title: "Twenty-three places. Five gates. · research"
url: "https://colindismuke.com/research/panthalassa-sites"
description: "Panthalassa is designing floating data centres that make their own electricity from waves at sea. It calls them nodes. The question on land is where to build the factory that makes them. I screened 23 Australian coastal sites against five gates, any one of which removes a site outright. I ranked the"
published: "2026-10-31"
---

[research](https://colindismuke.com/research) · site selection

#  Twenty-three places.  
Five gates. 

AUSTRALIA · 2026

**Bell Bay leads with** 69 / 100

3 points ahead of the next site. 8 of 23 sites clear the gates.

Panthalassa is designing floating data centres that make their own electricity from waves at sea. It calls them nodes. The question on land is where to build the factory that makes them. I screened 23 Australian coastal sites against five gates, any one of which removes a site outright. I ranked the survivors out of 100 on ten weighted criteria. Eight sites clear every gate on public evidence, and Bell Bay in Tasmania leads with 69\. Port Kembla and Bunbury both fall on the factory electricity gate: Bunbury fails, and no public document settles it for Port Kembla.

Colin Dismuke · 26 November 2026 · data updated on 31 October 2026 · 15 minute read

Bell Bay leads a closely grouped field

 Weighted score out of 100 for the eight sites that clear all five gates, and the removing gate for the fifteen that do not, 23 candidate sites as at 31 October 2026 · Source: Site screening record per row; weights from chapter 4 

Weighted score / 100 · detail from 50 to 70 

1. Bell Bay [](https://colindismuke.com/research/au-ai-data-centres/atlas#/site/bell-bay) 69
2. Kwinana and Cockburn Sound [](https://colindismuke.com/research/au-ai-data-centres/atlas#/site/kwinana-cockburn-sound) 66
3. Hastings [](https://colindismuke.com/research/au-ai-data-centres/atlas#/site/hastings-otra) 65
4. Gladstone [](https://colindismuke.com/research/au-ai-data-centres/atlas#/site/gladstone-fishermans-landing) 64.5
5. Henderson (Australian Marine Complex) [](https://colindismuke.com/research/au-ai-data-centres/atlas#/site/henderson) 63.5
6. Shortlist above this line Geelong [](https://colindismuke.com/research/au-ai-data-centres/atlas#/site/geelong-corio-quay) 59
7. Burnie/Heybridge [](https://colindismuke.com/research/au-ai-data-centres/atlas#/site/burnie-heybridge) 56.5
8. Darwin (East Arm Wharf) [](https://colindismuke.com/research/au-ai-data-centres/atlas#/site/darwin) 54

 50  55  60  65  70 

Removed, fails the load gate: Albany; Bunbury; Esperance; Fremantle Inner Harbour 

Removed, fails the hall gate: Australian Maritime College, Launceston; Melbourne Victoria Dock; Osborne and Port Adelaide 

Removed, load gate not known: Civmec Tomago/Newcastle; Hobart/Prince of Wales Bay; Mackay/Hay Point; Port Kembla; Portland 

Removed, hall gate not known: Eden 

Removed, fails the flip depth gate: Karratha and Port of Dampier; Whyalla 

 The fifteen sites listed here have no score. A site that fails a gate, or that no public document settles, is removed before any scoring. 

1 

## Chapter 1\. Twenty-three waterfronts screened for a node factory 

This page is the working behind one paragraph of the main report. It asks which Australian waterfront has the berths, the land and the power for a node factory by 2030, judged only on documents anyone can open.

I screened 23 Australian waterfront sites for a Panthalassa node factory, and 8 clear all five gates. Panthalassa, a public-benefit corporation, says it is building a planetary-scale ocean energy platform. The hardware is a node about 20 m across at the top that extends about 80 m below the waterline and forces water through internal channels into a turbine and a generator.[1](#au-src-1)1 [Panthalassa](https://panthalassa.com/), company site (Go where the energy is), accessed 2 September 2026.[2](#au-src-2)2 [The Very Wild, Very Real Plan To Build AI Data Centers In The Ocean, EP 65 Garth Sheldon-Coulson](https://www.corememory.com/p/ocean-ai-data-center-panthalassa-garth), Core Memory, 15 April 2026. The company plans to run GPU and TPU servers on that electricity and send the results back through Starlink. In May 2026 it announced a US$140 million Series B.[2](#au-src-2)2 [The Very Wild, Very Real Plan To Build AI Data Centers In The Ocean, EP 65 Garth Sheldon-Coulson](https://www.corememory.com/p/ocean-ai-data-center-panthalassa-garth), Core Memory, 15 April 2026.[3](#au-src-3)3 [Panthalassa raises $140 million to power AI](https://www.renewableenergymagazine.com/ocean%5Fenergy/panthalassa-raises-140-million-to-power-ai-20260508), Renewable Energy Magazine, 8 May 2026. In November it opened its first assembly line, at Vancouver, Washington, and a node was photographed under tow on the Columbia on its way to sea trials.[4](#au-src-4)4 [Vancouver gets a factory for floating wave-energy data centers](https://www.opb.org/article/2026/11/06/vancouver-floating-wave-energy-data-centers/), Oregon Public Broadcasting, 7 November 2026.[5](#au-src-5)5 [Panthalassa autonomous, wave-powered AI data center being towed out of Portland, Oregon for sea trials, photograph from the Astoria Riverwalk Fans Facebook group](https://www.kucoin.com/news/insight/FB/6b042fea9278e40007d92bcd), reposted by KuCoin News, 23 November 2026.

The node makes its own power in open water, so it needs no grid connection or cable landing where it operates. The factory that builds it is ordinary industry on land and does need a grid connection. One of the five gates tests for that connection; the other four test for deep water, a quay, a hall and a workforce. No gate tests for a cable landing.

The ranking answers one narrow question: which Australian waterfront could carry that factory by 2030, based on documents a reader can open. It is a desk screen against a published standard, not diligence, and it does not certify any site. No site here has a surveyed flip polygon, a modelled tow, a connection study or a title search. Most of the gate notes name the study still owed.

Eight of the twenty-three sites clear every gate, and they sit in five states and territories

 Candidate sites on the coast, the eight survivors as large rings and the fifteen removed as small ones, 23 sites as at 31 October 2026 · Source: Site screening record per row; Natural Earth coastline 

AdelaideSydneyBrisbaneHendersonKwinanaDarwinBurnieBell BayGeelongHastingsGladstone

- clears all five gates
- removed at a gate

The map does not draw water depth. The flip-depth gate asks for open water at least 120 m deep within one tow, with no bridge, lock or overhead line on the way. That deep water is offshore, and the map plots only the shore end of each route. The eight surviving sites are labelled, and the rest are named in the table below. 

[Explore every mark in the atlas](https://colindismuke.com/research/au-ai-data-centres/atlas) 

Read the five gates before the scores. A site that fails a gate or has no public document addressing it either way gets no score, so the matrix contains only sites whose gaps are all named and costed. Ten weighted dimensions then rank the survivors out of 100, and every cell in both tables cites its document.

1. [Panthalassa](https://panthalassa.com/), company site (Go where the energy is), accessed 2 September 2026\.
2. [The Very Wild, Very Real Plan To Build AI Data Centers In The Ocean, EP 65 Garth Sheldon-Coulson](https://www.corememory.com/p/ocean-ai-data-center-panthalassa-garth), Core Memory, 15 April 2026\.
3. [Panthalassa raises $140 million to power AI](https://www.renewableenergymagazine.com/ocean%5Fenergy/panthalassa-raises-140-million-to-power-ai-20260508), Renewable Energy Magazine, 8 May 2026\.
4. [Vancouver gets a factory for floating wave-energy data centers](https://www.opb.org/article/2026/11/06/vancouver-floating-wave-energy-data-centers/), Oregon Public Broadcasting, 7 November 2026\.
5. [Panthalassa autonomous, wave-powered AI data center being towed out of Portland, Oregon for sea trials, photograph from the Astoria Riverwalk Fans Facebook group](https://www.kucoin.com/news/insight/FB/6b042fea9278e40007d92bcd), reposted by KuCoin News, 23 November 2026\.

2 

## Chapter 2\. The five gates 

A gate asks whether a site can do the job at all. Every threshold is my own design assumption, because the company has not published one.

Five gates run before any site is scored, and the load gate alone accounts for 9 of the 15 sites the screen removes. Their thresholds come from the cases in my design brief, which I wrote because the company publishes no factory specification. None of them is published engineering. No first-party source verifies the 120 m flip depth, the 3,000 to 5,000 t assembly weight or the 50 to 150 MW factory load. Every gate below tests an assumption.

Each gate has four grades. Pass means a current primary source documents the attribute at or above the requirement today. Remediable means a named piece of work, with a public cost reference, closes the gap by 2030\. Fail means two independent sources show the requirement cannot be met at that site inside the window. Unknown means no public source addresses it either way. A missing diligence study does not make a gate unknown if the attribute itself is documented.

The flip gate tests whether a node can be turned upright near the yard. Water at least 120 m deep must lie within about 200 km by open-water tow, and 17 sites pass. The closest documented deep water in the set is Perth Canyon Marine Park, at 120 m to 5,000 m. Parks Australia gives depth ranges for a whole park, not a route, so a licensed chart route and a modelled tow are still owed.[6](#au-src-6)6 [Perth Canyon Marine Park](https://parksaustralia.gov.au/marine/parks/south-west/perth-canyon/), Parks Australia, accessed 23 August 2026.[7](#au-src-7)7 [AusENC electronic navigational charts](https://www.hydro.gov.au/charts/ausenc), Australian Hydrographic Office, accessed 23 August 2026.

