published capacity. Operators use seven different measures, and only IT capacity means the same thing at every campus: the electricity a campus's servers can draw before cooling and power losses. On that measure, 230 MW is installed today and 2,281 MW is proposed. The other 13,050 MW published across the inventory is real, but each operator is measuring something different, so I leave it out of both totals.

3 · The verdict

Every proposed megawatt sits on a grid below the national renewable share. All 2,281 MW of proposed IT capacity is in Victoria, New South Wales, Queensland and the Northern Territory, where the grids run at 43.3% renewable or less. South Australia at 79% and Tasmania at 97.7% have none of it.

4 · The cables

Cables do not decide where the data centres go. Cable landings cluster at Sydney, Perth, the Sunshine Coast and Darwin, while the proposed megawatts cluster in Melbourne and Sydney. Melbourne now has the most, yet it has no live international landing at all. Sixteen live cable systems land in Australia today, fifteen of them international. Eight more have been announced with a year published by their owners. Announced dates slip: ACC-1's Darwin landing has moved from 2025 to 2029.

5 · The sites

The start-up Panthalassa wants to turn the problem around with wave-powered data centres that float out to the power. Each unit, which the company calls a node, makes its own electricity at sea. The factory that builds them still needs a berth, a hall, a workforce and a grid connection on land. I screened 23 coastal sites for that factory, and eight clear every gate on public evidence.

6 · Everything at once

Four layers on one map: the power stations, the data centres, the cables and the candidate factory sites. Tasmania's grid runs at 97.7% renewable, the highest share in the country, yet it has no proposed megawatts of IT capacity. Its three new AI campuses publish capacity on other measures, mostly grid connections, and none gives an IT figure. Most of this report is about that gap between what is announced and what is pinned down. Around Sydney and Melbourne the marks pile on top of each other. The atlas lets you zoom into any city and click a mark to see what it is.

500 km

Generation

Brown emits, blue does not.

  • coal
  • hydro
  • gas
  • wind
  • battery
  • solar

Data centres

  • live
  • under construction
  • approved or committed
  • announced or applied for
  • funded: public money committed
  • not an IT measure
  • suburb location

Cables

  • in service
  • announced
  • landing station

Candidate sites

  • screened for the factory

Size by capacity

Generation 100 500 2,000 MW
Campus IT 100 500 2,000 MW

Square area follows built IT megawatts. Other measures, floors and unstated capacity: size withheld.

Chapter 1. Coal still makes most of the power where data centres are going

Australia generated 44.5% of its electricity from renewables in the year to September 2026. The three grids where most data centres are being built sit below that line. The two grids far above it have almost no data centres at all.

Over the twelve months to September 2026, coal supplied 56.1% of the electricity generated in New South Wales, 57.3% in Queensland and 53.5% in Victoria.11 Open Electricity v4 API, NEM energy by region and fuel technology, October 2025 to September 2026, Open Electricity, 31 October 2026. Western Australia's main grid, the South West Interconnected System or SWIS, is the fourth with coal. It ran on 22.8% coal and 32.0% gas over the same year.22 Open Electricity v4 API, WEM energy by fuel technology, October 2025 to September 2026, Open Electricity, 31 October 2026. These figures are shares of the energy each region actually generated across twelve monthly readings, not shares of installed capacity. For this report Australia has seven grids: the five regions of the National Electricity Market, the SWIS, and the Darwin-Katherine system in the Northern Territory.

Two grids look nothing like the others. Wind and solar supplied 79.0% of South Australia's generation, and the state burned no coal. Tasmania ran on 74.1% hydro and 18.9% wind, or 93.0% combined, and with rooftop solar counted its renewable share reaches 97.7%.11 Open Electricity v4 API, NEM energy by region and fuel technology, October 2025 to September 2026, Open Electricity, 31 October 2026. One caution applies to every figure in this chapter: a regional share describes what the power stations inside a region produced over a year, not what any one customer bought.

Three of the seven regions still take more than half their generation from coal

Share of generation by fuel technology, per cent, twelve months to September 2026, seven regionsSource: Open Electricity NEM and WEM APIs; NTESMO Northern Territory Renewables Report

  • New South Wales 41.0%
  • Queensland 36.8%
  • Victoria 43.3%
  • South Australia 79.0%
  • Tasmania 97.7%
  • South West Interconnected System 40.1%
  • Darwin-Katherine Interconnected System 19.6%

The first five bands, hydro to bioenergy, are the fuels counted as renewable. Where they stop short of the dashed national line, that grid is below the national share. These are shares of generation and not of capacity. The hollow band is generation published with no fuel label, which reaches 80% in the Northern Territory.

The year is an average of very different months

An annual share hides the seasons. Over 23 months of generation data starting in November 2024, the national renewable share swung between 50.1% in November 2025 and 34.6% in June 2025. The second winter was only a little better, at 38.4% in June 2026.33 Open Electricity v4 API, monthly energy by region and fuel technology, NEM and WEM, November 2024 to September 2026, Open Electricity, 31 October 2026. In June 2025, New South Wales dropped to 28.8% and Queensland to 26.6%. Both states sat below the national share in all 23 months, and Victoria sat below it in 12.33 Open Electricity v4 API, monthly energy by region and fuel technology, NEM and WEM, November 2024 to September 2026, Open Electricity, 31 October 2026. The seasons matter more for data centres than for most customers, because a data centre draws about the same load in July as in November. Winter is the season its power supply has to cover.

I count battery discharge separately and leave it out of the renewable share. Batteries supplied 1.5% of generation in New South Wales, 2.0% in Queensland, 1.8% in Victoria, 3.3% in South Australia and 5.0% in the SWIS.11 Open Electricity v4 API, NEM energy by region and fuel technology, October 2025 to September 2026, Open Electricity, 31 October 2026.22 Open Electricity v4 API, WEM energy by fuel technology, October 2025 to September 2026, Open Electricity, 31 October 2026. A battery only hands back energy that some other plant made, minus its losses. Calling that output renewable would count the same megawatt hour twice.

The outlook for 2030 and 2035

In the 2026 Integrated System Plan from the Australian Energy Market Operator, the Step Change scenario puts New South Wales at 91.36% renewable in 2030-31 and 96.28% in 2035-36.44 2026 Integrated System Plan, Step Change scenario workbook, AEMO, 2026. For the same two years, Queensland sits at 74.41% and 82.98%, Victoria at 85.02% and 98.31%, South Australia at 98.15% and 96.21%, and Tasmania at 100.00% and 99.99%. The operator, AEMO, runs the eastern grid and publishes this long-term plan every two years. I read these values from a public mirror of its workbook, because AEMO's own download blocks automated requests.55 IspParser, the public mirror of AEMO's ISP workbooks, OpenNEM, accessed 23 August 2026.

I have no 2030 or 2035 figure for the SWIS or Darwin-Katherine, so I left those cells empty instead of estimating them. Western Australia's SWIS Demand Assessment gives one figure for renewable generation: 96% by 2042. The state's better-known 80 per cent by 2030 is an emissions target, not a share of generation.66 SWIS Demand Assessment 2023 to 2042, Energy Policy WA, May 2023. The Northern Territory did have a target of 50% by 2030, measured as a share of electricity consumed. The incoming government scrapped it in March 2025 and has not replaced it.77 NT government scraps territory's 50 per cent renewables target, ABC News, 27 March 2025.

The Territory's current figure is also the weakest of the seven. It comes from NTESMO's report for the calendar year 2025, which covers all three regulated Territory systems together, not Darwin-Katherine alone. That report rolls thermal output into a single line. As a result, 80.4% of Territory generation has no fuel label, and the gas share shows as zero even though gas sits inside that unlabelled line.88 Northern Territory Renewables Report: 30 December 2024 to 28 December 2025, Northern Territory Electricity System and Market Operator, January 2026.

The plants, and what the map leaves out

The map shows 43 power stations of 100 MW or more. For most of them I use the maximum site capacity in AEMO's July 2026 Generation Information file.99 NEM Generation Information, July 2026, AEMO, July 2026. Among them, Eraring's 2,880 MW is now due to shut on 30 April 2029, and Yallourn's 1,600 MW on 1 July 2028.1010 2026 Electricity Statement of Opportunities, AEMO, August 2026. Pinjar is the shakiest entry: its 576 MW still comes from an archived Verve Energy page dated 2006.1111 Pinjar, Verve Energy, 22 August 2006. The 2026 WEM Electricity Statement of Opportunities schedules Pinjar's turbines to retire between 2031 and 2034, but never gives a total for the whole station.1212 2026 WEM Electricity Statement of Opportunities, AEMO, 15 July 2026.

There are no nuclear power plants on the map. The Coalition's material for its seven proposed sites gives no capacity for any of them. Nuclear power is also prohibited by section 10 of the Australian Radiation Protection and Nuclear Safety Act 1998 and section 140A of the Environment Protection and Biodiversity Conservation Act 1999. Both sections remain in the current compilations of those Acts.1313 Australian Radiation Protection and Nuclear Safety Act 1998, Federal Register of Legislation, accessed 23 August 2026.1414 Environment Protection and Biodiversity Conservation Act 1999, Federal Register of Legislation, accessed 23 August 2026.

The rest of the report looks at these seven grids from two directions. The first half lays the 65 data-centre campuses over them and asks who is buying their power, how much room the networks have, and where the undersea cables come ashore. The second half searches the coast for a site to build a factory for floating data centres that would generate their own power at sea. Even that factory has to plug into one of these grids.

  1. Open Electricity v4 API, NEM energy by region and fuel technology, October 2025 to September 2026, Open Electricity, 31 October 2026.
  2. Open Electricity v4 API, WEM energy by fuel technology, October 2025 to September 2026, Open Electricity, 31 October 2026.
  3. Open Electricity v4 API, monthly energy by region and fuel technology, NEM and WEM, November 2024 to September 2026, Open Electricity, 31 October 2026.
  4. 2026 Integrated System Plan, Step Change scenario workbook, AEMO, 2026.
  5. IspParser, the public mirror of AEMO's ISP workbooks, OpenNEM, accessed 23 August 2026.
  6. SWIS Demand Assessment 2023 to 2042, Energy Policy WA, May 2023.
  7. NT government scraps territory's 50 per cent renewables target, ABC News, 27 March 2025.
  8. Northern Territory Renewables Report: 30 December 2024 to 28 December 2025, Northern Territory Electricity System and Market Operator, January 2026.
  9. NEM Generation Information, July 2026, AEMO, July 2026.
  10. 2026 Electricity Statement of Opportunities, AEMO, August 2026.
  11. Pinjar, Verve Energy, 22 August 2006.
  12. 2026 WEM Electricity Statement of Opportunities, AEMO, 15 July 2026.
  13. Australian Radiation Protection and Nuclear Safety Act 1998, Federal Register of Legislation, accessed 23 August 2026.
  14. Environment Protection and Biodiversity Conservation Act 1999, Federal Register of Legislation, accessed 23 August 2026.

Chapter 2. The gigawatt headlines add up megawatts that measure different things

Operators publish capacity on seven different measures, and the gigawatt figures in the news add them together. Separated by measure, most announced megawatts sit outside operational and built IT capacity.

My totals use only IT capacity, the electricity a data centre's computers can draw before cooling and power losses are added on top. It is the only figure every operator defines the same way. I use two versions of it. Operational IT is what has been fitted out and switched on today. Built IT is what has been fitted or is planned to be fitted, and it is the version a proposal uses.

Across the 65 Australian data-centre campuses in my inventory, 230 MW of operational IT is installed today and 2,281 MW of built IT is proposed.1515 FY26 Record Results (ASX release), NEXTDC Limited, 27 August 2026. The same campuses publish another 13,050 MW on other measures, which I keep out of both totals because no two of those measures describe the same thing. The gigawatt numbers in the headlines are bigger still because they add seven measures together as if they were one.

Most of the published megawatts are not an IT measure

Data-centre capacity by the measure its operator published, megawatts, 65 campuses, consolidated 31 October 2026Source: Operator pages, ASX filings and NSW planning consents per campus; updated 31 October 2026

84% of the megawatts these campuses publish are on measures I leave out of the totals.