The quay gate tests the load-out. A berth or dock must be rated or proven at 3,000 t or more. Only one site in 23 passes today: Fremantle Ports rates Australian Marine Complex berths 1 and 5 at 3,000 t design displacement.[8](#au-src-8)8 [Port Information Guide 2025](https://www.fremantleports.com.au/docs/default-source/annual-report-case-study-videos-2023/fpa-port-information-guide-2025.pdf?sfvrsn=55215337%5F1), Fremantle Port Authority, 2025. Twenty are remediable, and my cost reference for them is Western Australia's A$53.2 million Jervoise Bay marine contract of 2001, which built a 15,000 t load-out wharf.[9](#au-src-9)9 [New Jervoise Bay marine complex contract signed](https://www.wa.gov.au/government/media-statements/Gallop%20Labor%20Government/New-Jervoise-Bay-marine-complex-contract-signed.-20010925), Government of Western Australia, 25 September 2001. No port publishes a verified transfer limit.

The hall gate tests whether the parcel can fit a clear-span building for an 80 m node and a path from it to the water. No site documents such a hall, so 16 are remediable, costed against the Australian National Audit Office's record of the A$457 million Osborne shipyard contract of 2017.[10](#au-src-10)10 [Naval Construction Programs: Mobilisation](https://www.anao.gov.au/work/performance-audit/naval-construction-programs-mobilisation), Australian National Audit Office, 14 May 2018. A site fails this gate where zoning, heritage or a committed programme already holds the waterfront. Title, tenure, contamination and Native Title are unsourced at every site.

The load gate tests electricity at the factory, not at the node. A site passes when a network planning document states that 50 MW or more is available at the connection point by 2027\. No document in the screen says that about any site. Nine sites are remediable on a named, costed augmentation that delivers 50 MW by 2030, four fail and ten are unknown. Four of the nine rest on Western Power's Transmission System Plan 2025 and TasNetworks' planning reports: the 2024 annual plan and the George Town assessment of 16 October 2026\. Three more rest on AEMO's Victorian planning documents.[11](#au-src-11)11 [Transmission System Plan 2025 (Draft)](https://www.westernpower.com.au/495bb8/siteassets/documents/nom/transmission-system-plan-2025-draft.pdf), Western Power, March 2026.[12](#au-src-12)12 [Annual Planning Report 2024](https://www.tasnetworks.com.au/Documents/Manual-documents/Planning-and-upgrades/APR/TasNetworks-Annual-Planning-Report-2024), TasNetworks, October 2024.[13](#au-src-13)13 [Meeting Network Planning Requirements at George Town, project assessment conclusions report](https://www.tasnetworks.com.au/planning-and-projects/major-projects/meeting-network-planning-requirements-at-george-town), TasNetworks, 16 October 2026.

The workforce gate tests whether the trades exist and are available. The gate requires a documented regional heavy-fabrication base that committed programmes are not shown to absorb, and 8 sites pass. A site is remediable on a named training programme with a cost reference, such as the A$11.4 million over three years for the Western Australian Defence Industry Pathways Program.[14](#au-src-14)14 [New investment in skills paves the way for AUKUS workforce](https://www.minister.defence.gov.au/media-releases/2023-05-16/new-investment-skills-paves-way-aukus-workforce), Minister for Defence, 16 May 2023. No region has a model of demand and supply by occupation. I can show that committed demand exists, but I cannot subtract it. Panthalassa's own first assembly line, opened at Vancouver, Washington, in November 2026, expects about 50 staff once fully staffed.[4](#au-src-4)4 [Vancouver gets a factory for floating wave-energy data centers](https://www.opb.org/article/2026/11/06/vancouver-floating-wave-energy-data-centers/), Oregon Public Broadcasting, 7 November 2026. I have not loosened the gate for it, because a first line says little about a plant built to supply a fleet.

A fail must meet a higher standard than the other three grades, because it ends a site's candidacy. Each requires two independent sources with different publishers and different addresses, and all ten verdicts have them. Esperance is the plainest case. Pacific Energy publishes a town system of 43.6 MW in total, and Energy Policy WA publishes the grid boundary that leaves the town outside it.[15](#au-src-15)15 [Esperance Hybrid Power System](https://pacificenergy.com.au/project/esperance-power-station-renewables-hub/), Pacific Energy, accessed 23 August 2026.[16](#au-src-16)16 [Electricity Industry, Energy Policy WA](https://www.wa.gov.au/organisation/energy-policy-wa/electricity-industry), Government of Western Australia, 26 June 2025.

1. [Perth Canyon Marine Park](https://parksaustralia.gov.au/marine/parks/south-west/perth-canyon/), Parks Australia, accessed 23 August 2026\.
2. [AusENC electronic navigational charts](https://www.hydro.gov.au/charts/ausenc), Australian Hydrographic Office, accessed 23 August 2026\.
3. [Port Information Guide 2025](https://www.fremantleports.com.au/docs/default-source/annual-report-case-study-videos-2023/fpa-port-information-guide-2025.pdf?sfvrsn=55215337%5F1), Fremantle Port Authority, 2025\.
4. [New Jervoise Bay marine complex contract signed](https://www.wa.gov.au/government/media-statements/Gallop%20Labor%20Government/New-Jervoise-Bay-marine-complex-contract-signed.-20010925), Government of Western Australia, 25 September 2001\.
5. [Naval Construction Programs: Mobilisation](https://www.anao.gov.au/work/performance-audit/naval-construction-programs-mobilisation), Australian National Audit Office, 14 May 2018\.
6. [Transmission System Plan 2025 (Draft)](https://www.westernpower.com.au/495bb8/siteassets/documents/nom/transmission-system-plan-2025-draft.pdf), Western Power, March 2026\.
7. [Annual Planning Report 2024](https://www.tasnetworks.com.au/Documents/Manual-documents/Planning-and-upgrades/APR/TasNetworks-Annual-Planning-Report-2024), TasNetworks, October 2024\.
8. [Meeting Network Planning Requirements at George Town, project assessment conclusions report](https://www.tasnetworks.com.au/planning-and-projects/major-projects/meeting-network-planning-requirements-at-george-town), TasNetworks, 16 October 2026\.
9. [New investment in skills paves the way for AUKUS workforce](https://www.minister.defence.gov.au/media-releases/2023-05-16/new-investment-skills-paves-way-aukus-workforce), Minister for Defence, 16 May 2023\.
10. [Esperance Hybrid Power System](https://pacificenergy.com.au/project/esperance-power-station-renewables-hub/), Pacific Energy, accessed 23 August 2026\.
11. [Electricity Industry, Energy Policy WA](https://www.wa.gov.au/organisation/energy-policy-wa/electricity-industry), Government of Western Australia, 26 June 2025\.

The electrical load gate is the main barrier

 Five gates by 23 candidate sites, one verdict per site and gate, with the documents behind each site named once beside it · Source: Gate verdicts and sources per row, site screening record 

- Pass
- Remediable, costed
- Fail
- Not known

Swipe to compare gates

__The five gates, all 23 sites, survivors first in score order, followed by removed sites. 8 clear every gate; the rest name the gate that removed them. Each gate opens its note.__
| Site                                    | State | Flip depth | Load-out quay | Node hall | Electrical load | Workforce | Result                    | Sources                                                                                                  |
| --------------------------------------- | ----- | ---------- | ------------- | --------- | --------------- | --------- | ------------------------- | -------------------------------------------------------------------------------------------------------- |
| Bell Bay                                | tas   |            |               |           |                 |           | Clears every gate         | [9](#au-src-9), [10](#au-src-10), [13](#au-src-13), [31](#au-src-31), [74](#au-src-74)                   |
| Kwinana and Cockburn Sound              | wa    |            |               |           |                 |           | Clears every gate         | [6](#au-src-6), [8](#au-src-8), [11](#au-src-11), [14](#au-src-14), [33](#au-src-33)                     |
| Hastings                                | vic   |            |               |           |                 |           | Clears every gate         | [9](#au-src-9), [10](#au-src-10), [37](#au-src-37), [74](#au-src-74), [79](#au-src-79)                   |
| Gladstone                               | qld   |            |               |           |                 |           | Clears every gate         | [9](#au-src-9), [10](#au-src-10), [19](#au-src-19), [74](#au-src-74), [85](#au-src-85)                   |
| Henderson (Australian Marine Complex)   | wa    |            |               |           |                 |           | Clears every gate         | [6](#au-src-6), [8](#au-src-8), [11](#au-src-11), [14](#au-src-14), [39](#au-src-39)                     |
| Geelong                                 | vic   |            |               |           |                 |           | Clears every gate         | [9](#au-src-9), [10](#au-src-10), [42](#au-src-42), [74](#au-src-74), [79](#au-src-79)                   |
| Burnie/Heybridge                        | tas   |            |               |           |                 |           | Clears every gate         | [9](#au-src-9), [10](#au-src-10), [12](#au-src-12), [31](#au-src-31), [74](#au-src-74)                   |
| Darwin (East Arm Wharf)                 | nt    |            |               |           |                 |           | Clears every gate         | [44](#au-src-44), [45](#au-src-45), [46](#au-src-46), [47](#au-src-47)                                   |
| Albany                                  | wa    |            |               |           |                 |           | Fails the load gate       | [11](#au-src-11), [56](#au-src-56), [60](#au-src-60), [61](#au-src-61), [62](#au-src-62)                 |
| Bunbury                                 | wa    |            |               |           |                 |           | Fails the load gate       | [11](#au-src-11), [20](#au-src-20), [57](#au-src-57), [58](#au-src-58), [59](#au-src-59)                 |
| Esperance                               | wa    |            |               |           |                 |           | Fails the load gate       | [15](#au-src-15), [16](#au-src-16), [62](#au-src-62), [63](#au-src-63), [64](#au-src-64)                 |
| Fremantle Inner Harbour                 | wa    |            |               |           |                 |           | Fails the load gate       | [6](#au-src-6), [8](#au-src-8), [11](#au-src-11), [14](#au-src-14), [56](#au-src-56)                     |
| Civmec Tomago/Newcastle                 | nsw   |            |               |           |                 |           | Load gate not known       | [9](#au-src-9), [10](#au-src-10), [17](#au-src-17), [74](#au-src-74), [82](#au-src-82)                   |
| Hobart/Prince of Wales Bay              | tas   |            |               |           |                 |           | Load gate not known       | [9](#au-src-9), [10](#au-src-10), [27](#au-src-27), [31](#au-src-31), [78](#au-src-78)                   |
| Mackay/Hay Point                        | qld   |            |               |           |                 |           | Load gate not known       | [9](#au-src-9), [10](#au-src-10), [19](#au-src-19), [74](#au-src-74), [85](#au-src-85)                   |
| Port Kembla                             | nsw   |            |               |           |                 |           | Load gate not known       | [9](#au-src-9), [10](#au-src-10), [17](#au-src-17), [74](#au-src-74), [82](#au-src-82)                   |
| Portland                                | vic   |            |               |           |                 |           | Load gate not known       | [9](#au-src-9), [10](#au-src-10), [28](#au-src-28), [74](#au-src-74), [79](#au-src-79)                   |
| Australian Maritime College, Launceston | tas   |            |               |           |                 |           | Fails the hall gate       | [25](#au-src-25), [27](#au-src-27), [31](#au-src-31), [77](#au-src-77)                                   |
| Melbourne Victoria Dock                 | vic   |            |               |           |                 |           | Fails the hall gate       | [9](#au-src-9), [26](#au-src-26), [42](#au-src-42), [79](#au-src-79), [80](#au-src-80), [81](#au-src-81) |
| Osborne and Port Adelaide               | sa    |            |               |           |                 |           | Fails the hall gate       | [14](#au-src-14), [23](#au-src-23), [24](#au-src-24), [71](#au-src-71), [72](#au-src-72)                 |
| Eden                                    | nsw   |            |               |           |                 |           | Hall gate not known       | [9](#au-src-9), [29](#au-src-29), [74](#au-src-74), [83](#au-src-83), [84](#au-src-84)                   |
| Karratha and Port of Dampier            | wa    |            |               |           |                 |           | Fails the flip depth gate | [21](#au-src-21), [62](#au-src-62), [65](#au-src-65), [66](#au-src-66), [67](#au-src-67)                 |
| Whyalla                                 | sa    |            |               |           |                 |           | Fails the flip depth gate | [22](#au-src-22), [68](#au-src-68), [69](#au-src-69), [70](#au-src-70)                                   |