The same megawatts, by the measure each operator used

  • Fitted IT capacity, operating Counted as live 230 MW · 9 campuses
  • Fitted IT capacity, operating, published as a floor Floor, in no total 14 MW · 1 campus
  • Fitted IT capacity, built or planned Counted as proposed 2,281 MW · 12 campuses
  • Fitted IT capacity, built or planned In no total 451 MW · 5 campuses
  • Fitted IT capacity, built or planned, published as a floor Floor, in no total 1,990 MW · 8 campuses
  • IT plus cooling and support In no total 6,891 MW · 11 campuses
  • IT plus cooling and support, published as a floor Floor, in no total 555 MW · 3 campuses
  • Maximum demand at the connection point In no total 392 MW · 2 campuses
  • The proponent's full buildout concept In no total 524 MW · 3 campuses
  • The proponent's full buildout concept, published as a floor Floor, in no total 2,234 MW · 4 campuses
  • No capacity published In no total Not published · 7 campuses

The rows share an axis so their sizes can be compared, but they measure different things, so there is no single capacity to read off them. Only the two solid IT rows go into my totals. A figure published as a floor stays out even when it is an IT measure.

The seven measures are the operators' own. Operational IT is the fitted power available to computing equipment, some of which can sit vacant. Built IT is fitted IT capacity that is complete or planned. Contracted capacity is what customers have reserved, and it can exceed what has been built. Gross facility power adds cooling, power conversion and support systems to the IT load. Grid connection is the maximum demand a campus is permitted, or has asked, to draw at its connection point. Commissioned capacity is the energised phase of a campus built in stages. Ultimate capacity is the proponent's concept for the full site.

AirTrunk, NEXTDC and CDC in their own words

None of AirTrunk's five Australian campuses enters my IT totals, because the company says IT load when it means IT load. Its 27 October 2026 release, announcing a A$4.25 billion loan for SYD3, describes the five campuses with more than 1.2 GW of capacity and never says IT.1616 AirTrunk secures A$4.25B green loan for SYD3 Western Sydney expansion, AirTrunk, 27 October 2026. A December 2025 release gave the five numbers: SYD1 at 121 MW and above, SYD2 at 158, SYD3 at 330, MEL1 at 276 and MEL2 at 354. That same release said the Osaka campus will deliver up to 100 MW of IT load.1717 AirTrunk expands Australian platform with a second hyperscale data centre campus in Melbourne, AirTrunk, 24 December 2025. I treat the five Australian numbers as facility figures: three for campuses as built, and two for SYD3 and MEL2 at full build.

NEXTDC publishes an end-state IT capacity for each facility, not the power fitted today. Its FY26 results list 287.9 MW built, 537 MW in progress and 740.1 MW contracted at 30 June 2026, meaning customers have reserved more than two and a half times what it has built.1515 FY26 Record Results (ASX release), NEXTDC Limited, 27 August 2026. The same filing announces M5 Melbourne at up to 1.2 GW of IT capacity. M5 has no development approval and no published first stage, yet on its own it is more than half of all the built IT proposed in the country.1818 FY26 Results Presentation, NEXTDC Limited, 27 August 2026. NEXTDC also shows how two primary documents can disagree and both be correct. The planning consent for S4 Horsley Park describes an operational capacity of 250 MW, while NEXTDC now says 365 MW; the planning application for S7 names 612 MW, while the operator says about 550 MW and more.1919 NEXTDC S4 Data Centre Horsley Park (SSD-63741210), NSW Department of Planning, Housing and Infrastructure, 24 December 2025.1818 FY26 Results Presentation, NEXTDC Limited, 27 August 2026.

Since 30 June 2026, CDC has reported leasable capacity instead of built megawatts and stopped publishing figures for individual campuses.2020 Infratil Investor Day 2026: CDC update, Infratil, 16 September 2026. Its last campus figures came in September 2025: Beard at 110 MW, Eastern Creek at 280 and Marsden Park at 720. Each was stated as "at least", making it a floor on a measure the company has since retired.2121 Infratil Investor Day: CDC update, Infratil, 1 September 2025. CDC now reports by state: 220 MW leasable and operating in New South Wales, 120 in the Australian Capital Territory and 130 in Victoria, with 1.1 GW contracted against 350 MW deployed.2020 Infratil Investor Day 2026: CDC update, Infratil, 16 September 2026.

The totals, one measure at a time

Of the 230 MW of operational IT capacity, 181 MW is in New South Wales and the Australian Capital Territory, 44 MW is in Victoria and 5.4 MW is in South Australia.2222 NEXTDC 1H26 Results Announcement (ASX release), NEXTDC Limited, 25 February 2026. The 2,281 MW of proposed built IT splits into 1,414 MW in Victoria, 849 MW in New South Wales, 12 MW in Queensland and 6 MW in the Northern Territory. Victoria leads because of M5. New South Wales picked up Microsoft's 96 MW Huntingwood consent on 1 October and a Macquarie campus of roughly 200 MW announced in August. Macquarie's release does not state an IT measure, so I have inferred one from its wording.2323 Honeman Close Data Centre (SSD-58601963), NSW Department of Planning, Housing and Infrastructure, 1 October 2026.2424 Macquarie Technology FY26 results (ASX release), Macquarie Technology Group, 26 August 2026. Western Australia, South Australia and Tasmania still have nothing proposed on this measure.

Most announced megawatts sit in the excluded 13,050 MW. Gross facility power accounts for 7,446 MW and ultimate capacity for 2,758 MW. Grid connection accounts for 392 MW: 288 MW that Firmus says its Bell Bay site will draw, plus 104 MW in its Launceston supply contract.2525 Project Southgate Bell Bay: FAQs, Firmus Technologies, 3 July 2026. The remaining 2,455 MW uses an IT measure but still stays out of my totals, either because the operator published it as an "at least" floor or because it is a planned end state for a building already running. Each of those four figures is rounded to the nearest megawatt, which is why they add to 13,051. By grid, New South Wales has 6,171 of the excluded megawatts, Victoria 4,193, the Northern Territory 2,000, Tasmania 444, the South West Interconnected System 230 and Queensland 12.

Most of the newest proposals arrive as facility power. CDC's third Sydney campus, at Kemps Creek, was lodged at a total power consumption of 1.4 GW, and a Mamre Road campus for an undisclosed client at 1 GW. AirTrunk applied for 550.5 MW on the former aluminium smelter site at Kurri Kurri, the first hyperscale application in the Hunter.2626 KC1 Data Centre, Kemps Creek (SSD-133677993), NSW Department of Planning, Housing and Infrastructure, accessed 31 October 2026.2727 Mamre Road Data Centre Campus (SSD-92743706), NSW Department of Planning, Housing and Infrastructure, accessed 31 October 2026.2828 Kurri Kurri Data Centre (SSD-128819490), NSW Department of Planning, Housing and Infrastructure, 14 October 2026. Keppel describes 720 MW of gross power near Morwell in the Latrobe Valley, and Beetaloo Digital says its Weddell campus would need 2 GW from a gas power station of its own.2929 Keppel secures 720MW powerbank for AI data centre campus near Melbourne, Keppel Ltd, 15 January 2026.3030 Proposed $40b, 185ha data centre to use six times Top End's annual electricity consumption, ABC News, 22 July 2026. None of these enters an IT total. Together they are larger than every IT figure in the inventory.

The industry's 26.8 GW and AEMO's 67 GW

The number most people now quote is 26.8 GW. It comes from the second forecast Data Centres Australia published with DC Byte, using data at 30 September 2026. The forecast adds four phases of IT load: 1.6 GW operating, 0.4 GW under construction, 5.2 GW committed and 19.6 GW at an early stage. It defines early stage as projects that have not secured land, power or permits.3131 Australian Data Centre Forecast Report, Issue 2, data at 30 September 2026, Data Centres Australia and DC Byte, 30 October 2026. The April edition said 21.6 GW. Most of the five gigawatts of growth came from committed capacity, which rose from 3.1 GW, and from early-stage projects outside Sydney. Melbourne's pipeline is now 10.7 GW against Sydney's 7.8 GW, and 31% of the total is outside both cities.3131 Australian Data Centre Forecast Report, Issue 2, data at 30 September 2026, Data Centres Australia and DC Byte, 30 October 2026. DC Byte's phases are all IT load, so the gap between my 2,281 MW and its 5.6 GW under construction and committed has nothing to do with the measure. It comes down to stage and evidence: I count only named campuses that publish a built-IT figure with a source.

AEMO's 2026 reliability outlook counts connection capacity instead. It finds 225 data centres in development with 67 GW combined, and records that 36% of the projects on its 2025 list were cancelled within the year.3232 2026 ESOO data centre forecasting overview, AEMO, August 2026. AEMO also finds that connected data centres draw about 27% of the connection capacity they hold, and that their average demand across the NEM passed 700 MW in June 2026. That figure, DC Byte's 1.6 GW of operating IT load and my 230 MW measure three different things. Mine is the sum of what operators have published as operational IT. It is a floor, not an estimate, and AEMO's demand figure shows how far under the real load that floor sits.

Seven campuses publish no megawatt figure at all. Three are Digital Realty facilities that give floor area and cooling redundancy but no power number, and four are DCI sites.3333 Sydney Data Center & Colocation, Digital Realty, accessed 23 August 2026.3434 Melbourne Data Center & Colocation, Digital Realty, accessed 23 August 2026. Firmus's Wesley Vale campus came off that list in August, when ABC News reported it at 52 MW.3535 Firmus 288-megawatt AI data centre at Bell Bay receives George Town Council approval, ABC News, 25 August 2026. I record those seven with no capacity and no measure so the inventory still tracks real campuses without public figures.

No campus shows public funding from the Australian Renewable Energy Agency (ARENA) or the Clean Energy Finance Corporation (CEFC). The only register I could check by machine, though, is a data.gov.au file frozen on 21 December 2020, older than almost every campus here.3636 ARENA and CEFC projects, resource arena_cefc_20201221.csv, Department of Climate Change, Energy, the Environment and Water, 21 December 2020. I treat that result as checked but weak.

New South Wales publishes the most megawatts of any grid, and one in seven of them enters a total

Published capacity of each tracked campus by grid, status and measure, megawatts on one scale, 65 campuses, consolidated 31 October 2026Source: Operator pages, ASX filings and NSW planning consents per campus; updated 31 October 2026

Live Building Approved, applied for or announced Outline: a measure that does not add At least

New South Wales and ACT 34 campuses

  1. CDC Kemps Creek Campus (KC1) CDC Data Centres, announced, 1,400 MW on gross facility 1,400 gross
  2. Mamre Road Data Centre Campus Undisclosed (proponent: Plan Project Management for a confidential client), application, 1,000 MW on gross facility 1,000 gross
  3. CDC Marsden Park Campus CDC Data Centres, live, at least 720 MW on built it ≥720
  4. AirTrunk Kurri Kurri Data Centre AirTrunk, application, 550.5 MW on gross facility 550.5 gross
  5. NEXTDC S7 Sydney NEXTDC, announced, at least 550 MW on ultimate ≥550 ultimate
  6. STACK SYD01 Erskine Park STACK Infrastructure, application, 450 MW on gross facility 450 gross
  7. NEXTDC S4 Sydney NEXTDC, construction, 365 MW on built it 365
  8. AirTrunk SYD3 AirTrunk, construction, at least 330 MW on ultimate ≥330 ultimate
  9. CDC Eastern Creek Campus CDC Data Centres, live, at least 280 MW on built it ≥280
  10. Glendenning Road Data Centre (reported AWS) Amazon Web Services (reported; applicant not confirmed), approved, 202.4 MW on gross facility 202.4 gross
  11. Macquarie Engineering & Technology Campus Macquarie Data Centres, announced, 200 MW on built it 200
  12. AirTrunk SYD2 AirTrunk, live, at least 158 MW on gross facility ≥158 gross
  13. AirTrunk SYD1 AirTrunk, live, at least 121 MW on gross facility ≥121 gross
  14. CDC Beard Campus CDC Data Centres, live, at least 110 MW on built it ≥110
  15. Goodman Project Pluto Goodman Group, approved, 100 MW on gross facility 100 gross
  16. Microsoft Honeman Close Data Centre (SYD01) Microsoft, approved, 96 MW on built it 96
  17. Fujitsu Western Sydney Data Centre Fujitsu Australia (sale to Next Capital agreed 20 Jul 2026; completion pending), live, 92 MW on ultimate 92 ultimate
  18. NEXTDC S3 Sydney NEXTDC, live, 80 MW on built it 80
  19. NEXTDC S5 Sydney NEXTDC, announced, 80 MW on built it 80
  20. Goodman SYD01 Artarmon Goodman Group, construction, 61 MW on built it 61
  21. CDC Hume Campus Two CDC Data Centres, live, 51 MW on operational it 51
  22. Macquarie IC3 Super West Macquarie Data Centres, construction, 47 MW on built it 47
  23. CDC Fyshwick Campus CDC Data Centres, live, 45 MW on operational it 45
  24. NEXTDC S2 Sydney NEXTDC, live, 30 MW on operational it 30
  25. CDC Hume Campus One CDC Data Centres, live, 21 MW on operational it 21
  26. Macquarie Park Data Centre Campus (IC2, IC3 East) Macquarie Data Centres, live, 18 MW on operational it 18
  27. NEXTDC S1 Sydney NEXTDC, live, 16 MW on operational it 16
  28. Equinix SY9x Sydney Equinix (Equinix/PGIM xScale joint venture), live, at least 14 MW on operational it ≥14
  29. NEXTDC S6 Sydney NEXTDC, live, 13.5 MW on built it 13.5
  30. DCI CBR01 Jerrabomberra DCI Data Centers, announced, no megawatt figure published Not published
  31. DCI SYD01 Eastern Creek DCI Data Centers, live, no megawatt figure published Not published
  32. DCI SYD02/SYD03 Eastern Creek DCI Data Centers, announced, no megawatt figure published Not published
  33. Digital Realty SYD10 Digital Realty, live, no megawatt figure published Not published
  34. Digital Realty SYD11 Digital Realty, live, no megawatt figure published Not published