1. Bell Bay tas  
Clears every gate  
Sources [9](#au-src-9), [10](#au-src-10), [13](#au-src-13), [31](#au-src-31), [74](#au-src-74)
2. Kwinana and Cockburn Sound wa  
Clears every gate  
Sources [6](#au-src-6), [8](#au-src-8), [11](#au-src-11), [14](#au-src-14), [33](#au-src-33)
3. Hastings vic  
Clears every gate  
Sources [9](#au-src-9), [10](#au-src-10), [37](#au-src-37), [74](#au-src-74), [79](#au-src-79)
4. Gladstone qld  
Clears every gate  
Sources [9](#au-src-9), [10](#au-src-10), [19](#au-src-19), [74](#au-src-74), [85](#au-src-85)
5. Henderson (Australian Marine Complex) wa  
Clears every gate  
Sources [6](#au-src-6), [8](#au-src-8), [11](#au-src-11), [14](#au-src-14), [39](#au-src-39)
6. Geelong vic  
Clears every gate  
Sources [9](#au-src-9), [10](#au-src-10), [42](#au-src-42), [74](#au-src-74), [79](#au-src-79)
7. Burnie/Heybridge tas  
Clears every gate  
Sources [9](#au-src-9), [10](#au-src-10), [12](#au-src-12), [31](#au-src-31), [74](#au-src-74)
8. Darwin (East Arm Wharf) nt  
Clears every gate  
Sources [44](#au-src-44), [45](#au-src-45), [46](#au-src-46), [47](#au-src-47)
9. Albany wa  
Fails the load gate  
Sources [11](#au-src-11), [56](#au-src-56), [60](#au-src-60), [61](#au-src-61), [62](#au-src-62)
10. Bunbury wa  
Fails the load gate  
Sources [11](#au-src-11), [20](#au-src-20), [57](#au-src-57), [58](#au-src-58), [59](#au-src-59)
11. Esperance wa  
Fails the load gate  
Sources [15](#au-src-15), [16](#au-src-16), [62](#au-src-62), [63](#au-src-63), [64](#au-src-64)
12. Fremantle Inner Harbour wa  
Fails the load gate  
Sources [6](#au-src-6), [8](#au-src-8), [11](#au-src-11), [14](#au-src-14), [56](#au-src-56)
13. Civmec Tomago/Newcastle nsw  
Load gate not known  
Sources [9](#au-src-9), [10](#au-src-10), [17](#au-src-17), [74](#au-src-74), [82](#au-src-82)
14. Hobart/Prince of Wales Bay tas  
Load gate not known  
Sources [9](#au-src-9), [10](#au-src-10), [27](#au-src-27), [31](#au-src-31), [78](#au-src-78)
15. Mackay/Hay Point qld  
Load gate not known  
Sources [9](#au-src-9), [10](#au-src-10), [19](#au-src-19), [74](#au-src-74), [85](#au-src-85)
16. Port Kembla nsw  
Load gate not known  
Sources [9](#au-src-9), [10](#au-src-10), [17](#au-src-17), [74](#au-src-74), [82](#au-src-82)
17. Portland vic  
Load gate not known  
Sources [9](#au-src-9), [10](#au-src-10), [28](#au-src-28), [74](#au-src-74), [79](#au-src-79)
18. Australian Maritime College, Launceston tas  
Fails the hall gate  
Sources [25](#au-src-25), [27](#au-src-27), [31](#au-src-31), [77](#au-src-77)
19. Melbourne Victoria Dock vic  
Fails the hall gate  
Sources [9](#au-src-9), [26](#au-src-26), [42](#au-src-42), [79](#au-src-79), [80](#au-src-80), [81](#au-src-81)
20. Osborne and Port Adelaide sa  
Fails the hall gate  
Sources [14](#au-src-14), [23](#au-src-23), [24](#au-src-24), [71](#au-src-71), [72](#au-src-72)
21. Eden nsw  
Hall gate not known  
Sources [9](#au-src-9), [29](#au-src-29), [74](#au-src-74), [83](#au-src-83), [84](#au-src-84)
22. Karratha and Port of Dampier wa  
Fails the flip depth gate  
Sources [21](#au-src-21), [62](#au-src-62), [65](#au-src-65), [66](#au-src-66), [67](#au-src-67)
23. Whyalla sa  
Fails the flip depth gate  
Sources [22](#au-src-22), [68](#au-src-68), [69](#au-src-69), [70](#au-src-70)

Bell Bay · Flip depth · Pass

The CC BY 4.0 AusBathyTopo screening grid shows open-water depths of at least 120 m within about 200 km of Bell Bay, with no bridge, lock or overhead-line barrier on the screened seaward route. Confirm two polygons and the full tow geometry with licensed AHO data.

[Source 74](#au-src-74)

Bell Bay · Load-out quay · Remediable

Build a dedicated heavy load-out quay, reinforced apron and SPMT route for 3,000, 4,000 and 5,000 t cases at Bell Bay; use the public Jervoise Bay A$53.2 million 2001 civil-and-marine contract as the cost reference, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 9](#au-src-9)

Bell Bay · Node hall · Remediable

Build the node hall, supports, doors, apron and full hall-to-water path on the documented industrial waterfront at Bell Bay; use the ANAO A$457 million 2017 Osborne surface-shipyard contract as the public cost envelope, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 10](#au-src-10)

Bell Bay · Electrical load · Remediable

Deliver the George Town augmentation TasNetworks' project assessment conclusions report of 16 October 2026 prefers: a new air-insulated substation with 550 MVAr of reactive support and reconfiguration of the existing 220 kV switchyard, estimated at A$370.6 million. It is a contingent project in the 2024-2029 determination, triggered by the commitment of 210 MW or more of new load at George Town, and Firmus's approved 288 MW Bell Bay campus exceeds that trigger alone, so a factory's 50 to 150 MW is a second load on the same substation. Commissioning is not certain by 2030.

[Source 13](#au-src-13)

Bell Bay · Workforce · Pass

Bell Bay has a documented heavy-industry or manufacturing labour base and a current training pathway. No public source shows full labour absorption by 2030\. Complete the occupation-by-year demand model before investment.

[Source 31](#au-src-31)

Kwinana and Cockburn Sound · Flip depth · Pass

Perth Canyon Marine Park, 19 km west of Rottnest Island, holds depths of 120 m to 5,000 m and is reachable from Cockburn Sound in one open-water tow of about 50 km with no bridge, lock or overhead line; South-west Corner Marine Park is the backup. Fremantle Ports limits the Stirling and Calista Channels serving the Kwinana quay line to 230 m LOA, 32.5 m beam and under 10.6 m draft on DUKC, and the Woodman, Jervoise and Medina Channels to under 8.5 m. Diligence still owes the modelled tow geometry - node and tug draft, towline, under-keel allowance, turns, currents, pilotage and abort areas - and a certified primary and backup polygon.

[Source 6](#au-src-6)

Kwinana and Cockburn Sound · Load-out quay · Remediable

The Kwinana quay line is bulk and liquids only. Fremantle Ports records KBB3 and KBB4 at 85,000 t design displacement with 80 t bollards and 14.0 m declared depth, the Kwinana Grain Jetty at 75,000 t and 16.7 m and the oil refinery jetties at 14.5 m, but no berth on the Kwinana line carries a load-out or transfer rating. The named work is a purpose-built heavy load-out wharf on the available Cockburn Sound waterfront the State already holds. Cost reference: the Lumsden Point common-user development at Port Hedland delivers two new multi-user wharves including a heavy-lift land-backed wharf for $450 million from the Commonwealth and $96.6 million from Western Australia, with imports from mid-2026\. Diligence still owes the engineering drawings, SPMT route, deck and line loads, bollard loads and verified transfer limits at 3,000, 4,000 and 5,000 tonnes.