Victoria 18 campuses

  1. NEXTDC M5 Melbourne NEXTDC, announced, 1,200 MW on built it 1,200
  2. AirTrunk Mickleham campus (reported) AirTrunk (reported; applicant not named in planning documents), application, at least 1,000 MW on ultimate ≥1,000 ultimate
  3. Keppel Morwell AI campus Keppel, announced, 720 MW on gross facility 720 gross
  4. AirTrunk MEL2 AirTrunk, construction, at least 354 MW on ultimate ≥354 ultimate
  5. CDC Brooklyn Campus CDC Data Centres, live, at least 350 MW on built it ≥350
  6. Zerra DC Campbellfield campus Zerra DC, application, 336 MW on gross facility 336 gross
  7. CDC Laverton Campus CDC Data Centres, construction, at least 300 MW on built it ≥300
  8. AirTrunk MEL1 AirTrunk, live, at least 276 MW on gross facility ≥276 gross
  9. STACK MEL02 Melbourne STACK Infrastructure, live, 252 MW on ultimate 252 ultimate
  10. NEXTDC M3 Melbourne NEXTDC, live, 225 MW on built it 225
  11. STACK MEL01 Melbourne STACK Infrastructure, live, 180 MW on ultimate 180 ultimate
  12. NEXTDC M4 Melbourne NEXTDC, construction, 150 MW on built it 150
  13. NEXTDC M2 Melbourne NEXTDC, live, 120 MW on built it 120
  14. PGIM Truganina campus, building 1 PGIM Real Estate, approved, 80 MW on gross facility 80 gross
  15. Vantage MEL1 Melbourne Vantage Data Centers, construction, 64 MW on built it 64
  16. Fujitsu Noble Park Data Centre Fujitsu Australia (sale to Next Capital agreed 20 Jul 2026; completion pending), live, 28 MW on operational it 28
  17. NEXTDC M1 Melbourne NEXTDC, live, 16 MW on operational it 16
  18. Digital Realty MEL11 Digital Realty, live, no megawatt figure published Not published

Queensland 3 campuses

  1. NEXTDC B2 Brisbane NEXTDC, live, 12 MW on built it 12
  2. NEXTDC GC1 Gold Coast NEXTDC, announced, 6 MW on built it 6
  3. NEXTDC SC2 Sunshine Coast NEXTDC, construction, 6 MW on built it 6

South Australia 2 campuses

  1. DCI ADL01/ADL02 Kidman Park DCI Data Centers, live, 5.4 MW on operational it 5.4
  2. DCI ADL03 Mawson Lakes DCI Data Centers, announced, no megawatt figure published Not published

Tasmania 3 campuses

  1. Firmus Project Southgate Bell Bay (Long Reach) Firmus Technologies, approved, 288 MW on grid connection 288 grid
  2. Firmus Project Southgate Launceston (St Leonards) Firmus Technologies, construction, 104 MW on grid connection 104 grid
  3. Firmus Project Southgate Wesley Vale Firmus Technologies, application, 52 MW on gross facility 52 gross

Western Australia 3 campuses

  1. CDC Maddington Campus CDC Data Centres, construction, at least 200 MW on built it ≥200
  2. NEXTDC P2 Perth NEXTDC, live, at least 20 MW on built it ≥20
  3. NEXTDC P1 Perth NEXTDC, live, at least 10 MW on built it ≥10

Northern Territory 2 campuses

  1. Beetaloo Digital Weddell hyperscale data centre Beetaloo Energy (subsidiary), announced, 2,000 MW on gross facility 2,000 gross
  2. NEXTDC D2 Darwin NEXTDC, construction, 6 MW on built it 6
  1. FY26 Record Results (ASX release), NEXTDC Limited, 27 August 2026.
  2. AirTrunk secures A$4.25B green loan for SYD3 Western Sydney expansion, AirTrunk, 27 October 2026.
  3. AirTrunk expands Australian platform with a second hyperscale data centre campus in Melbourne, AirTrunk, 24 December 2025.
  4. FY26 Results Presentation, NEXTDC Limited, 27 August 2026.
  5. NEXTDC S4 Data Centre Horsley Park (SSD-63741210), NSW Department of Planning, Housing and Infrastructure, 24 December 2025.
  6. Infratil Investor Day 2026: CDC update, Infratil, 16 September 2026.
  7. Infratil Investor Day: CDC update, Infratil, 1 September 2025.
  8. NEXTDC 1H26 Results Announcement (ASX release), NEXTDC Limited, 25 February 2026.
  9. Honeman Close Data Centre (SSD-58601963), NSW Department of Planning, Housing and Infrastructure, 1 October 2026.
  10. Macquarie Technology FY26 results (ASX release), Macquarie Technology Group, 26 August 2026.
  11. Project Southgate Bell Bay: FAQs, Firmus Technologies, 3 July 2026.
  12. KC1 Data Centre, Kemps Creek (SSD-133677993), NSW Department of Planning, Housing and Infrastructure, accessed 31 October 2026.
  13. Mamre Road Data Centre Campus (SSD-92743706), NSW Department of Planning, Housing and Infrastructure, accessed 31 October 2026.
  14. Kurri Kurri Data Centre (SSD-128819490), NSW Department of Planning, Housing and Infrastructure, 14 October 2026.
  15. Keppel secures 720MW powerbank for AI data centre campus near Melbourne, Keppel Ltd, 15 January 2026.
  16. Proposed $40b, 185ha data centre to use six times Top End's annual electricity consumption, ABC News, 22 July 2026.
  17. Australian Data Centre Forecast Report, Issue 2, data at 30 September 2026, Data Centres Australia and DC Byte, 30 October 2026.
  18. 2026 ESOO data centre forecasting overview, AEMO, August 2026.
  19. Sydney Data Center & Colocation, Digital Realty, accessed 23 August 2026.
  20. Melbourne Data Center & Colocation, Digital Realty, accessed 23 August 2026.
  21. Firmus 288-megawatt AI data centre at Bell Bay receives George Town Council approval, ABC News, 25 August 2026.
  22. ARENA and CEFC projects, resource arena_cefc_20201221.csv, Department of Climate Change, Energy, the Environment and Water, 21 December 2020.

Chapter 3. Every proposed megawatt sits below the national share

The test is one rule: most proposed megawatts on grids below the national share, few on grids above it. Every proposed megawatt passes, though the grid that holds the most sits only 1.3 points under the line.

All 2,281 MW of data-centre capacity proposed as built IT sits in regions whose renewable share of generation is below the national share of 44.5% for the year to September 2026. The national share weights each of the seven regions by how much electricity it generates. A simple average of the seven would be 51.1%, and every proposed megawatt sits below that too.11 Open Electricity v4 API, NEM energy by region and fuel technology, October 2025 to September 2026, Open Electricity, 31 October 2026.22 Open Electricity v4 API, WEM energy by fuel technology, October 2025 to September 2026, Open Electricity, 31 October 2026.88 Northern Territory Renewables Report: 30 December 2024 to 28 December 2025, Northern Territory Electricity System and Market Operator, January 2026. Renewable here means hydro, wind, utility solar, rooftop solar and bioenergy. Battery discharge is left out.

The mismatch holds if more than 60% of proposed megawatts sit in regions below the national share and under 20% sit in regions above it. A result of exactly 60% or 20% counts as weaker than expected. A region with no proposed megawatts drops out of the denominator.

Region by region

Victoria now holds the most: 1,414 proposed megawatts on a grid with a renewable share of 43.3%. Most of that is NEXTDC's M5 campus, which the company's FY26 filing puts at up to 1.2 GW of IT capacity.1515 FY26 Record Results (ASX release), NEXTDC Limited, 27 August 2026. New South Wales holds 849 MW at 41.0%, Queensland 12 MW at 36.8%, and the Darwin-Katherine system 6 MW at 19.6%.11 Open Electricity v4 API, NEM energy by region and fuel technology, October 2025 to September 2026, Open Electricity, 31 October 2026.88 Northern Territory Renewables Report: 30 December 2024 to 28 December 2025, Northern Territory Electricity System and Market Operator, January 2026. Three regions have no proposed built-IT megawatts: South Australia at 79.0%, Tasmania at 97.7% and the South West Interconnected System at 40.2%.11 Open Electricity v4 API, NEM energy by region and fuel technology, October 2025 to September 2026, Open Electricity, 31 October 2026.22 Open Electricity v4 API, WEM energy by fuel technology, October 2025 to September 2026, Open Electricity, 31 October 2026. The thresholds were 60% and 20%. The result is 100% and zero.

The verdict holds, but narrowly. The largest block is in Victoria, 1.3 points under the line, while New South Wales sits 3.5 points under it. That 1.3 comes from the unrounded shares, 44.53% nationally against 43.26% in Victoria, though the rounded figures of 44.5% and 43.3% differ by 1.2. Month by month, Victoria was above the national share in 11 of the last 23 months.33 Open Electricity v4 API, monthly energy by region and fuel technology, NEM and WEM, November 2024 to September 2026, Open Electricity, 31 October 2026. The verdict holds for the year I measured and is fragile beyond it.

One contested reading would change the headline number without changing the verdict. If NEXTDC's and AirTrunk's published IT figures are read as distant end states instead of planned builds, the proposed total shrinks and M5 drops out. Every campus either reading counts is in Victoria, New South Wales, Queensland or the Territory, and all four are below the line. I kept the operators' own reading. Built IT means capacity completed or planned to be completed, and the other reading would also strip the operational figure from NEXTDC data centres that are plainly running. The 13,050 MW published on the other measures never enters the count.

Tasmania has the highest renewable share and no proposed built-IT megawatts

Tasmania makes this result look stark, and it is also the one that is moving. It does have campuses, and it is absent from the test only because none of them publishes an IT figure. George Town Council approved Firmus's Bell Bay campus on 25 August 2026 by six votes to one, on a 288 MW grid connection. The approval is under appeal.3535 Firmus 288-megawatt AI data centre at Bell Bay receives George Town Council approval, ABC News, 25 August 2026. Firmus's Launceston campus is under construction on a 104 MW supply contract, and its Wesley Vale campus, reported at 52 MW, is still waiting for approval.3737 Firmus yet to secure full funding for Tasmanian AI data centre project, ABC News, 21 October 2026. The three add up to 444 MW, the request now in front of Hydro Tasmania, and none of the three is an IT measure.

Tasmania holds three Firmus campuses and no proposed megawatts on the IT measure

Tasmania and its Bass Strait islands, generating plants by fuel and tracked campuses by status, as at 31 October 2026Source: AEMO NEM Generation Information July 2026; operator pages, Tasmanian planning records and ABC reporting per campus

Tasmania and its Bass Strait islands
200 km
Numbers identify campus squares whose names do not fit beside the map marks.

Campus squares use the report’s live, construction and proposed marks. Short lines connect separated squares to their recorded locations.

  1. Firmus yet to secure full funding for Tasmanian AI data centre project, ABC News, 21 October 2026.

Chapter 4. Most large campuses say nothing about the power they buy

Operators have published almost nothing about the electricity any single campus buys. Their tenants do buy renewable power, but under contracts that name a generator and never a data centre.

Of the 41 campuses I tracked that publish 50 MW or more on any measure, 34 have no public electricity supply arrangement. Seven do. Not one of the 41 publishes a renewable share or megawatt hours matched for a single campus. When Australian operators disclose renewable matching, they do it for a whole company or a portfolio. CDC does it for the customers inside its portfolio who opt in.