[Source 8](#au-src-8)

Kwinana and Cockburn Sound · Node hall · Remediable

The Australian Marine Complex spans five precincts - shipbuilding, fabrication, support, technology and recreational boating - on Western Australian Government land in Perth's premier industrial corridor, with significant available land reserved for the development of high-tech and innovative industries and the adjacent Marine Industry Technology Park. The named work is a purpose-built assembly hall and hall-to-water load path on that land. Cost reference: Defence has committed $12 billion of early works and infrastructure at the Henderson Defence Precinct against a total infrastructure estimate of about $25 billion for shipyard halls, docks and berths of this class. Diligence still owes title, tenure, zoning, contamination, acid-sulfate soils, geotechnical conditions, biodiversity, cultural heritage, Native Title and neighbour checks, plus hall geometry and the full hall-to-water load path.

[Source 33](#au-src-33)

Kwinana and Cockburn Sound · Electrical load · Remediable

Western Power's Transmission System Plan 2025 lists CEL Kwinana Stage 1 as a Fixed project with an earliest entry of 2030 and Stage 2 for 2033, and states that Stage 1 is assumed complete by 2030 and addresses reliability of supply issues in the Kwinana area. Funding sits inside the SWIS Transmission Plan, $1.6 billion provided plus a $1.4 billion Clean Energy Fund. Diligence still owes connection studies at 50, 100 and 150 MW for 2027 and 2030 with connection voltage, shared-network works, system-strength needs, firm capacity, curtailment, lead time, contribution and energy price.

[Source 11](#au-src-11)

Kwinana and Cockburn Sound · Workforce · Remediable

The same named, costed instrument applies as at Henderson 6 km north: $11.4 million over three years to extend the Defence Industry Pathways Program within the Western Australian shipbuilding sector, inside a nearly $150 million Commonwealth AUKUS skills package. The gap is the same 10,000-job Henderson precinct demand and Weld Australia's estimate of a shortfall of at least 70,000 welders by 2030\. Diligence still owes an annual occupation-level demand and supply model with committed defence, steel, energy and infrastructure demand deducted.

[Source 14](#au-src-14)

Hastings · Flip depth · Pass

The CC BY 4.0 AusBathyTopo screening grid shows open-water depths of at least 120 m within about 200 km of Hastings OTRA, with no bridge, lock or overhead-line barrier on the screened seaward route. Confirm two polygons and the full tow geometry with licensed AHO data.

[Source 74](#au-src-74)

Hastings · Load-out quay · Remediable

Build a dedicated heavy load-out quay, reinforced apron and SPMT route for 3,000, 4,000 and 5,000 t cases at the OTRA waterfront; use the public Jervoise Bay A$53.2 million 2001 civil-and-marine contract as the cost reference, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 9](#au-src-9)

Hastings · Node hall · Remediable

Build the node hall, supports, doors, apron and full hall-to-water path on the documented industrial waterfront at the OTRA parcel; use the ANAO A$457 million 2017 Osborne surface-shipyard contract as the public cost envelope, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 10](#au-src-10)

Hastings · Electrical load · Remediable

Build a fourth 150 MVA 220/66 kV transformer at Cranbourne Terminal Station plus a dedicated OTRA feeder. The RIT-T ran from the October 2024 PSCR through the 6 June 2025 PADR, which put the preferred option at A$56.0 million (real 2025) with optimum timing 2026-27; the later PACR carries A$62.9 million. Cranbourne Terminal Station is about 25 km from the OTRA parcel and the project is a supply-reliability investment for the Cranbourne 66 kV supply area, so a dedicated Hastings connection study for 50, 100 and 150 MW is still required.

[Source 37](#au-src-37)

Hastings · Workforce · Pass

Hastings and south-east Melbourne has a documented heavy-industry or manufacturing labour base and a current training pathway. No public source shows full labour absorption by 2030\. Complete the occupation-by-year demand model before investment.

[Source 79](#au-src-79)

Gladstone · Flip depth · Pass

The CC BY 4.0 AusBathyTopo screening grid shows open-water depths of at least 120 m within about 200 km of Fisherman's Landing, with no bridge, lock or overhead-line barrier on the screened seaward route. Confirm two polygons and the full tow geometry with licensed AHO data.

[Source 74](#au-src-74)

Gladstone · Load-out quay · Remediable

Build a dedicated heavy load-out quay, reinforced apron and SPMT route for 3,000, 4,000 and 5,000 t cases at Fisherman's Landing; use the public Jervoise Bay A$53.2 million 2001 civil-and-marine contract as the cost reference, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 9](#au-src-9)

Gladstone · Node hall · Remediable

Build the node hall, supports, doors, apron and full hall-to-water path on the documented industrial waterfront at the Northern Land Expansion; use the ANAO A$457 million 2017 Osborne surface-shipyard contract as the public cost envelope, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 10](#au-src-10)

Gladstone · Electrical load · Remediable

Build Powerlink's preferred Gladstone 275 kV double-circuit, substation, transformer and security-service works; use the A$1.788 billion real-2025 estimate and commission by 2030.

[Source 19](#au-src-19)

Gladstone · Workforce · Pass

Gladstone has a documented heavy-industry or manufacturing labour base and a current training pathway. No public source shows full labour absorption by 2030\. Complete the occupation-by-year demand model before investment.

[Source 85](#au-src-85)

Henderson (Australian Marine Complex) · Flip depth · Pass

Perth Canyon Marine Park lies 19 km west of Rottnest Island with depths of 120 m to 5,000 m and an average of 2,399 m - the closest documented polygon at or beyond 120 m in this set, about 45 km from Cockburn Sound by open water with no bridge, lock or overhead line. South-west Corner Marine Park (to 6,400 m) is the backup. Fremantle Ports limits the Jervoise Channel serving the AMC to 230 m LOA, 32.5 m beam and under 8.5 m draft, and the Success and Parmelia Channels to 275 m LOA, 46 m beam and under 13 m draft on DUKC. Diligence still owes the modelled tow geometry - node and tug draft, towline, under-keel allowance, turns, currents, pilotage and abort areas - and a certified primary and backup polygon.

[Source 6](#au-src-6)

Henderson (Australian Marine Complex) · Load-out quay · Pass

Fremantle Ports rates AMC berths 1 and 5 at 3,000 t design displacement, with AMC berth 4 designated Maintenance / Heavy Lift at 245 m and an AMC4 Heavy Lift Berth declared at 12.6 m, and the AMC floating dock declared at 12.6 m. Western Australia's own directory records a 3,000 tonne wharf dredged to 11 m able to service vessels over 200 m, a floating dock 99 m long with 44 m between sidewalls, and self-propelled modular transporters to transfer vessels. That meets a rated transfer at or above 3,000 t today. Diligence still owes the engineering drawings, SPMT route, deck and line loads, bollard loads and verified transfer limits at 3,000, 4,000 and 5,000 tonnes.

[Source 8](#au-src-8)

Henderson (Australian Marine Complex) · Node hall · Remediable

The Common User Facility has a rail-mounted main fabrication hall of 80 m by 60 m with a 200 t crane, 40 ha of fully serviced laydown and assembly area, a protected harbour dredged to 10 m and a heavy-high-wide road link to the Main Roads network, on Western Australian Government land under an open-access policy with significant further land reserved for industry. An 80 m by 60 m hall cannot host a 120 m node, so a purpose-built hall and hall-to-water load path are the named work. Cost reference: Defence has committed $12 billion of early works and infrastructure at the Henderson Defence Precinct against a total infrastructure estimate of about $25 billion for shipyard halls, docks and berths of this class. The Commonwealth's Bechtel master plan for the precinct is not public, so the boundary between Defence-committed land and land available to a commercial tenant is not yet drawn. Diligence still owes title, tenure, zoning, contamination, acid-sulfate soils, geotechnical conditions, biodiversity, cultural heritage, Native Title and neighbour checks, plus hall geometry and the full hall-to-water load path.

[Source 39](#au-src-39)

Henderson (Australian Marine Complex) · Electrical load · Remediable

Western Power's Transmission System Plan 2025 lists CEL Kwinana Stage 1 as a Fixed project with an earliest entry of 2030 and CEL Kwinana Stage 2 for 2033, and states that CEL Kwinana Stage 1 is assumed complete by 2030 and addresses reliability of supply issues in the Kwinana area. The Clean Energy Link programme is funded by $1.6 billion already provided plus the $1.4 billion Clean Energy Fund in the 2026-27 State Budget. That is a named, costed augmentation delivering inside the window. The TSP also records constraints arising at peak demand in the Kwinana load area today. Diligence still owes connection studies at 50, 100 and 150 MW for 2027 and 2030 with connection voltage, shared-network works, system-strength needs, firm capacity, curtailment, lead time, contribution and energy price.

[Source 11](#au-src-11)

Henderson (Australian Marine Complex) · Workforce · Remediable

The named, costed instrument is the Commonwealth's AUKUS skills package: $11.4 million over three years to extend the Defence Industry Pathways Program within the Western Australian shipbuilding sector, inside a package of nearly $150 million that also funds $128.5 million over four years for 4,000 additional university places in naval architecture, materials science and mechanical, electrical and nuclear engineering, and a $3.9 million skills taskforce. The gap it must close is large: the Henderson precinct alone will support in the order of 10,000 high-skilled jobs over two decades, and Weld Australia estimates Australia will be at least 70,000 welders short by 2030\. Diligence still owes an annual occupation-level demand and supply model with committed defence, steel, energy and infrastructure demand deducted.

[Source 14](#au-src-14)

Geelong · Flip depth · Pass

The CC BY 4.0 AusBathyTopo screening grid shows open-water depths of at least 120 m within about 200 km of Corio Quay, with no bridge, lock or overhead-line barrier on the screened seaward route. Confirm two polygons and the full tow geometry with licensed AHO data.