No campus publishes a renewable share for its own load, and every share that is published belongs to a wider boundary

Supply arrangement, instruments, matching period and claim boundary, 41 campuses at or above 50 MW, consolidated 31 October 2026Source: Operator sustainability reports, ASX filings and campus pages; updated 31 October 2026

34 of 41 campuses at or above 50 MW publish no electricity supply arrangement. The 7 that do are below.

41 campuses at or above 50 MW on the measure their operator publishes, and what each one says about where its electricity comes from. 34 of them say nothing.
Campus Operator Grid MW Published supply arrangement
Supply arrangement published 7 of 41
CDC Marsden Park Campus CDC Data Centres NSW ≥ 720 Unbundled certificates Annual matching · Australian operations boundary
CDC Brooklyn Campus CDC Data Centres VIC ≥ 350 Unbundled certificates Annual matching · Australian operations boundary
CDC Eastern Creek Campus CDC Data Centres NSW ≥ 280 Unbundled certificates Annual matching · Australian operations boundary
AirTrunk SYD1 AirTrunk NSW ≥ 121 Virtual PPA and on-site generation Matching period not published · Site boundary
Fujitsu Western Sydney Data Centre Fujitsu Australia (sale to Next Capital agreed 20 Jul 2026; completion pending) NSW 92 Physical PPA Annual matching · Australian operations boundary
Vantage MEL1 Melbourne Vantage Data Centers VIC 64 On-site generation Matching period not published · Site boundary
CDC Hume Campus Two CDC Data Centres NSW 51 Unbundled certificates Annual matching · Australian operations boundary

The megawatt column shows whatever measure each operator published, so read it as context and do not add it up. No campus in this table publishes a renewable share for its own load.

Seven campuses, five kinds of arrangement

Only one instrument has ever been tied to a named Australian campus, and its owner has now untied it. AirTrunk's FY25 Sustainability Report listed SYD1 against a virtual power purchase agreement (VPPA) and 25 MW of solar. That is the Mulwala farm in the Riverina, announced by AirTrunk, Google and OX2 in December 2023 and completed in June 2026.3838 Sustainability Report FY25, AirTrunk, October 2025.3939 Google, AirTrunk and OX2 to add renewable energy capacity in Australia, AirTrunk, 19 December 2023.4040 Google, AirTrunk and European Energy Australia set to launch Mulwala Solar Farm, AirTrunk, 1 June 2026. The FY26 report, released in October, describes the same 25 MW as New South Wales capacity contracted on behalf of customers, and names no site.4141 Sustainability Report FY26, AirTrunk, October 2026. I still record the instrument against SYD1 on the strength of the older report, though the newer one is the better guide. It is Google's purchase, time-matched to Google's consumption, not SYD1's meter.3939 Google, AirTrunk and OX2 to add renewable energy capacity in Australia, AirTrunk, 19 December 2023. Even on the old reading, 25 MW is the nameplate of a solar farm, and SYD1 is a campus of 121 MW and above on the gross-facility measure. Turning one into a share of the other needs load and generation profiles that nobody publishes.1717 AirTrunk expands Australian platform with a second hyperscale data centre campus in Melbourne, AirTrunk, 24 December 2025.

Four CDC campuses share a single instrument. In the Australian Capital Territory, Hume Campus Two sits inside a government scheme that CDC describes as supplying over 97% renewable power. That 97% belongs to the ACT scheme and was not measured at Hume, so I do not credit it to the campus. Everywhere else in Australia, CDC surrenders Large-scale Generation Certificates to the Clean Energy Regulator.4242 Sustainability Report 2026 (AASB S2), CDC Data Centres, 2026. Its FY26 report says 100% of the electricity consumed from the grid in CDC data centres was matched annually with renewable electricity for customers who opt in. Footnote 22 adds that matching does not represent real-time consumption and that the electricity actually consumed can come from non-renewable resources.4242 Sustainability Report 2026 (AASB S2), CDC Data Centres, 2026. The claim covers Eastern Creek, Brooklyn and Marsden Park. I stop it short of Laverton and Maddington, because a matching claim means nothing at a campus with no operating load.4343 CDC Data Centres update, Infratil Investor Day presentation (ASX release), Infratil Limited, 26 March 2026.

Annual matching with certificates adds roughly a tenth to the energy bill. In the September quarter of 2026, certificates traded at about A$7 each, while average wholesale prices ran from A$56 to A$74 per megawatt hour across the mainland regions and Tasmania.4444 Quarterly Energy Dynamics Q3 2026, AEMO, October 2026. The claim those certificates buy covers a year and says nothing about any particular hour.

The other two arrangements are thinner. Vantage says solar panels at MEL1 power non-critical areas such as office space, and gives no capacity, period or share.4545 Melbourne (MEL1) Data Center Campus, Vantage Data Centers, accessed 23 August 2026. Fujitsu signed a ten-year agreement with the Sapphire Wind Farm starting 30 June 2022, covering about 30% of its Australian electricity and about 40% of its New South Wales data-centre load. I record the 30% against the Western Sydney campus, at the boundary of Fujitsu's Australian operations.4646 Fujitsu Australia signs its first power purchase agreement in a key step towards decarbonising its operations and providing lower-emissions services, Fujitsu Australia, 7 April 2022. In July Fujitsu agreed to sell its Australian data centres to Next Capital, and nothing public says whether the wind agreement goes with the buildings.4747 Next Capital agrees to acquire Fujitsu's Australian data centre business, W.Media, 20 July 2026.

The claims that stop at the company boundary

AirTrunk reports that 73% of its electricity was matched with renewable energy in FY26, up from 72% in FY25, while its consumption nearly doubled to 2.63 TWh.4141 Sustainability Report FY26, AirTrunk, October 2026. Inside that figure, the share AirTrunk sources itself fell from 27 points to 18 and the share its customers match rose from 45 points to 55. Three quarters of the matching now belongs to the tenants. The combined figure covers the whole Asia-Pacific and Japan portfolio over a financial year, so it cannot be attached to any one campus. The tenants buy the same way in Australia. Amazon's nine Australian agreements of April 2026 and Microsoft's 150 MW Carwarp solar farm, in service from 12 August, each name a generator and no data centre.4848 Batteries included: Amazon makes record haul of hybrid renewable PPAs to power Australian AI push, RenewEconomy, 16 April 2026.4949 Carwarp Energy Park press release, Recurrent Energy, 12 August 2026.

NEXTDC's FY26 annual report still names no power purchase agreement. It reports more than A$90 million of gross electricity costs, mostly passed through to customers, and lists evaluating renewable procurement as a mitigation it has yet to carry out.5050 Appendix 4E and FY26 Annual Report (ASX release), NEXTDC Limited, 27 August 2026. Its results release says power arrangements are in place across its contracted capacity without naming an instrument. For renewables and firming, the contracted backup that covers the hours when wind and sun fall short, it points to its customers' global procurement.1515 FY26 Record Results (ASX release), NEXTDC Limited, 27 August 2026.

Macquarie Technology's 2026 annual report says its Canberra campus runs on 100% renewable electricity under the ACT initiative, with nothing comparable for Macquarie Park.5151 2026 Annual Report (ASX release), Macquarie Technology Group Limited, 22 October 2026. Goodman's FY26 report puts its own operations at 98% renewable electricity. That boundary leaves out its data-centre customers' load, and the report names no arrangement for SYD01.5252 Goodman Group Annual Report 2026 (ASX release), Goodman Group, 20 August 2026.

The largest contracts sit outside the set

The largest facility-level arrangement I found carries no renewable instrument at all. Hydro Tasmania confirms that in March 2026 Aurora Energy signed a three-year retail agreement for 104 MW at Firmus's Launceston site, backed by a fixed-price Hydro wholesale contract.5353 Hydro Tasmania and Firmus Technologies, Hydro Tasmania, updated 27 October 2026. Hydro has not yet decided on Firmus's request for 444 MW across all three Tasmanian campuses, and expects a decision by the end of 2026. It is weighing two structures. In one, Firmus contracts new wind and solar and Hydro firms it. In the other, Hydro does the contracting. My supply categories have no slot for a retail contract without a renewable claim attached. The Launceston campus is therefore recorded as not public, which understates what is known, and I describe the agreement here instead.

The largest data-centre supply deal disclosed anywhere in Australia is now Firmus's 12-year agreement with Gunvor for 600 MW of firm supply in South Australia, backed by 1.2 GW of new renewables and 1.5 GWh of storage by 2032. One trade outlet reports it, and I could not find a release from either party.5454 Firmus secures 600MW energy agreement to support SA AI factory expansion, W.Media, 30 June 2026. The two campuses it serves, at Tailem Bend and Stirling North, are not in my inventory, so the biggest contract in the country attaches to no campus counted here. Firmus withdrew its share float on 9 October, having already parted from CDC, its partner in the Tasmanian programme.5555 CDC kills off its $73.3 billion data centre rollout deal with Firmus, Startup Daily, 6 October 2026.

When I write not public, I am describing disclosure. It does not mean a campus has no supply arrangement, and it says nothing about the electricity at the meter. Voluntary disclosure may not last. On 5 August the Australian Energy Market Commission (AEMC), which writes the national electricity rules, advised energy ministers that data centres should hold firm contracts for their load and surrender certificates split by time of day.5656 Three major data centre reforms announced on 5 August 2026, King & Wood Mallesons, August 2026. On 20 October it received the federal energy minister's rule change request for the first of those, the firm-contract obligation. That request is separate from the two network-cost requests he lodged in August.5757 Australia proposes firm energy contracting obligation for data centres, W.Media, 28 October 2026. If either proposal becomes law, a campus's power supply stops being something an operator chooses to disclose and becomes something it has to prove.

  1. Sustainability Report FY25, AirTrunk, October 2025.
  2. Google, AirTrunk and OX2 to add renewable energy capacity in Australia, AirTrunk, 19 December 2023.
  3. Google, AirTrunk and European Energy Australia set to launch Mulwala Solar Farm, AirTrunk, 1 June 2026.
  4. Sustainability Report FY26, AirTrunk, October 2026.
  5. Sustainability Report 2026 (AASB S2), CDC Data Centres, 2026.
  6. CDC Data Centres update, Infratil Investor Day presentation (ASX release), Infratil Limited, 26 March 2026.
  7. Quarterly Energy Dynamics Q3 2026, AEMO, October 2026.
  8. Melbourne (MEL1) Data Center Campus, Vantage Data Centers, accessed 23 August 2026.
  9. Fujitsu Australia signs its first power purchase agreement in a key step towards decarbonising its operations and providing lower-emissions services, Fujitsu Australia, 7 April 2022.
  10. Next Capital agrees to acquire Fujitsu's Australian data centre business, W.Media, 20 July 2026.
  11. Batteries included: Amazon makes record haul of hybrid renewable PPAs to power Australian AI push, RenewEconomy, 16 April 2026.
  12. Carwarp Energy Park press release, Recurrent Energy, 12 August 2026.
  13. Appendix 4E and FY26 Annual Report (ASX release), NEXTDC Limited, 27 August 2026.
  14. 2026 Annual Report (ASX release), Macquarie Technology Group Limited, 22 October 2026.
  15. Goodman Group Annual Report 2026 (ASX release), Goodman Group, 20 August 2026.
  16. Hydro Tasmania and Firmus Technologies, Hydro Tasmania, updated 27 October 2026.
  17. Firmus secures 600MW energy agreement to support SA AI factory expansion, W.Media, 30 June 2026.
  18. CDC kills off its $73.3 billion data centre rollout deal with Firmus, Startup Daily, 6 October 2026.
  19. Three major data centre reforms announced on 5 August 2026, King & Wood Mallesons, August 2026.
  20. Australia proposes firm energy contracting obligation for data centres, W.Media, 28 October 2026.

Chapter 5. Western Sydney has no room for new load without new transmission

No network publishes how many megawatts a whole region can take. The only study that works it out covers Western Sydney and finds no room for new data-centre load in 2032/33 without new transmission. About 20 GW is asking to connect.

By headroom I mean the megawatts of new demand a region's network can take. Grid planners separate it from generator hosting capacity, which measures how many megawatts of new solar or wind farms can feed power into a line. Headroom runs the other way: how many megawatts a new factory or data centre can draw from the network around the clock.

Western Sydney has 0.00 GW of capacity for new data-centre load in 2032/33 on the network as currently planned.5858 Studies on augmentation supporting data centre connections in Western Sydney, Transgrid, April 2026. Transgrid, which runs the high-voltage network in New South Wales, published that finding in an April 2026 power-flow study of headroom for one area. A table in the study shows what various fixes would buy. An extra static var compensator, a device that holds voltage steady, lifts headroom to 0.35 GW. Adding 2.6 GW of batteries on top of that brings it to 0.60 GW. Building the Hunter Transmission Project provides between 0.5 and 2 GW, and adding the Sydney Ring South a year later raises headroom to between 2.8 and 3.2 GW.

Against that zero, Transgrid's 2026 planning report puts data-centre load seeking connection in New South Wales at about 20 GW, roughly twice the state's peak demand. Its June update records 1.5 GW already signed and calls Sydney's capacity largely exhausted beyond 2033.5959 2026 Transmission Annual Planning Report, Transgrid, September 2026.6060 Update on network capacity, Transgrid, 17 June 2026. In a 20 August update, Transgrid describes limited remaining capacity and says a network upgrade would unlock up to 2 GW.6161 Sydney basin network capacity update, Transgrid, 20 August 2026. The NSW Government's August consultation paper lists 28 GW sought and 13 GW advanced.6262 Reforming electricity network connections for data centres, consultation paper, NSW Department of Climate Change, Energy, the Environment and Water, August 2026. AEMO counts 22 data centres and 10.1 GW in the transmission queue, with 56% in New South Wales and 35% in Victoria.4444 Quarterly Energy Dynamics Q3 2026, AEMO, October 2026. These figures track different things at different stages. None of them measures load that is certain to connect.

Transgrid's connection enquiries sit on the same ground as the campuses already announced

The Sydney basin, tracked campuses by status and published capacity measure over the generating plants, as at 31 October 2026Source: Transgrid 2026 Transmission Annual Planning Report and Western Sydney augmentation studies; operator pages and NSW planning consents per campus; AEMO NEM Generation Information July 2026

the Sydney basin and its coast
100 km
Numbers identify campus squares whose names do not fit beside the map marks.
1Amazon Web Services Glendenning Road (reported AWS)
2CDC Eastern Creek
3CDC Hume One
4CDC Hume Two
5CDC Kemps Creek (KC1)
6DCI SYD01 Eastern Creek
7Digital Realty SYD10
8Digital Realty SYD11
9Equinix SY9x Sydney
10Goodman Project Pluto
11Goodman SYD01 Artarmon
12Macquarie IC3 Super West
13Macquarie Engineering & Technology
14Macquarie Park (IC2, IC3 East)
15Undisclosed Mamre Road
16NEXTDC S1 Sydney
17NEXTDC S2 Sydney
18NEXTDC S3 Sydney
19NEXTDC S6 Sydney
20NEXTDC S7 Sydney

Campus squares use the report’s live, construction and proposed marks. Short lines connect separated squares to their recorded locations.

No region outside Western Sydney publishes headroom

Transgrid's 2026 report goes further than any network plan I have read. Its Figure 1.6 sorts locations into bands of large-load hosting capacity. Dumaresq, the Hunter, Wallerawang, Marulan and Canberra are in the 0.5 to 1 GW band. Newcastle, Yass and Wagga are in the 1 to 2 GW band. Sydney reaches up to 2 GW only with future works.5959 2026 Transmission Annual Planning Report, Transgrid, September 2026. The report warns that the bands are not necessarily cumulative, so they do not give a statewide figure. Summing the bands would count shared lines twice.

The other six regions publish nothing like it. I went through Powerlink's 2025 report, VicGrid's 2025 material, ElectraNet's 2026 report, TasNetworks' planning pages, Western Power's draft Transmission System Plan and Power and Water's Darwin-Katherine plan. Powerlink, TasNetworks and VicGrid had not released a 2026 report by the end of October, and Western Power's plan is still a draft. All six cover constraints, connection opportunities or substation capacity. None gives the megawatts of load a region can accept.6363 Transmission Annual Planning Report 2025, Powerlink Queensland, December 2025.6464 2025 Victorian Annual Planning Report, VicGrid, 2025.6565 2026 Transmission Annual Planning Report, ElectraNet, 2026.6666 Planning our network, TasNetworks, accessed 23 August 2026.6767 Transmission System Plan 2025 (Draft), Western Power, March 2026.6868 Darwin-Katherine Electricity System Plan, Power and Water Corporation, accessed 23 August 2026. A hosting figure for generators, a rating at one substation and a constraint map do not amount to a headroom figure for load. Outside Western Sydney, no network has published the study that would produce one.

Western Sydney has no room for new data-centre load in 2032/33 unless someone pays for new transmission, and the queue for it runs to tens of gigawatts. What still cannot be said is how many megawatts any region can take by 2030.

  1. Studies on augmentation supporting data centre connections in Western Sydney, Transgrid, April 2026.
  2. 2026 Transmission Annual Planning Report, Transgrid, September 2026.
  3. Update on network capacity, Transgrid, 17 June 2026.
  4. Sydney basin network capacity update, Transgrid, 20 August 2026.
  5. Reforming electricity network connections for data centres, consultation paper, NSW Department of Climate Change, Energy, the Environment and Water, August 2026.
  6. Transmission Annual Planning Report 2025, Powerlink Queensland, December 2025.
  7. 2025 Victorian Annual Planning Report, VicGrid, 2025.
  8. 2026 Transmission Annual Planning Report, ElectraNet, 2026.
  9. Planning our network, TasNetworks, accessed 23 August 2026.
  10. Transmission System Plan 2025 (Draft), Western Power, March 2026.
  11. Darwin-Katherine Electricity System Plan, Power and Water Corporation, accessed 23 August 2026.

Chapter 6. The rules arrive after the load

Between March and October 2026, every government that wrote rules for data centres asked them to bring new renewable supply to the grid they sit on. None of those rules is law yet. The national rule is not meant to reach projects already approved, and the two jurisdictions that burn the most fossil fuel refused it.

The rules in this chapter are for the next pipeline, not the one this report measures. On 26 August 2026 National Cabinet agreed to consistent mandatory standards for data-centre energy, water and land use, which the Commonwealth is to legislate in early 2027.6969 Meeting of National Cabinet, Prime Minister of Australia, 26 August 2026. The Prime Minister had already said in July that the obligation would not be retrospective. The ABC has counted 27 data centres approved but not yet built, with at least 3.38 GW between them on whatever measure each one published, and the standards as described would not reach any of them.7070 The bigger, hungrier AI data centres set to escape looming water and power restrictions, ABC News, 11 September 2026. Most of the campuses in my inventory are live, under construction or already approved, so those standards would not reach them either.

Every written rule asks for new supply on the same grid

On 28 July the energy ministers, except those from Queensland and the Northern Territory, agreed to mandate that data centres offset their electricity demand by investing in additional renewable generation in the jurisdiction where they sit, including through guarantee-of-origin certificates.7171 Power struggle: data centre energy rules spark concerns, RenewEconomy, 29 July 2026. The AEMC's advice of 5 August turned that into four proposals. Data centres would surrender certificates split by time of day and tied to new generation, and they would hold firm contracts for their load. They would also register with AEMO and sign flexible connection agreements. The AEMC allowed 12 to 36 months to implement the proposals once ministers endorse them.5656 Three major data centre reforms announced on 5 August 2026, King & Wood Mallesons, August 2026. I could not retrieve the AEMC's own documents, so these terms rest on law-firm and trade summaries that quote them.

New South Wales wrote the most detailed version. Its guidelines of 17 August are voluntary, and a campus that follows them gets assessed in 75 days.7272 NSW Data Centre Guidelines, NSW Government, August 2026. To qualify, a campus must contract with additional New South Wales generation that has not yet reached its investment decision, so the campus brings the plant into being. The guidelines require at least 40% of that generation to be wind, plus four hours of storage sized at a quarter of the campus's megawatts. The contracts must match the campus's annual average demand from its fourth year and run for ten years or more. The campus also has to keep a quarter of its average demand ready to switch off for two hours without starting diesel generators.

Victoria's action plan of 22 September asks new campuses to offset their consumption with new renewables and storage, and to pay for the network upgrades they trigger. It does not apply to projects already built, under construction or assessed.7373 Victoria targets grid costs and water use in new data centre action plan, W.Media, 23 September 2026.7474 Data centre development focus: the evolving regulatory landscape across Australia, Johnson Winter Slattery, 1 October 2026. Tasmania's draft expectations of 7 September ask proponents to bring on additional Tasmanian generation, with Hydro Tasmania firming it on commercial terms. The state calls them non-statutory.7575 Draft Expectations for Data Centres and AI Infrastructure Developers, Tasmanian Government, September 2026.

Set beside chapter three, these rules accept where the data centres are going and make no attempt to change it. Not one of them steers load towards South Australia or Tasmania. Each asks the load to build new supply on the grid it has already chosen. In New South Wales and Victoria, those grids took 56.1% and 53.5% of their generation from coal in the year to September.11 Open Electricity v4 API, NEM energy by region and fuel technology, October 2025 to September 2026, Open Electricity, 31 October 2026.

The split along coal and gas

Queensland and the Northern Territory, the two jurisdictions with the most fossil generation in their grids, refused the July mandate. At National Cabinet the statement dropped the word renewables, and both jurisdictions claimed flexibility over their energy mix.7676 Queensland's satisfaction suggests Albanese may have caved on renewables-only approach for data centres, RenewEconomy, 26 August 2026.6969 Meeting of National Cabinet, Prime Minister of Australia, 26 August 2026. The Commonwealth's consultation paper followed in September. It proposes tiers by connection capacity, exempting campuses under 30 MW and putting the heaviest obligations on those above 100 MW, while letting gas, batteries or hydro firm the renewable offset.7777 AI companies would need to report 'rogue' incidents under proposed national standards, ABC News, 18 September 2026.7878 Regulation of data centres and AI training: the Commonwealth asks the hard questions, Clayton Utz, September 2026.

The federal energy minister said in August that a data centre proposed to run only on gas will not meet the national standards.7979 Bowen says gas-only NT data centres will not meet new rules, NT Independent, 5 August 2026. Since then the Northern Territory has granted land at Weddell to a 2 GW campus that Beetaloo Digital says would run on its own gas power station.3030 Proposed $40b, 185ha data centre to use six times Top End's annual electricity consumption, ABC News, 22 July 2026. Queensland took 57.3% of its generation from coal in the year to September.11 Open Electricity v4 API, NEM energy by region and fuel technology, October 2025 to September 2026, Open Electricity, 31 October 2026. It has written no data-centre rules of its own and has barred commercial data centres from State strategic project status.8080 State Development and Public Works Organisation (Critical Minerals) and Other Legislation Amendment Act 2026 (Act No. 19 of 2026), Queensland Legislation, 3 September 2026.

A price on location

New South Wales is the only government proposing to charge more for building in crowded places. Western Australia charges a flat A$100,000 per megawatt on every new transmission connection of 10 MW or more, wherever it is.8181 Capital Charges Scheme Consultation Paper: Impact on Connections to Existing Transmission Infrastructure, Energy Policy WA, 18 August 2026. The August consultation paper from New South Wales proposes a network upgrade fee of A$200,000 per megawatt inside the Sydney, Newcastle and Wollongong load centre and A$100,000 elsewhere, plus an entry bond of A$30,000 per megawatt, with regulation starting at 15 MW.6262 Reforming electricity network connections for data centres, consultation paper, NSW Department of Climate Change, Energy, the Environment and Water, August 2026. A bill introduced on 5 August, still before the upper house in October, would let the minister ration access to large-load areas.7474 Data centre development focus: the evolving regulatory landscape across Australia, Johnson Winter Slattery, 1 October 2026. The same government's Investment Delivery Authority has fast-tracked 15 data-centre projects worth A$51.89 billion, and every one of them is in metropolitan Sydney.8282 Projects supported by the Investment Delivery Authority, NSW Government, accessed 31 October 2026.

What the rules leave out

Two gaps sit behind these proposals. The first is the Safeguard Mechanism, the country's main instrument for industrial emissions. It covers only facilities with more than 100,000 tonnes of direct emissions a year. Because a grid-powered data centre's emissions are almost all indirect, the mechanism does not reach it.8383 Safeguard Mechanism, Clean Energy Regulator, accessed 31 October 2026. The second is information. On 5 August the federal energy minister lodged two rule-change requests that would make data centres pay for the network upgrades they trigger and require networks to publish their data-centre connection pipelines. Publishing those pipelines would give each network its first public queue figure.5656 Three major data centre reforms announced on 5 August 2026, King & Wood Mallesons, August 2026. Those two requests are separate from his firm-contract request, which the AEMC received on 20 October.5757 Australia proposes firm energy contracting obligation for data centres, W.Media, 28 October 2026. Until one of them becomes a rule, the load, the rules and the headroom stay in three separate sets of documents that nobody is required to reconcile.