[Source 74](#au-src-74)

Geelong · Load-out quay · Remediable

Build a dedicated heavy load-out quay, reinforced apron and SPMT route for 3,000, 4,000 and 5,000 t cases at Corio Quay; use the public Jervoise Bay A$53.2 million 2001 civil-and-marine contract as the cost reference, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 9](#au-src-9)

Geelong · Node hall · Remediable

Build the node hall, supports, doors, apron and full hall-to-water path on the documented industrial waterfront at Corio Quay; use the ANAO A$457 million 2017 Osborne surface-shipyard contract as the public cost envelope, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 10](#au-src-10)

Geelong · Electrical load · Remediable

Build the AEMO/AVP Western Metropolitan Melbourne Reinforcement, whose Option 1 uprates the Geelong-Moorabool 220 kV lines and cuts the Geelong-Keilor circuits into Deer Park, plus a Corio connection. AEMO's March 2025 PSCR estimates capital costs of A$73.6 million for Option 1A, A$127.5 million for Option 1B, A$119.7 million for Option 2A and A$173.6 million for Option 2B, all real 2024 dollars at plus or minus 50% accuracy. Option 1A raises western metropolitan network capacity at 45 degrees C from 2,700 MW to about 3,500 MW; Option 1B reaches about 3,600 MW. Earliest indicative commissioning runs Q4-2028 to Q4-2030\. This is a PSCR, the first RIT-T stage, not a committed investment.

[Source 42](#au-src-42)

Geelong · Workforce · Pass

Geelong has a documented heavy-industry or manufacturing labour base and a current training pathway. No public source shows full labour absorption by 2030\. Complete the occupation-by-year demand model before investment.

[Source 79](#au-src-79)

Burnie/Heybridge · Flip depth · Pass

The CC BY 4.0 AusBathyTopo screening grid shows open-water depths of at least 120 m within about 200 km of Burnie/Heybridge, with no bridge, lock or overhead-line barrier on the screened seaward route. Confirm two polygons and the full tow geometry with licensed AHO data.

[Source 74](#au-src-74)

Burnie/Heybridge · Load-out quay · Remediable

Build a dedicated heavy load-out quay, reinforced apron and SPMT route for 3,000, 4,000 and 5,000 t cases at Heybridge; use the public Jervoise Bay A$53.2 million 2001 civil-and-marine contract as the cost reference, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 9](#au-src-9)

Burnie/Heybridge · Node hall · Remediable

Build the node hall, supports, doors, apron and full hall-to-water path on the documented industrial waterfront at Heybridge; use the ANAO A$457 million 2017 Osborne surface-shipyard contract as the public cost envelope, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 10](#au-src-10)

Burnie/Heybridge · Electrical load · Remediable

Deliver the AER-approved North West Transmission Developments Stage 1: a new 220 kV switching station at Heybridge and a Sheffield-Heybridge-Burnie 220 kV double-circuit line. TasNetworks costs this first stage at A$1,144 million, and the AER approved A$151.9 million (2023/24) of Stage 1 early works in March 2025\. Delivery is tied to Marinus Link Stage 1, not to 2027\. The Burnie-Hampshire Hills 220 kV line is a separate post-Stage-1 North West REZ option with no public cost estimate. Complete the 50/100/150 MW connection studies for the Heybridge switching station before investment.

[Source 12](#au-src-12)

Burnie/Heybridge · Workforce · Remediable

Reserve and target A$12.6 million of the cited programme for the required trades, engineers, mariners and supervisors at Burnie/Heybridge; add employer attraction and housing actions, start in 2027, and deliver the cohorts by 2029.

[Source 31](#au-src-31)

Darwin (East Arm Wharf) · Flip depth · Pass

Oceanic Shoals Marine Park lies about 150 km north-west of Darwin, just west of the Tiwi Islands, with depths from under 15 m to 500 m, inside a single open-water tow with no bridge, lock or overhead line. The park averages 87 m over 71,743 square kilometres, so a specific polygon at or beyond 120 m still has to be charted, and Darwin's large tidal range and cyclone season constrain the window. Diligence still owes the modelled tow geometry - node and tug draft, towline, under-keel allowance, turns, currents, pilotage and abort areas - and a certified primary and backup polygon.

[Source 46](#au-src-46)

Darwin (East Arm Wharf) · Load-out quay · Remediable

The 5,500 t ship lift is a funded construction project, not a current transfer facility. Infrastructure NT states that the project will deliver the lift, wet berths, hardstand and self-propelled modular transporter access. Its Q1 2026 construction update records marine piling and staged operation in 2027\. The named $515 million project in the row's funding evidence closes the 3,000 t transfer gap before 2030\. Diligence still needs operating certification and transfer limits.

[Source 45](#au-src-45)

Darwin (East Arm Wharf) · Node hall · Remediable

The ship lift sits on Northern Territory Government land in the East Arm precinct of Darwin Harbour, between the Marine Supply Base and the multi-user barge ramp facility at the Marine Industry Park, with hard stand for repair and maintenance works. A parcel in a purpose-built marine industry precinct is therefore obtainable and the named work is a purpose-built assembly hall and hall-to-water load path. Cost reference: the ship lift and associated marine industry infrastructure is a $515 million project - a $300 million NAIF loan to the Northern Territory Treasury Corporation plus $215 million from the Northern Territory Government. Diligence still owes title, tenure, zoning, contamination, acid-sulfate soils, geotechnical conditions, biodiversity, cultural heritage, Native Title and neighbour checks, plus hall geometry and the full hall-to-water load path.

[Source 44](#au-src-44)

Darwin (East Arm Wharf) · Electrical load · Remediable

The Northern Territory Government's Darwin-Katherine Electricity System Plan is the network planning document, and it is built around exactly this class of load: its 'Sunshine for Sale' scenario assumes demand grows to four times current demand 'as new industries including advanced manufacturing, data centres and mines locate in our region', at an average 6.31 per cent a year, and the plan states it is compatible with a system delivering almost four times today's demand - a 1 GW system - that must 'accommodate large loads from new industry, including data centres, advanced manufacturing, renewable hydrogen for export, and electric vehicles'. Today's system is small by comparison: the 2020 maximum-demand-day profile peaks under 300 MW and 12 per cent of underlying demand is met by renewables. The plan does not state available capacity at an East Arm connection point, so it is not a pass. It is a named, costed, dated programme delivering far more than 50 MW inside the window: six focus areas over three stages - Ready 2021-23, Set 2024-26, Go 2027-30 - comprising 320 MW of new solar by 2030, 110 MW (600 MWh) of storage batteries, 100 MW of high spec security batteries, about 80 MW of new thermal generation, virtual power plants and demand management, plus a Renewable Energy Hub optimally sized at 180 to 230 MW of large-scale solar that aligns with the capacity of the existing Channel Island to Hudson Creek 132 kV line without uprating it, for transmission connection costs 'in the vicinity of $80 million' in 2020 real dollars covering diversion and extension of the 132 kV lines and a new 132/22 kV substation. Committed work in the first stage included 60 MW of large-scale solar on the Darwin-Katherine Transmission Line and the first of three high spec batteries in 2023, alongside an existing 35 MW battery. Two material risks stay in this verdict: Darwin-Katherine is a stand-alone power system with no interconnection, and the plan is a 2021 document whose Ready stage is now past, so delivery against its own timetable is unverified here. Diligence still owes connection studies at 50, 100 and 150 MW for 2027 and 2030 with connection voltage, shared-network works, system-strength needs, firm capacity, curtailment, lead time, contribution and energy price.

[Source 47](#au-src-47)

Darwin (East Arm Wharf) · Workforce · Remediable

Darwin has a marine services base at East Arm - the Marine Supply Base, the multi-user barge ramp facility and two stevedore operators at East Arm Wharf - and the named, costed instrument is the $515 million Darwin Ship Lift project, forecast by the Northern Australia Infrastructure Facility to deliver $924 million of public benefit and 287 jobs and to consolidate Darwin as a hub for marine maintenance and servicing in northern Australia. Diligence still owes an annual occupation-level demand and supply model with committed defence, steel, energy and infrastructure demand deducted.

[Source 44](#au-src-44)

Albany · Flip depth · Pass

Albany sits on King George Sound and Princess Royal Harbour, opening straight onto the Southern Ocean, and South-west Corner Marine Park wraps the south-west corner of Western Australia with depths from under 15 m to 6,400 m, enclosing Bremer Marine Park. A polygon at or beyond 120 m is reachable by open-water tow with no bridge, lock or overhead line, though the exact distance to the 120 m isobath south of Albany is not established. Diligence still owes the modelled tow geometry - node and tug draft, towline, under-keel allowance, turns, currents, pilotage and abort areas - and a certified primary and backup polygon.

[Source 60](#au-src-60)

Albany · Load-out quay · Remediable

Southern Ports publishes four berths on an 84 ha estate serving grain, woodchips, silica sands and fertiliser, with no design displacement, bollard rating or transfer limit published; its berth-specification page returned HTTP 404\. Princess Royal Harbour waterfront is available and Southern Ports already lists an Albany General Purpose Berth among its planned projects, so a heavy quay build is the named work. Cost reference: the Lumsden Point common-user development at Port Hedland delivers two new multi-user wharves including a heavy-lift land-backed wharf for $450 million from the Commonwealth and $96.6 million from Western Australia, with imports from mid-2026\. Diligence still owes the engineering drawings, SPMT route, deck and line loads, bollard loads and verified transfer limits at 3,000, 4,000 and 5,000 tonnes.

[Source 61](#au-src-61)

Albany · Node hall · Remediable

Southern Ports holds an 84 ha estate at Albany and offers leases for port-related industries plus marine leases and licences, so a parcel is obtainable, but no zoning, title, contamination or Native Title record was sourced and no hall of any relevant geometry exists. The named work is a purpose-built assembly hall and load path on the port estate. Cost reference: Defence has committed $12 billion of early works and infrastructure at the Henderson Defence Precinct against a total infrastructure estimate of about $25 billion for shipyard halls, docks and berths of this class. Diligence still owes title, tenure, zoning, contamination, acid-sulfate soils, geotechnical conditions, biodiversity, cultural heritage, Native Title and neighbour checks, plus hall geometry and the full hall-to-water load path.

[Source 61](#au-src-61)

Albany · Electrical load · Fail

Western Power's Transmission System Plan 2025 records the Albany zone substation at 60 MW of planning capacity and 103 per cent utilisation in the first year of the study, rising to 133 per cent by year ten, with the only listed remedy an upgrade to higher capacity transformers. Albany is fed radially from Muja - the Muja to Albany 132 kV constraint appears in the plan's top-20 system-normal congestion table - and no Clean Energy Link project serves the Great Southern: the Western Australian Government's Phase One for 2025 to 2030 comprises CEL North and CEL East, both far to the north and east. There is no documented pathway to 50 MW or more of new load at Albany by 2030.

[Source 11](#au-src-11), [Source 56](#au-src-56)

Albany · Workforce · Not known

No regional heavy-fabrication base is documented at Albany - the port trades grain, woodchips, silica sands and fertiliser with 37 local staff - and no named training, attraction or housing programme with a cost reference for the Great Southern was found. Jobs and Skills Australia publishes state and regional shortage ratings but no Albany net position after committed demand was derived.

[Source 62](#au-src-62)

Bunbury · Flip depth · Pass

Geographe Marine Park sits 8 km from Bunbury with depths of 15 m to 70 m and an average of 30 m, so no polygon at or beyond 120 m exists in Geographe Bay. A primary polygon is available in Perth Canyon Marine Park (120 m to 5,000 m, 19 km west of Rottnest Island, about 150 km north by sea) and a backup in South-west Corner Marine Park (to 6,400 m) beyond Cape Naturaliste. Both are single open-water tows inside 200 km with no bridge, lock or overhead line. Southern Ports warns that Bunbury wind gusts can be 40 per cent above forecast and maximum waves twice the forecast height, so the weather window is the real marine constraint. Diligence still owes the modelled tow geometry - node and tug draft, towline, under-keel allowance, turns, currents, pilotage and abort areas - and a certified primary and backup polygon.

[Source 57](#au-src-57)

Bunbury · Load-out quay · Remediable

The Port of Bunbury has seven active berths across an inner and an outer harbour with multi-user terminals and extensive laydown, and already takes project cargo including wind farm components and batteries, but Southern Ports publishes no berth design displacement, bollard rating or transfer limit. The named work is a purpose-built land-backed heavy load-out wharf on the port's undeveloped waterfront within its 470 ha estate. Cost reference: the Lumsden Point common-user development at Port Hedland delivers two new multi-user wharves including a heavy-lift land-backed wharf for $450 million from the Commonwealth and $96.6 million from Western Australia, with imports from mid-2026\. Diligence still owes the engineering drawings, SPMT route, deck and line loads, bollard loads and verified transfer limits at 3,000, 4,000 and 5,000 tonnes.

[Source 58](#au-src-58)

Bunbury · Node hall · Remediable

Southern Ports holds 470 ha at Bunbury across two harbours with established road and rail, describes the port as primed for growth with an expansive landholding ready for development, and offers land leases and licences for port-related industry. The named work is a purpose-built assembly hall and hall-to-water load path on that estate under a long lease. Cost reference: Defence has committed $12 billion of early works and infrastructure at the Henderson Defence Precinct against a total infrastructure estimate of about $25 billion for shipyard halls, docks and berths of this class. Diligence still owes title, tenure, zoning, contamination, acid-sulfate soils, geotechnical conditions, biodiversity, cultural heritage, Native Title and neighbour checks, plus hall geometry and the full hall-to-water load path.

[Source 58](#au-src-58)

Bunbury · Electrical load · Fail

Western Power's Transmission System Plan 2025 lists CEL East Stage 1 as a Fixed project with an earliest entry of 2029 and CEL Kemerton SIA as a Fixed, load-driven project, Kemerton being the Strategic Industrial Area about 20 km from Bunbury, with CEL Collie a Candidate for 2032\. Funding sits inside the SWIS Transmission Plan, $1.6 billion provided plus a $1.4 billion Clean Energy Fund, and Clean Energy Link - East connects a new terminal east of Collie to the Shotts and Muja terminals by two new high-voltage lines and is to be declared a priority project under the State Development Act 2025\. The Bunbury Harbour zone substation has 65 MW of planning capacity at 120 per cent utilisation with a transformer addition planned for 2028, so a large load must connect at transmission, not at the zone substation. Diligence still owes connection studies at 50, 100 and 150 MW for 2027 and 2030 with connection voltage, shared-network works, system-strength needs, firm capacity, curtailment, lead time, contribution and energy price.

[Source 11](#au-src-11), [Source 20](#au-src-20)

Bunbury · Workforce · Remediable

The named, costed instrument is the Western Australian Government's Collie Transition Package, which follows the 2020 Collie Just Transition Plan and funds a $230 million Collie Industrial Transition Fund for new industries and $16.9 million for local skills, training and career advice inside a package above $662 million, timed to the phased retirement of State-owned coal power stations by 2030 about 50 km from Bunbury. The South West is Western Australia's most populated region outside Perth. Residual risk is national: Weld Australia puts Australia at least 70,000 welders short by 2030\. Diligence still owes an annual occupation-level demand and supply model with committed defence, steel, energy and infrastructure demand deducted.

[Source 59](#au-src-59)

Esperance · Flip depth · Pass

Eastern Recherche Marine Park lies 135 km east of Esperance with depths from 15 m to 6,000 m and an average of 3,407 m, inside a single open-water tow with no bridge, lock or overhead line, and Esperance has the deepest channel in southern Western Australia. The exact distance to the 120 m isobath south of Esperance Bay is not established. Diligence still owes the modelled tow geometry - node and tug draft, towline, under-keel allowance, turns, currents, pilotage and abort areas - and a certified primary and backup polygon.

[Source 63](#au-src-63)

Esperance · Load-out quay · Remediable

Southern Ports publishes three berths on a 75 ha estate with an iron ore circuit and the only container crane of its size at a regional Western Australian port, but no design displacement, bollard rating or transfer limit, and remediation works on the piles beneath Berths 1 and 2 ran to August 2026\. Esperance Bay waterfront is available, so a heavy quay build is the named work. Cost reference: the Lumsden Point common-user development at Port Hedland delivers two new multi-user wharves including a heavy-lift land-backed wharf for $450 million from the Commonwealth and $96.6 million from Western Australia, with imports from mid-2026\. Diligence still owes the engineering drawings, SPMT route, deck and line loads, bollard loads and verified transfer limits at 3,000, 4,000 and 5,000 tonnes.

[Source 64](#au-src-64)

Esperance · Node hall · Remediable

Southern Ports holds a 75 ha estate at Esperance and offers leases for port-related industries, so a parcel is obtainable, but the estate is small and sits on the town foreshore, and no zoning, title, contamination or Native Title record was sourced. The named work is a purpose-built assembly hall and load path. Cost reference: Defence has committed $12 billion of early works and infrastructure at the Henderson Defence Precinct against a total infrastructure estimate of about $25 billion for shipyard halls, docks and berths of this class. Diligence still owes title, tenure, zoning, contamination, acid-sulfate soils, geotechnical conditions, biodiversity, cultural heritage, Native Title and neighbour checks, plus hall geometry and the full hall-to-water load path.

[Source 64](#au-src-64)

Esperance · Electrical load · Fail

Esperance is an islanded system. The Western Australian Government defines the SWIS as stretching from Kalbarri in the north to Albany in the south and Kalgoorlie in the east, which excludes Esperance. Esperance runs on a town hybrid system of 43.6 MW in total - a 4 MW solar farm, two 4.5 MW wind turbines, a 5.6 MW battery and a 22 MW gas station - built for Horizon Power under a build-own-operate agreement and commissioned in 2022 under a 20-year power purchase agreement. A 150 MW load is more than three times the entire local system and no interconnection is planned.

[Source 15](#au-src-15), [Source 16](#au-src-16)

Esperance · Workforce · Not known

No regional heavy-fabrication base is documented at Esperance - the port trades iron ore, grain, spodumene, fuel, sulphur, woodchips, fertiliser, copper concentrate, nickel and containers with 125 local staff - and no named training, attraction or housing programme with a cost reference for the Goldfields-Esperance region was found.

[Source 62](#au-src-62)

Fremantle Inner Harbour · Flip depth · Pass

The Inner Harbour Entrance Channel takes 350 m LOA, 48 m beam and up to 14.7 m draft with DUKC above 13.5 m, and Perth Canyon Marine Park at 120 m to 5,000 m lies 19 km west of Rottnest Island. Depth and channel geometry are not the binding constraint at Fremantle. Diligence still owes the modelled tow geometry - node and tug draft, towline, under-keel allowance, turns, currents, pilotage and abort areas - and a certified primary and backup polygon.

[Source 6](#au-src-6)

Fremantle Inner Harbour · Load-out quay · Remediable

Fremantle Ports lists every Inner Harbour berth by use - container terminals CT1 to CT4, general cargo at North Quay 1, 2, 11 and 12, lay-up at C, D and E, cruise and general cargo at F and G, RoRo at H - with bollards of 35 t to 100 t and declared depths of 8.5 m to 14.5 m. No Inner Harbour berth carries a load-out or heavy-lift designation or a transfer rating. Waterfront exists at the Rous Head and North Quay planning precincts, so a heavy quay build is the named work. Cost reference: the Lumsden Point common-user development at Port Hedland delivers two new multi-user wharves including a heavy-lift land-backed wharf for $450 million from the Commonwealth and $96.6 million from Western Australia, with imports from mid-2026\. Diligence still owes the engineering drawings, SPMT route, deck and line loads, bollard loads and verified transfer limits at 3,000, 4,000 and 5,000 tonnes.

[Source 8](#au-src-8)

Fremantle Inner Harbour · Node hall · Not known

No available, zoned, unencumbered waterfront parcel at Fremantle was documented either way. The Inner Harbour land in the port's own guide is allocated to container, cruise, RoRo, general cargo and lay-up operations, and the Fremantle Ports planning-precinct pages for North Quay, Rous Head and Victoria Quay, and its leasing and land page, all returned HTTP 404 on 2026-08-23\. No hall geometry, floor loading or load path is published.