  1. Meeting of National Cabinet, Prime Minister of Australia, 26 August 2026.
  2. The bigger, hungrier AI data centres set to escape looming water and power restrictions, ABC News, 11 September 2026.
  3. Power struggle: data centre energy rules spark concerns, RenewEconomy, 29 July 2026.
  4. NSW Data Centre Guidelines, NSW Government, August 2026.
  5. Victoria targets grid costs and water use in new data centre action plan, W.Media, 23 September 2026.
  6. Data centre development focus: the evolving regulatory landscape across Australia, Johnson Winter Slattery, 1 October 2026.
  7. Draft Expectations for Data Centres and AI Infrastructure Developers, Tasmanian Government, September 2026.
  8. Queensland's satisfaction suggests Albanese may have caved on renewables-only approach for data centres, RenewEconomy, 26 August 2026.
  9. AI companies would need to report 'rogue' incidents under proposed national standards, ABC News, 18 September 2026.
  10. Regulation of data centres and AI training: the Commonwealth asks the hard questions, Clayton Utz, September 2026.
  11. Bowen says gas-only NT data centres will not meet new rules, NT Independent, 5 August 2026.
  12. State Development and Public Works Organisation (Critical Minerals) and Other Legislation Amendment Act 2026 (Act No. 19 of 2026), Queensland Legislation, 3 September 2026.
  13. Capital Charges Scheme Consultation Paper: Impact on Connections to Existing Transmission Infrastructure, Energy Policy WA, 18 August 2026.
  14. Projects supported by the Investment Delivery Authority, NSW Government, accessed 31 October 2026.
  15. Safeguard Mechanism, Clean Energy Regulator, accessed 31 October 2026.

Chapter 7. Cables do not decide where the campuses go

Laid over the campus inventory, the undersea cable landings coincide with the proposed load in only one city, Sydney. Six of the eight announced systems land there too.

Sixteen submarine cable systems land in Australia and are in service.8484 International submarine cables landing in Australia, Australian Communications and Media Authority, updated 17 September 2026. Fifteen are international; the sixteenth is SMAP, a domestic system joining Perth, Adelaide, Melbourne and Sydney. Eight more have been announced with a service year published by their owner. Another five have no owner year, and I leave them off the list. The list counts systems, not traffic. No owner publishes how much data each landing carries, so I cannot say how much of Australia's international bandwidth passes through any one station.

Two of the sixteen in-service systems were carrying no traffic on 31 October. INDIGO-West has been down since early August and the Australia-Singapore Cable since 4 September, with repairs to both scheduled to run into November. That left the Oman Australia Cable as Perth's only working international link.8585 AARNet says Perth-Singapore cable repairs will run into mid November, Best Effort, 26 October 2026.

Sydney takes six of the eight announced systems

Submarine cable systems landing in Australia by landfall, status and service year, 24 systems including the domestic SMAP, as at 31 October 2026Source: ACMA landing list and May 2026 map, owner and consortium releases and ASX filings per system; updated 31 October 2026

In service Announced, owner-published year Domestic system Year has slipped One system, several shores

  1. Sydney 11 in service · 6 announced

    Announced: Honomoana 2026, Tabua 2026, Hawaiki Nui 1 2027, APX East 2028, SX Tasman Express 2028, APX North 2029

  2. Sunshine Coast 1 in service · 1 announced

    Announced: Tabua 2026

  3. Melbourne and Geelong 1 in service · 1 announced

    Announced: Honomoana 2026

  4. Adelaide 1 in service · 0 announced

  5. Perth 4 in service · 1 announced

    Announced: APX West 2029

  6. Port Hedland 2 in service · 0 announced

  7. Darwin 2 in service · 2 announced

    Announced: Hawaiki Nui 1 2027, Asia Connect Cable System (ACC-1) 2029

2000 2005 2010 2015 2020 2025 2030 Today Sydney 11 in service · 6 announced Sunshine Coast 1 in service · 1 announced Melbourne and Geelong 1 in service · 1 announced Adelaide 1 in service · 0 announced Perth 4 in service · 1 announced Port Hedland 2 in service · 0 announced Darwin 2 in service · 2 announced Southern Cross Cable Network · in service 2000 · Brookvale cable landing station; Alexandria cable landing station Southern Cross Cable Network Australia-Japan Cable · in service 2001 · Oxford Falls cable station; Paddington cable station Australia-Japan Cable Gondwana-1 · in service 2008 · Brookvale cable landing station Gondwana-1 Telstra Endeavour · in service 2008 · Paddington cable station Telstra Endeavour PIPE Pacific Cable-1 (PPC-1) · in service 2009 · Cromer cable landing station PIPE Pacific Cable-1 (PPC-1) Tasman Global Access · in service 2017 · Oxford Falls cable station Tasman Global Access Hawaiki · in service 2018 · Equinix SY4 cable landing station Hawaiki Coral Sea Cable System · in service 2020 · Paddington cable station Coral Sea Cable System Japan-Guam-Australia South (JGA-South) · in service 2020 · Brookvale cable landing station Japan-Guam-Australia South (JGA-South) Southern Cross NEXT · in service 2022 · Equinix SY5 cable station Southern Cross NEXT Honomoana · announced 2026 · Equinix Australia Honomoana cable landing station Honomoana SMAP · domestic · in service 2026 · SMAP Sydney cable landing station SMAP Tabua · announced 2026 · Tabua Maroubra cable landing station Tabua Hawaiki Nui 1 · announced 2027 (was 2026) · Unconfirmed Hawaiki Nui Sydney cable landing station Hawaiki Nui 1 APX East · announced 2028 · Equinix SY5 cable station APX East SX Tasman Express · announced 2028 · Unconfirmed SX Tasman Express Sydney cable landing station SX Tasman Express APX North · announced 2029 · Unconfirmed APX North Sydney cable landing station APX North Japan-Guam-Australia South (JGA-South) · in service 2020 · NEXTDC SC1 Sunshine Coast cable landing station Japan-Guam-Australia South (JGA-South) Tabua · announced 2026 · NEXTDC SC1 Sunshine Coast cable landing station Tabua Honomoana · announced 2026 · Barramundi Services Honomoana cable landing station Honomoana SMAP · domestic · in service 2026 · SMAP Torquay West cable landing station SMAP SMAP · domestic · in service 2026 · SMAP Adelaide cable landing station SMAP Australia-Singapore Cable · in service 2018 · Shenton Park cable landing station (Equinix PE2) Australia-Singapore Cable INDIGO-West · in service 2019 · Shenton Park cable landing station (Equinix PE2) INDIGO-West Oman Australia Cable · in service 2022 · Shenton Park cable landing station (Equinix PE2) Oman Australia Cable SMAP · domestic · in service 2026 · SMAP Perth cable landing station; SMAP Garden Island cable landing station SMAP APX West · announced 2029 · Unconfirmed APX West Perth cable landing station APX West Darwin-Jakarta-Singapore Cable · in service 2023 · Port Hedland cable landing station Darwin-Jakarta-Singapore Cable Timor-Leste South Submarine Cable · in service 2026 · Port Hedland cable landing station Timor-Leste South Submarine Cable Darwin-Jakarta-Singapore Cable · in service 2023 · Mindil Beach cable landing station Darwin-Jakarta-Singapore Cable Timor-Leste South Submarine Cable · in service 2026 · Mindil Beach cable landing station Timor-Leste South Submarine Cable Hawaiki Nui 1 · announced 2027 (was 2026) · Unconfirmed Hawaiki Nui Darwin cable landing station Hawaiki Nui 1 Asia Connect Cable System (ACC-1) · announced 2029 (was 2025) · Darwin One open cable landing station Asia Connect Cable System (ACC-1)
  • Asia Connect Cable System (ACC-1): announced for 2029, previously 2025; lands at Darwin One open cable landing station.
  • APX East: announced for 2028; lands at Equinix SY5 cable station.
  • APX North: announced for 2029; lands at Unconfirmed APX North Sydney cable landing station.
  • APX West: announced for 2029; lands at Unconfirmed APX West Perth cable landing station.
  • Australia-Japan Cable: in service 2001; lands at Oxford Falls cable station; Paddington cable station.
  • Australia-Singapore Cable: in service 2018; lands at Shenton Park cable landing station (Equinix PE2).
  • Coral Sea Cable System: in service 2020; lands at Paddington cable station.
  • Darwin-Jakarta-Singapore Cable: in service 2023; lands at Mindil Beach cable landing station; Port Hedland cable landing station.
  • Gondwana-1: in service 2008; lands at Brookvale cable landing station.
  • Hawaiki: in service 2018; lands at Equinix SY4 cable landing station.
  • Hawaiki Nui 1: announced for 2027, previously 2026; lands at Unconfirmed Hawaiki Nui Sydney cable landing station; Unconfirmed Hawaiki Nui Darwin cable landing station.
  • Honomoana: announced for 2026; lands at Equinix Australia Honomoana cable landing station; Barramundi Services Honomoana cable landing station.
  • INDIGO-West: in service 2019; lands at Shenton Park cable landing station (Equinix PE2).
  • Japan-Guam-Australia South (JGA-South): in service 2020; lands at Brookvale cable landing station; NEXTDC SC1 Sunshine Coast cable landing station.
  • Oman Australia Cable: in service 2022; lands at Shenton Park cable landing station (Equinix PE2).
  • PIPE Pacific Cable-1 (PPC-1): in service 2009; lands at Cromer cable landing station.
  • SMAP: domestic, in service 2026; lands at SMAP Perth cable landing station; SMAP Garden Island cable landing station; SMAP Adelaide cable landing station; SMAP Torquay West cable landing station; SMAP Sydney cable landing station.
  • Southern Cross Cable Network: in service 2000; lands at Brookvale cable landing station; Alexandria cable landing station.
  • Southern Cross NEXT: in service 2022; lands at Equinix SY5 cable station.
  • SX Tasman Express: announced for 2028; lands at Unconfirmed SX Tasman Express Sydney cable landing station.
  • Tabua: announced for 2026; lands at NEXTDC SC1 Sunshine Coast cable landing station; Tabua Maroubra cable landing station.
  • Tasman Global Access: in service 2017; lands at Oxford Falls cable station.
  • Telstra Endeavour: in service 2008; lands at Paddington cable station.
  • Timor-Leste South Submarine Cable: in service 2026; lands at Mindil Beach cable landing station; Port Hedland cable landing station.

The list grew by two in September. SUBCO announced APX North, from Sydney to Guam and Japan, and APX West, from Perth to Singapore with branches to Jakarta and Batam, targeting completion of both in 2029.8686 SUBCO announces three new subsea cables to meet surging AI demand, SUBCO, 22 September 2026. In the same month APX East reached contract in force, the stage when a cable's construction contract takes effect. Its Sydney landing is confirmed at Equinix SY5, manufacturing is under way, and the first segment is due to be laid out of Sydney in August 2027.8787 APX East reaches Contract in Force, SUBCO, 24 September 2026. Earlier, on 28 July, the Timor-Leste South system entered commercial service.8888 Timor-Leste launches commercial operations of submarine cable to boost digital connectivity, Tatoli, 28 July 2026. My baseline is still the landing list kept by the Australian Communications and Media Authority (ACMA), with its May 2026 map. Every service year here comes from an owner, a consortium, a filing or a government release.8484 International submarine cables landing in Australia, Australian Communications and Media Authority, updated 17 September 2026.

Fewer places qualify as international gateways than the map suggests. ACMA's map, updated on 17 September 2026, marks mainland landings at Sydney, Perth, Mandurah, the Sunshine Coast, Melbourne, Adelaide, Port Hedland and Darwin, along with two protection zones, both in Sydney. Only four of those clusters have a confirmed international landfall: Sydney, Perth, the Sunshine Coast and Darwin.8484 International submarine cables landing in Australia, Australian Communications and Media Authority, updated 17 September 2026. Port Hedland has no international shore-end of its own; it is a terminus of Vocus's North-West Cable System, which is how the Darwin-Jakarta-Singapore Cable reaches it.8989 ESG Annual Report FY23, Vocus, 30 November 2023. Melbourne and Geelong have two station records between them and no live international landing. One is SMAP's Torquay West station, which belongs to a domestic system.9090 SUBCO announces SMAP hypercable ready for service, SUBCO, 25 June 2026. The other is Honomoana, which is announced but not in service; its owner names Melbourne and Sydney as its Australian landings.9191 Vocus and Google sign contracts to deliver Pacific Connect, Vocus, 30 April 2024. Darwin gained a second planned station site in October, when Google lodged an application at Fannie Bay, across from the open landing station Inligo is building for ACC-1.9292 Darwin could host multiple international subsea cables, ABC News, 7 October 2026.