[Source 8](#au-src-8)

Fremantle Inner Harbour · Electrical load · Fail

Western Power's Transmission System Plan 2025 places Fremantle in the Southern Terminal and metropolitan load areas, where it states reliability of supply limitations may arise across the 10-year period and that the options it is developing are CEL Metro and CEL Chittering. CEL Metro 2 is Fixed for 2036 with timing under review, CEL Chittering is only a Candidate for 2033, and CEL Perth Circuit is only a Candidate for 2030\. The Western Australian Government's own Phase One for 2025 to 2030 comprises CEL North and CEL East. No named project delivers 50 MW or more of new load capacity to a Fremantle connection point inside the window.

[Source 11](#au-src-11), [Source 56](#au-src-56)

Fremantle Inner Harbour · Workforce · Remediable

Fremantle shares the Perth metropolitan trades pool that the Henderson Defence Precinct is committing at more than 10,000 jobs over two decades, against a national shortfall of at least 70,000 welders by 2030 that Weld Australia estimates. The named, costed offset is $11.4 million over three years for the Western Australian Defence Industry Pathways Program inside a nearly $150 million Commonwealth AUKUS skills package. Diligence still owes an annual occupation-level demand and supply model with committed defence, steel, energy and infrastructure demand deducted.

[Source 14](#au-src-14)

Civmec Tomago/Newcastle · Flip depth · Pass

The CC BY 4.0 AusBathyTopo screening grid shows open-water depths of at least 120 m within about 200 km of Civmec Newcastle, with no bridge, lock or overhead-line barrier on the screened seaward route. Confirm two polygons and the full tow geometry with licensed AHO data.

[Source 74](#au-src-74)

Civmec Tomago/Newcastle · Load-out quay · Remediable

Build a dedicated heavy load-out quay, reinforced apron and SPMT route for 3,000, 4,000 and 5,000 t cases at Civmec Newcastle; use the public Jervoise Bay A$53.2 million 2001 civil-and-marine contract as the cost reference, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 9](#au-src-9)

Civmec Tomago/Newcastle · Node hall · Remediable

Build the node hall, supports, doors, apron and full hall-to-water path on the documented industrial waterfront at Civmec Newcastle; use the ANAO A$457 million 2017 Osborne surface-shipyard contract as the public cost envelope, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 10](#au-src-10)

Civmec Tomago/Newcastle · Electrical load · Not known

No public source identifies 50 MW of available capacity at a Tomago connection point by 2027, or a named costed load augmentation delivering 50-150 MW there by 2030\. Transgrid's A$259 million Hunter region REZ line is a proposed contingent project for generation, not load, and Transgrid states the NSW cost-recovery framework for it was not finalised. Request a Transgrid connection enquiry and studies for 50, 100 and 150 MW at Tomago 132 kV in 2027 and 2030.

[Source 17](#au-src-17)

Civmec Tomago/Newcastle · Workforce · Pass

Newcastle and the Hunter has a documented heavy-industry or manufacturing labour base and a current training pathway. No public source shows full labour absorption by 2030\. Complete the occupation-by-year demand model before investment.

[Source 82](#au-src-82)

Hobart/Prince of Wales Bay · Flip depth · Not known

Public port material does not resolve the design-case air draft under the Tasman Bridge or certify two 120 m polygons.

[Source 78](#au-src-78)

Hobart/Prince of Wales Bay · Load-out quay · Remediable

Build a dedicated heavy load-out quay, reinforced apron and SPMT route for 3,000, 4,000 and 5,000 t cases at Prince of Wales Bay; use the public Jervoise Bay A$53.2 million 2001 civil-and-marine contract as the cost reference, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 9](#au-src-9)

Hobart/Prince of Wales Bay · Node hall · Remediable

Build the node hall, supports, doors, apron and full hall-to-water path on the documented industrial waterfront at Prince of Wales Bay; use the ANAO A$457 million 2017 Osborne surface-shipyard contract as the public cost envelope, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 10](#au-src-10)

Hobart/Prince of Wales Bay · Electrical load · Not known

TasNetworks does not identify 50 MW by 2027 or a named costed Prince of Wales Bay augmentation closing 50 to 150 MW by 2030.

[Source 27](#au-src-27)

Hobart/Prince of Wales Bay · Workforce · Remediable

Reserve and target A$12.6 million of the cited programme for the required trades, engineers, mariners and supervisors at Hobart; add employer attraction and housing actions, start in 2027, and deliver the cohorts by 2029.

[Source 31](#au-src-31)

Mackay/Hay Point · Flip depth · Pass

The CC BY 4.0 AusBathyTopo screening grid shows open-water depths of at least 120 m within about 200 km of Mackay/Hay Point, with no bridge, lock or overhead-line barrier on the screened seaward route. Confirm two polygons and the full tow geometry with licensed AHO data.

[Source 74](#au-src-74)

Mackay/Hay Point · Load-out quay · Remediable

Build a dedicated heavy load-out quay, reinforced apron and SPMT route for 3,000, 4,000 and 5,000 t cases at Mackay/Hay Point; use the public Jervoise Bay A$53.2 million 2001 civil-and-marine contract as the cost reference, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 9](#au-src-9)

Mackay/Hay Point · Node hall · Remediable

Build the node hall, supports, doors, apron and full hall-to-water path on the documented industrial waterfront at a secured Mackay/Hay Point port parcel; use the ANAO A$457 million 2017 Osborne surface-shipyard contract as the public cost envelope, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 10](#au-src-10)

Mackay/Hay Point · Electrical load · Not known

No public source identifies 50 MW of available capacity at a Mackay or Hay Point connection point by 2027, or a named costed augmentation delivering 50-150 MW there by 2030\. Powerlink's A$34 million Alligator Creek work is a condition-driven replacement of 1982-vintage 132 kV primary plant and 132 kV and SVC secondary systems by December 2030; it restores existing supply to loads of up to 70 MW and adds no new capacity. Request Powerlink connection studies for 50, 100 and 150 MW at Alligator Creek 132 kV in 2027 and 2030.

[Source 19](#au-src-19)

Mackay/Hay Point · Workforce · Remediable

Reserve and target A$5.06 million of the cited programme for the required trades, engineers, mariners and supervisors at Mackay/Hay Point; add employer attraction and housing actions, start in 2027, and deliver the cohorts by 2029.

[Source 85](#au-src-85)

Port Kembla · Flip depth · Pass

The CC BY 4.0 AusBathyTopo screening grid shows open-water depths of at least 120 m within about 200 km of Port Kembla Outer Harbour, with no bridge, lock or overhead-line barrier on the screened seaward route. Confirm two polygons and the full tow geometry with licensed AHO data.

[Source 74](#au-src-74)

Port Kembla · Load-out quay · Remediable

Build a dedicated heavy load-out quay, reinforced apron and SPMT route for 3,000, 4,000 and 5,000 t cases at Port Kembla Outer Harbour; use the public Jervoise Bay A$53.2 million 2001 civil-and-marine contract as the cost reference, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 9](#au-src-9)

Port Kembla · Node hall · Remediable

Build the node hall, supports, doors, apron and full hall-to-water path on the documented industrial waterfront at Port Kembla Outer Harbour; use the ANAO A$457 million 2017 Osborne surface-shipyard contract as the public cost envelope, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 10](#au-src-10)

Port Kembla · Electrical load · Not known

No public source identifies 50 MW of available capacity at a Port Kembla Outer Harbour connection point by 2027, or a named costed load augmentation delivering 50-150 MW there by 2030\. Transgrid's A$259 million Illawarra region REZ line is a proposed contingent project for generation, declared by the Minister under s19(1) of the Electricity Infrastructure Investment Act 2020, and Transgrid states the NSW cost-recovery framework for it was not finalised. Request a Transgrid connection enquiry and studies for 50, 100 and 150 MW at Dapto in 2027 and 2030.

[Source 17](#au-src-17)

Port Kembla · Workforce · Pass

Port Kembla and the Illawarra has a documented heavy-industry or manufacturing labour base and a current training pathway. No public source shows full labour absorption by 2030\. Complete the occupation-by-year demand model before investment.

[Source 82](#au-src-82)

Portland · Flip depth · Pass

The CC BY 4.0 AusBathyTopo screening grid shows open-water depths of at least 120 m within about 200 km of Portland, with no bridge, lock or overhead-line barrier on the screened seaward route. Confirm two polygons and the full tow geometry with licensed AHO data.

[Source 74](#au-src-74)

Portland · Load-out quay · Remediable

Build a dedicated heavy load-out quay, reinforced apron and SPMT route for 3,000, 4,000 and 5,000 t cases at Portland; use the public Jervoise Bay A$53.2 million 2001 civil-and-marine contract as the cost reference, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 9](#au-src-9)

Portland · Node hall · Remediable

Build the node hall, supports, doors, apron and full hall-to-water path on the documented industrial waterfront at Portland; use the ANAO A$457 million 2017 Osborne surface-shipyard contract as the public cost envelope, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 10](#au-src-10)

Portland · Electrical load · Not known

The VAPR documents the dedicated Alcoa 500 kV line and renewal needs, but no public source identifies spare 50 MW by 2027 or a costed 50 to 150 MW Portland augmentation by 2030.

[Source 28](#au-src-28)

Portland · Workforce · Pass

Portland and south-west Victoria has a documented heavy-industry or manufacturing labour base and a current training pathway. No public source shows full labour absorption by 2030\. Complete the occupation-by-year demand model before investment.

[Source 79](#au-src-79)

Australian Maritime College, Launceston · Flip depth · Not known

No public source addresses a full-size Newnham-to-sea tow geometry, Batman Bridge clearance for the design cases, or two 120 m polygons.

[Source 77](#au-src-77)

Australian Maritime College, Launceston · Load-out quay · Not known

AMC documents research and training facilities, but no rated Newnham industrial quay, ramp, SPMT route or 3,000 to 5,000 t load path.