Announced years move

When an announced year slips, I keep both the old year and the new one. Hawaiki Nui 1 moved from an owner target of 2026 to 2027 for its Sydney to Darwin and Darwin to Singapore route. I could find no public construction or supply contract behind that year.9393 BW Digital and Telin join forces to build Hawaiki Nui 1, BW Digital, 14 May 2024. ACC-1 has moved further, from late 2025 to a 2029 landing at its purpose-built Darwin station, and TeleGeography's analyst puts it at 2029 or 2030.9494 South Australia's digital future: data centres, energy precincts and the cable systems, Inligo Networks, 10 August 2026.9292 Darwin could host multiple international subsea cables, ABC News, 7 October 2026.

Two more owner years are at risk. Tabua has landed at the Sunshine Coast and at Maroubra, and its owner still targets 2026. Honomoana has the same target with no landing on record, and I read that year only in search excerpts, not on an owner page. I will move both if no service announcement arrives by 31 December.9595 Google subsea cable reaches Sydney, RCR Wireless, 3 February 2026. An announced year is a statement of intent from the party that benefits from making it. These slips are the only public evidence of how far that intent runs ahead of the work.

Two systems a reader might look for are gone. ACMA's August list recorded SEA-ME-WE 3 as decommissioned in December 2024, and the September map no longer shows it. The Perth protection zone declared in 2007 for a single cable off City Beach is still in force.8484 International submarine cables landing in Australia, Australian Communications and Media Authority, updated 17 September 2026.9696 Zone to protect Perth submarine cables, Australian Communications and Media Authority, updated 17 September 2026. PNG DataCo decommissioned APNG-2, the Sydney to Papua New Guinea system, in February 2021, after 16 years of service.9797 APNG 2 Submarine Cable Decommissioned, Submarine Telecoms Forum, 15 February 2021.

Where the landings and the campuses sit

Sydney has 13 of the 25 Australian landing stations on record and 11 of the live systems.8484 International submarine cables landing in Australia, Australian Communications and Media Authority, updated 17 September 2026. New South Wales has 34 of the 65 tracked campuses and 849 MW of proposed built-IT capacity. Victoria now leads on that measure, with 1,414 MW from three of its 18 campuses, 1,200 MW of it at NEXTDC's M5. It has no live international landing at all. Perth is the reverse case. Three live international systems land at Shenton Park, and SMAP adds two more stations there. Yet the three Western Australian campuses publish only floors, stated as at least so many megawatts, so the state contributes nothing to the IT totals. Queensland has 12 MW of proposed built-IT capacity and the Northern Territory has 6 MW; each sits beside a working gateway.

Sydney holds 13 of the 25 station records and most of the campuses

The Sydney basin, cable landing stations and routes with the tracked campuses, as at 31 October 2026Source: ACMA landing list and May 2026 map; owner releases per system; the campus inventory

the Sydney basin and its coast
100 km
Numbers identify campus squares whose names do not fit beside the map marks.
1Amazon Web Services Glendenning Road (reported AWS)
2CDC Eastern Creek
3CDC Hume One
4CDC Hume Two
5CDC Kemps Creek (KC1)
6DCI SYD01 Eastern Creek
7Digital Realty SYD10
8Digital Realty SYD11
9Equinix SY9x Sydney
10Goodman Project Pluto
11Goodman SYD01 Artarmon
12Macquarie IC3 Super West
13Macquarie Engineering & Technology
14Macquarie Park (IC2, IC3 East)
15Undisclosed Mamre Road
16NEXTDC S1 Sydney
17NEXTDC S2 Sydney
18NEXTDC S3 Sydney
19NEXTDC S6 Sydney
20NEXTDC S7 Sydney

Campus squares use the report’s live, construction and proposed marks. Short lines connect separated squares to their recorded locations.

The international landings cluster in four places, and the largest proposed campus is in none of them

Cable landing stations and tracked data-centre campuses, Australia, as at 31 October 2026Source: ACMA landing list and May 2026 map, owner releases per system, and the campus inventory; updated 31 October 2026

500 km

Campus squares use the report’s live, construction and proposed marks. Short lines connect separated squares to their recorded locations.

Put the two layers together and Sydney is the only place where the landings and the load coincide. Melbourne has the largest proposed built-IT total and no live international landing. Perth has three live systems, two of them out of service this quarter, and no built-IT megawatts. If cables decided where data centres went, the map would not look like this.

The cable map is no help with the proposal in the next chapter, which turns the question around. A machine that makes its own power in open water needs no cable landing, although satellite capacity, latency, licensing and redundancy would still constrain it.

  1. International submarine cables landing in Australia, Australian Communications and Media Authority, updated 17 September 2026.
  2. AARNet says Perth-Singapore cable repairs will run into mid November, Best Effort, 26 October 2026.
  3. SUBCO announces three new subsea cables to meet surging AI demand, SUBCO, 22 September 2026.
  4. APX East reaches Contract in Force, SUBCO, 24 September 2026.
  5. Timor-Leste launches commercial operations of submarine cable to boost digital connectivity, Tatoli, 28 July 2026.
  6. ESG Annual Report FY23, Vocus, 30 November 2023.
  7. SUBCO announces SMAP hypercable ready for service, SUBCO, 25 June 2026.
  8. Vocus and Google sign contracts to deliver Pacific Connect, Vocus, 30 April 2024.
  9. Darwin could host multiple international subsea cables, ABC News, 7 October 2026.
  10. BW Digital and Telin join forces to build Hawaiki Nui 1, BW Digital, 14 May 2024.
  11. South Australia's digital future: data centres, energy precincts and the cable systems, Inligo Networks, 10 August 2026.
  12. Google subsea cable reaches Sydney, RCR Wireless, 3 February 2026.
  13. Zone to protect Perth submarine cables, Australian Communications and Media Authority, updated 17 September 2026.
  14. APNG 2 Submarine Cable Decommissioned, Submarine Telecoms Forum, 15 February 2021.

Chapter 8. Panthalassa's factory runs into the same grid

A floating data centre that makes its own electricity at sea avoids every problem in earlier chapters, until someone has to build it. I screened 23 factory sites and ended where the report began, at grid power. The top site now shares its substation with a data centre.

Panthalassa is a start-up whose idea turns the rest of this report around. It wants to float wave-powered data centres out to where the energy is, rather than building power for them on land. Each floating unit, which the company calls a node, makes its own electricity at sea. The factory that builds them still needs a berth, a hall, a workforce and a grid connection on land.

Eight of the 23 Australian coastal sites I screened for that factory clear all five gates. Nine fail a named gate. Six are unknown, five of them on the electricity gate. This is a desk screen of public documents; it sorts the candidates without certifying any of them.

The node itself is public in outline, though most of the numbers a factory would need are private. An April 2026 Core Memory interview with the chief executive compares the node to a giant lollipop, about 20 metres across the top and reaching about 80 metres down into the water. It steers itself, travels about 30 miles a day in the interview's own unit, and sends the results from its GPUs and TPUs through Starlink.9898 The Very Wild, Very Real Plan To Build AI Data Centers In The Ocean, EP 65 Garth Sheldon-Coulson, Core Memory, 15 April 2026. Since then the chief executive has put ranges on the record: tops 10 to 30 metres across and draughts of 70 to 100 metres. Each node carries 200 kW to 1 MW of compute, with an optimum near 400 kW, and is towed out horizontal and flipped upright offshore.9999 Building inference data centers on the high seas, Latitude Media, 28 May 2026. He has also said the factories will sit near the regions where the wave energy is best, and he singles out the Southern Hemisphere's waves. That is the strongest public support so far for the premise of this screen, although the company has not named an Australian site or partner.9999 Building inference data centers on the high seas, Latitude Media, 28 May 2026.

In May the company announced a US$140 million Series B, with Anthony Pratt and Fortescue Ventures among the backers.100100 Panthalassa raises $140 million to power AI, Renewable Energy Magazine, 8 May 2026. A further round of about US$225 million, at a valuation near US$2 billion, was reported in August.101101 Ocean-powered AI data center startup Panthalassa is reportedly raising $225M at nearly $2 billion valuation, Tech Startups, 6 August 2026. Naver, the Korean internet company, announced an investment that month without giving the amount.102102 Naver Invests in Panthalassa, a Startup Developing AI Data Centers Powered by Wave Energy, Edaily, 13 August 2026. In November OPB put the company's total for the year at more than US$300 million. If that is right, the second round has closed at least in part.103103 Vancouver gets a factory for floating wave-energy data centers, Oregon Public Broadcasting, 7 November 2026.

Neither the weight of a node nor any factory specification is published, so I wrote my own design brief. Its three cases pair an assembly weight of 3,000 to 5,000 tonnes with a factory connection of 50 to 150 MW. The brief also specifies water at least 120 metres deep for the flip, a hall of 120 by 30 by 20 metres and a workforce of 1,000 to 3,000. Every one of those is my assumption, not the company's. One can at least be checked: the published maximum draught of 100 metres fits inside the 120 metre flip assumption. That 50 to 150 MW is a factory grid connection on shore, separate from the data-centre totals elsewhere in this report.

The company's first assembly line now gives a second check, and it is far smaller than my brief. On 6 November Panthalassa cut the ribbon on an assembly line at Vancouver, Washington, in a warehouse on the Columbia River that was part of the Kaiser Shipyard, a Second World War yard. About 50 people will work there once it is fully staffed, rolling plate steel and welding nodes with robots. That is a twentieth of the smallest workforce in my brief. The company has published neither the floor area nor the grid connection, so the hall and load assumptions stay untested.103103 Vancouver gets a factory for floating wave-energy data centers, Oregon Public Broadcasting, 7 November 2026. It sits across the river from the company's Portland base. In May the chief executive said the company would not tend to put factories on the coast of North America.9999 Building inference data centers on the high seas, Latitude Media, 28 May 2026. OPB reports that the aim in Vancouver is a blueprint for node factories around the world.103103 Vancouver gets a factory for floating wave-energy data centers, Oregon Public Broadcasting, 7 November 2026. So I have left the workforce gate as it was, because 50 people on a first line say little about a plant built to supply a fleet.

The factory is an ordinary load

Up to here, this report has measured data centres against the grid each one sits on. A node goes the other way: it makes its own electricity in open water, takes no grid connection where it operates and needs no cable landing, which is what the company means by going where the energy is.104104 Panthalassa, company site (Go where the energy is), accessed 2 September 2026. The factory stays on shore, where it is an ordinary load on an ordinary network.

The five gates test flip depth, quay, hall, electrical load and workforce. I judged them to a desk-screen standard, which is looser than diligence. A pass means a primary source documents the attribute today. A remediable grade means named work, with a public cost reference, would close the gap by 2030. A fail needs two independent sources showing the requirement cannot be met at that site inside the window. Unknown means no public source addresses the attribute either way. Real diligence would still have to supply engineering drawings, a modelled tow, connection studies at 50, 100 and 150 MW, and a workforce model.

The load gate, not the sea, removes most of the candidate sites

Screened sites by gate outcome under the desk-screen standard, count of sites, 23 candidates as at 31 October 2026Source: Port authority, network planning and marine park documents per gate, with Western Power, Transgrid, Powerlink and TasNetworks planning reports

  • Screened Coastal candidates 23 sites
  • Clear every gate Go on to the weighted scoring 8 sites
  • Electrical load gate Fails: Albany, Bunbury, Esperance, Fremantle Inner HarbourNot known: Civmec Tomago/Newcastle, Hobart/Prince of Wales Bay, Mackay/Hay Point, Port Kembla, Portland 9 sites · 4 fail, 5 not known
  • Node hall gate Fails: Australian Maritime College, Launceston, Melbourne Victoria Dock, Osborne and Port AdelaideNot known: Eden 4 sites · 3 fail, 1 not known
  • Flip depth gate Fails: Karratha and Port of Dampier, Whyalla 2 sites · fail

8 sites clear every gate and 15 do not. A fail means two sources show the site cannot meet the requirement. Not known means no public document settles it, so the site is set aside without a finding against it.

Three strong waterfronts fall on the network

Port Kembla, Civmec Tomago and Bunbury all have water deep enough for the flip within tow range, and none has a marine problem. All three fall on network documents. Tomago sits in the Hunter, where Transgrid's preliminary revenue proposal of October 2021 carries a A$259 million line for the renewable energy zone. Beside that line, Transgrid publishes a trigger of more than 1,000 MW of new generation: an allowance for hosting generators, not headroom for a load.105105 Transgrid 2023-28 preliminary revenue proposal, Transgrid, 5 October 2021. Port Kembla sits in the Illawarra, where EnergyCo's zone was also declared for generation.106106 Illawarra Renewable Energy Zone, EnergyCo NSW, accessed 23 August 2026. With no document showing room for a factory's load, both sites go to unknown. Tomago's aluminium smelter will not free up its connection either; a government agreement now secures it to 2038.107107 Tomago Aluminium welcomes agreement to secure smelter's long-term future, Tomago Aluminium, 13 August 2026.

Bunbury fails outright. Western Power's Transmission System Plan 2025 aims Clean Energy Link East at the region, not the port, and records the Bunbury Harbour zone substation at 65 MW of planning capacity and 120% utilisation.6767 Transmission System Plan 2025 (Draft), Western Power, March 2026. The Stage 1 contracts awarded on 14 October cover Collie, Shotts and Muja, with nothing at the harbour.108108 Clean Energy Link East powers local jobs with major contract award, Government of Western Australia, 14 October 2026.

Across the whole screen, the load gate accounts for nine of the fifteen sites that get no score. Eight sites receive a score, and the five above 60 points form the shortlist. Geelong at 59.0, Burnie/Heybridge at 56.5 and Darwin at 54.0 follow them on the companion page.

Bell Bay leads with 69.0 out of 100. It is a brownfield industrial estate beside George Town substation. TasNetworks' 16 October conclusions report prefers a A$370.6 million network upgrade there, a new substation with 550 MVAr of reactive support, to be triggered when 210 MW or more of new load commits.109109 Meeting Network Planning Requirements at George Town, project assessment conclusions report, TasNetworks, 16 October 2026. Firmus's 288 MW Bell Bay campus, the approved data centre from chapter 3, exceeds that trigger on its own.3535 Firmus 288-megawatt AI data centre at Bell Bay receives George Town Council approval, ABC News, 25 August 2026. TasNetworks builds the upgrade only once new load commits at George Town, and Firmus is that load. A 50 to 150 MW factory would be a second load on the same substation, with its connection study starting from 288 MW already there.

The next four are close together. Kwinana and Cockburn Sound score 66.0 on the Kwinana stage of the same Western Australian link, which Western Power now targets for 2029.110110 Clean Energy Link Kwinana Strengthening, Western Power, accessed 31 October 2026. Hastings scores 65.0 on deep water and a Cranbourne transformer that AEMO costs at A$62.9 million, though its undecided environmental effects statement could remove it.111111 Cranbourne RIT-T project assessment conclusions report, Australian Energy Market Operator, accessed 23 August 2026. Gladstone scores 64.5 beside Powerlink's A$1.788 billion reinforcement, whose first stage began site clearing in July.6363 Transmission Annual Planning Report 2025, Powerlink Queensland, December 2025.112112 Central Queensland Transmission Update, Powerlink Queensland, July 2026. Henderson scores 63.5 on two berths that Fremantle Ports rates at 3,000 tonnes design displacement. It is the only quay in the set rated at the base design weight today, though that rating applies to the vessels a berth can take, and I inferred node transfer from it.113113 Port Information Guide 2025, Fremantle Port Authority, 2025. The defence precinct boundary fixed on 24 August now pulls naval work towards the common-user facility that Henderson's hall gate relies on.114114 Australia Selects Site Layout for Henderson Defence Precinct, Naval News, 24 August 2026.

Bell Bay leads the shortlist at 69, and the next four sit within 2.5 points of each other

Weighted screening score across ten dimensions, out of 100, five shortlisted sites as at 31 October 2026Source: Gate verdicts and dimension scores per site from port authority, network planning and marine park documents; weights as set out on the companion page

Weighted score / 100 · detail from 50 to 70

  1. Bell Bay 69

    A brownfield industrial estate beside the George Town substation, where the network upgrade is already through its regulatory test and an approved data centre is the load that triggers it.

  2. Kwinana and Cockburn Sound 66

    The Australian Marine Complex and its fabrication yards are next door, and the Kwinana stage of Western Power's Clean Energy Link is a fixed project for 2030.

  3. Hastings 65

    Deep water, and a renewable energy terminal already planned on the same waterfront. The undecided environmental assessment is the risk that would remove it.

  4. Gladstone 64.5

    The heaviest industrial base of any site, beside the largest load-driven network build in Queensland. Its weak point is the route to sea, through a long harbour and reef-linked approvals.

  5. Henderson (Australian Marine Complex) 63.5

    The only quay of the 23 rated at 3,000 tonnes design displacement today. AUKUS work both strengthens its fabrication base and competes for its workforce.

  6. Geelong 59
  7. Burnie/Heybridge 56.5
  8. Darwin (East Arm Wharf) 54

The first five, in the accent colour, are my shortlist. Only 5.5 points separate Bell Bay from Henderson, and all eight sites clear every gate.

Building one delivered node in Australia comes out about 40% over on capital cost and 30 months over on schedule compared with an established Asian yard. That misses the design brief's target of 30% and 18 months. The 40% is the top of the 30% to 40% premium the Commonwealth published with RAND's study of Australian naval shipbuilding. Setting it against an Asian yard is my step, not RAND's.115115 Minister for Defence, release of the RAND Corporation report, Department of Defence, 16 April 2015. The 30 months is the audited gap between the planned and achieved provisional acceptance of the first Air Warfare Destroyer, HMAS Hobart, from December 2014 to 16 June 2017.116116 Auditor-General Report No.19 2020-21, 2019-20 Major Projects Report, Air Warfare Destroyer Build, Australian National Audit Office, 30 November 2020. RAND found that a continuous build on a mature, frozen design halves the cost premium, which would put a series of 20 nodes at 20%. Halving the schedule overrun to 15 months is my extrapolation, not RAND's. Only that combined case lands inside the target.

None of this shows whether a node works at sea. Panthalassa's site names Ocean-2 as its Pacific pilot and publishes no quantified result.104104 Panthalassa, company site (Go where the energy is), accessed 2 September 2026. The chief executive said in May that the Ocean-3 series would start going into the water in October.9999 Building inference data centers on the high seas, Latitude Media, 28 May 2026. The first sign of a launch came in November. A photograph posted to an Astoria community group shows a node under tow on the Columbia on 19 November, captioned as heading out for sea trials.117117 Panthalassa autonomous, wave-powered AI data center being towed out of Portland, Oregon for sea trials, photograph from the Astoria Riverwalk Fans Facebook group, reposted by KuCoin News, 23 November 2026. Five days later a node was photographed at the Port of Everett, north of Seattle, and the local news site that ran the picture believes it is Ocean-3.118118 Mysterious Object In Everett Again: Learn About Panthalassa, My Everett News, 25 November 2026. Ocean-2 left from Everett for its three-week trial in February 2024.119119 Ocean-2 Puget Sound Trial, PRIMRE Projects Database, Open Energy Information, accessed 26 November 2026. Neither sighting comes from the company, which has announced no trial and no result. The companion page has the gate table, the ten weighted dimensions and the document behind every cell, along with the fifteen sites that carry no score and the gate that removed each one.

  1. The Very Wild, Very Real Plan To Build AI Data Centers In The Ocean, EP 65 Garth Sheldon-Coulson, Core Memory, 15 April 2026.
  2. Building inference data centers on the high seas, Latitude Media, 28 May 2026.
  3. Panthalassa raises $140 million to power AI, Renewable Energy Magazine, 8 May 2026.
  4. Ocean-powered AI data center startup Panthalassa is reportedly raising $225M at nearly $2 billion valuation, Tech Startups, 6 August 2026.
  5. Naver Invests in Panthalassa, a Startup Developing AI Data Centers Powered by Wave Energy, Edaily, 13 August 2026.
  6. Vancouver gets a factory for floating wave-energy data centers, Oregon Public Broadcasting, 7 November 2026.
  7. Panthalassa, company site (Go where the energy is), accessed 2 September 2026.
  8. Transgrid 2023-28 preliminary revenue proposal, Transgrid, 5 October 2021.
  9. Illawarra Renewable Energy Zone, EnergyCo NSW, accessed 23 August 2026.
  10. Tomago Aluminium welcomes agreement to secure smelter's long-term future, Tomago Aluminium, 13 August 2026.
  11. Clean Energy Link East powers local jobs with major contract award, Government of Western Australia, 14 October 2026.
  12. Meeting Network Planning Requirements at George Town, project assessment conclusions report, TasNetworks, 16 October 2026.
  13. Clean Energy Link Kwinana Strengthening, Western Power, accessed 31 October 2026.
  14. Cranbourne RIT-T project assessment conclusions report, Australian Energy Market Operator, accessed 23 August 2026.
  15. Central Queensland Transmission Update, Powerlink Queensland, July 2026.
  16. Port Information Guide 2025, Fremantle Port Authority, 2025.
  17. Australia Selects Site Layout for Henderson Defence Precinct, Naval News, 24 August 2026.
  18. Minister for Defence, release of the RAND Corporation report, Department of Defence, 16 April 2015.
  19. Auditor-General Report No.19 2020-21, 2019-20 Major Projects Report, Air Warfare Destroyer Build, Australian National Audit Office, 30 November 2020.
  20. Panthalassa autonomous, wave-powered AI data center being towed out of Portland, Oregon for sea trials, photograph from the Astoria Riverwalk Fans Facebook group, reposted by KuCoin News, 23 November 2026.
  21. Mysterious Object In Everett Again: Learn About Panthalassa, My Everett News, 25 November 2026.
  22. Ocean-2 Puget Sound Trial, PRIMRE Projects Database, Open Energy Information, accessed 26 November 2026.

Chapter 9. The load is going where the coal is

Most large campuses publish no electricity supply arrangement, and the only study of grid headroom finds none. Even the design that avoids the grid still needs a factory connected to it.

All 2,281 MW proposed as built IT sits in regions below the 44.5% national renewable share. South Australia and Tasmania, the two regions furthest above that share, hold none of it.11 Open Electricity v4 API, NEM energy by region and fuel technology, October 2025 to September 2026, Open Electricity, 31 October 2026. Australia's AI load and its low-emission generation are in different places, more completely than I expected. The margin is the weak part. The largest block is in Victoria, which sits 1.3 points below that share and was above it in 11 of the last 23 months.

Thirty-four of the 41 campuses of 50 MW or more publish no electricity supply arrangement, and none publishes a campus renewable share. I did not expect that gap to matter as much as it does. The few public arrangements come with caveats. One is a 25 MW solar farm that its owner now describes as capacity bought for customers. Another relies on certificates surrendered for a whole portfolio, and the operator's own footnote says matching is not the same as consumption. A third is a government scheme standing in for a campus figure. The largest contract disclosed in the country, 600 MW of firm supply for Firmus in South Australia, attaches to no campus in my inventory. If you want to know what powers a particular data centre at three in the morning, nothing any operator has published will tell you. The firm-contract obligation the AEMC advised in August would make each campus hold supply for its load. None of the proposals so far would make it publish that supply.

Transgrid's April study finds no capacity for new data-centre load in Western Sydney in 2032/33 on the network as planned.5858 Studies on augmentation supporting data centre connections in Western Sydney, Transgrid, April 2026. No other network publishes a comparable capacity figure. Meanwhile, Transgrid's 2026 planning report counts about 20 GW seeking connection in the state.5959 2026 Transmission Annual Planning Report, Transgrid, September 2026. The public conversation runs on a 26.8 GW pipeline, though the publisher itself classes 19.6 GW as early stage.3131 Australian Data Centre Forecast Report, Issue 2, data at 30 September 2026, Data Centres Australia and DC Byte, 30 October 2026. AEMO counts 67 GW of connection capacity in development and finds that connected data centres use about 27% of what they hold.3232 2026 ESOO data centre forecasting overview, AEMO, August 2026. Those numbers describe stage, intent and contracted access. None of them describes what the grid can take.

The cables do not explain where the load is going. Sydney is the only place where the landings and the load coincide. Victoria now has the largest proposed total and no live international landing. Perth has three live systems, two of them out of service this quarter, and no built-IT megawatts. AI processing that does not have to answer immediately has no reason to sit beside a cable landing.

Panthalassa gets a chapter because its node would make its own power in open water and need neither a grid connection nor a cable landing where it operates. The mismatch would not apply to the node, but Panthalassa still needs a factory. When I screened 23 sites for one, the gate that removed the most candidates was electrical load. Bell Bay, at the top of that screen, now shares its substation with an approved 288 MW data centre whose load triggers the network upgrade there.109109 Meeting Network Planning Requirements at George Town, project assessment conclusions report, TasNetworks, 16 October 2026. I ended up at the same conclusion from the opposite side. The data centres are here and the power is not. Even the one design that avoids the problem has to plug its factory into the same grid, in one case right beside the data centres themselves.