[Source 77](#au-src-77)

Australian Maritime College, Launceston · Node hall · Fail

The Newnham zone is for tertiary education, research and related accommodation, while AMC documents research facilities rather than a serial factory. No industrial rezoning and waterfront conversion programme can deliver this location by 2030.

[Source 25](#au-src-25), [Source 77](#au-src-77)

Australian Maritime College, Launceston · Electrical load · Not known

No public source addresses a 50, 100 or 150 MW Newnham industrial connection for 2027 or 2030.

[Source 27](#au-src-27)

Australian Maritime College, Launceston · Workforce · Remediable

Reserve and target A$12.6 million of the cited programme for the required trades, engineers, mariners and supervisors at Launceston; add employer attraction and housing actions, start in 2027, and deliver the cohorts by 2029.

[Source 31](#au-src-31)

Melbourne Victoria Dock · Flip depth · Not known

Public sources do not resolve design-case clearance beneath the West Gate Bridge or certify two 120 m polygons.

[Source 80](#au-src-80)

Melbourne Victoria Dock · Load-out quay · Remediable

Build a dedicated heavy load-out quay, reinforced apron and SPMT route for 3,000, 4,000 and 5,000 t cases at Victoria Dock; use the public Jervoise Bay A$53.2 million 2001 civil-and-marine contract as the cost reference, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 9](#au-src-9)

Melbourne Victoria Dock · Node hall · Fail

The precinct control caps normal wall height at 20 m and requires a 15 m berth setback; the City inventory classifies Victoria Dock as significant heritage. No adopted programme removes these combined limits by 2030.

[Source 26](#au-src-26), [Source 81](#au-src-81)

Melbourne Victoria Dock · Electrical load · Remediable

Build the Western Metropolitan reinforcement and a dock connection; use AEMO's A$128 million option and five-year lead time, and commission by 2030.

[Source 42](#au-src-42)

Melbourne Victoria Dock · Workforce · Pass

metropolitan Melbourne has a documented heavy-industry or manufacturing labour base and a current training pathway. No public source shows full labour absorption by 2030\. Complete the occupation-by-year demand model before investment.

[Source 79](#au-src-79)

Osborne and Port Adelaide · Flip depth · Fail

The Osborne berths sit in Port Adelaide's Inner Harbour, which Flinders Ports limits to 206 m LOA, 32.2 m beam and 9.3 m maintained depth below lowest astronomical tide, with a 330 m swing basin; even Outer Harbor is limited to 350 m LOA and 14.2 m. Gulf St Vincent is an enclosed gulf and the nearest Commonwealth-mapped water reaching 120 m is the 90 m to 120 m escarpment in Western Kangaroo Island Marine Park, 230 km south-west of Adelaide beyond Backstairs Passage, outside a single open-water tow. No primary or backup flip polygon is reachable.

[Source 23](#au-src-23), [Source 71](#au-src-71)

Osborne and Port Adelaide · Load-out quay · Not known

Flinders Ports publishes wharf hard-stand, wharf height and berth-box dimensions for Port Adelaide but no design displacement, bollard rating or transfer limit for the Osborne berths, which sit under the 206 m LOA and 32.2 m beam Inner Harbour limit. Whether the Osborne shipyard's own launch infrastructure is rated at or above 3,000 t is not addressed in any public document reached.

[Source 23](#au-src-23)

Osborne and Port Adelaide · Node hall · Fail

The waterfront land is committed. The Australian Submarine Agency's preferred Submarine Construction Yard site is north of the existing Osborne Naval Shipyard on the Lefevre Peninsula, and Australian Naval Infrastructure states that more than 50 new structures will be built across a site of more than 100 hectares with construction spanning more than a decade. The South Australian Minister for Planning approved the impact-assessed development on 4 December 2025 and the Commonwealth issued an EPBC strategic-assessment approval decision notice on 19 February 2026\. The parcel, its approvals and its launch berth are legally committed to the nuclear-powered submarine programme through the window.

[Source 24](#au-src-24), [Source 72](#au-src-72)

Osborne and Port Adelaide · Electrical load · Not known

No South Australian network planning document could be read: ElectraNet's TAPR page returns HTTP 404 and the 2026 TAPR PDF returned an HTML document on 2026-08-23\. Preliminary enabling works are relocating utilities to maintain power to the Osborne Naval Shipyards, but no available capacity, voltage, works or lead time for a third-party load is published.

[Source 24](#au-src-24)

Osborne and Port Adelaide · Workforce · Remediable

Osborne has a documented regional shipbuilding base and the named, costed instrument is the Skills and Training Academy being co-designed by the Commonwealth and South Australia, with a campus built close to the Osborne Submarine Construction Yard and training delivered from 2028, inside a nearly $150 million Commonwealth AUKUS skills package that includes $128.5 million for 4,000 university places. The demand it must serve is the submarine programme itself, and Weld Australia estimates Australia will be at least 70,000 welders short by 2030\. Diligence still owes an annual occupation-level demand and supply model with committed defence, steel, energy and infrastructure demand deducted.

[Source 14](#au-src-14)

Eden · Flip depth · Pass

The CC BY 4.0 AusBathyTopo screening grid shows open-water depths of at least 120 m within about 200 km of Eden, with no bridge, lock or overhead-line barrier on the screened seaward route. Confirm two polygons and the full tow geometry with licensed AHO data.

[Source 74](#au-src-74)

Eden · Load-out quay · Remediable

Build a dedicated heavy load-out quay, reinforced apron and SPMT route for 3,000, 4,000 and 5,000 t cases at Eden; use the public Jervoise Bay A$53.2 million 2001 civil-and-marine contract as the cost reference, obtain a 2026 quantity-surveyor update, and commission by 2030.

[Source 9](#au-src-9)

Eden · Node hall · Not known

No public source identifies a secure, suitably zoned Eden waterfront parcel with expansion space and a full hall-to-water path.

[Source 29](#au-src-29)

Eden · Electrical load · Not known

No public source identifies 50 MW Eden capacity by 2027 or a named costed augmentation delivering 50 to 150 MW by 2030.

[Source 83](#au-src-83)

Eden · Workforce · Not known

No public source addresses net annual Eden labour and housing supply for all required occupations after committed demand.

[Source 84](#au-src-84)

Karratha and Port of Dampier · Flip depth · Fail

The Port of Dampier sits on the shallow North West Shelf. Dampier Marine Park, 10 km north-east of Cape Lambert, runs from under 15 m to 70 m with an average depth of 22 m, and the port's own declared depths span 3.6 m to 20.7 m, with the Facilities Channel at 11.0 m and the Rio Tinto Channel at 15.8 m. No water at or beyond 120 m is reachable within a practical open-water tow, so neither a primary nor a backup flip polygon can be identified.

[Source 21](#au-src-21), [Source 65](#au-src-65)

Karratha and Port of Dampier · Load-out quay · Remediable

The Port of Dampier's Heavy Loadout Wharf is declared at 6.0 m depth, the Dampier Cargo Wharf at 7.2 m on the east face and 10.0 m on the west face, and the Bulk Liquid Berth at 13.0 m, none with a published design displacement, bollard rating or transfer limit. Dampier waterfront is available and Pilbara Ports has delivered a comparable facility, so a heavy quay build is the named work. Cost reference: the Lumsden Point common-user development at Port Hedland delivers two new multi-user wharves including a heavy-lift land-backed wharf for $450 million from the Commonwealth and $96.6 million from Western Australia, with imports from mid-2026\. Diligence still owes the engineering drawings, SPMT route, deck and line loads, bollard loads and verified transfer limits at 3,000, 4,000 and 5,000 tonnes.

[Source 65](#au-src-65)

Karratha and Port of Dampier · Node hall · Not known

No available, zoned, unencumbered industrial waterfront parcel at Dampier or Karratha with published title, tenure, contamination, Native Title and expansion status was found, and no hall geometry or load path is published. Commonwealth common-user port investment in the Pilbara, $565 million in total, is directed to Lumsden Point at Port Hedland rather than to Dampier.

[Source 66](#au-src-66)

Karratha and Port of Dampier · Electrical load · Not known

Karratha is outside the SWIS, which the Western Australian Government defines as running from Kalbarri to Albany and east to Kalgoorlie; the Pilbara is served by the separate North West Interconnected System. No North West Interconnected System planning document was read inside the budget, so available capacity at a Dampier connection point is not addressed either way.

[Source 67](#au-src-67)

Karratha and Port of Dampier · Workforce · Not known

No regional heavy-fabrication base for ship or module work at Karratha is documented, and no named training, attraction or housing programme with a cost reference for the Pilbara marine trades was found. Jobs and Skills Australia publishes state and regional shortage ratings but no Karratha net position after committed iron ore and LNG demand was derived.

[Source 62](#au-src-62)

Whyalla · Flip depth · Fail

Whyalla sits at the head of Upper Spencer Gulf, an enclosed gulf. Flinders Ports runs the Spencer Gulf Deep Water Pilotage Network purely to move Cape-size bulk carriers between the Whyalla offshore transhipment point and the open sea, with pilotage required at 16.0 m draft or more, which is the deepest water that route serves. The nearest Commonwealth-mapped water reaching 120 m is the 90 m to 120 m escarpment in Western Kangaroo Island Marine Park, 230 km south-west of Adelaide and roughly 600 km by sea from Whyalla. No flip polygon is reachable within a practical tow.

[Source 22](#au-src-22), [Source 68](#au-src-68)

Whyalla · Load-out quay · Remediable

The Whyalla wharf is a steelworks and transhipment facility with no published design displacement, bollard rating, SPMT route or transfer limit. Upper Spencer Gulf waterfront exists alongside the steelworks, so a heavy quay build is the named work. Cost reference: the Lumsden Point common-user development at Port Hedland delivers two new multi-user wharves including a heavy-lift land-backed wharf for $450 million from the Commonwealth and $96.6 million from Western Australia, with imports from mid-2026\. Diligence still owes the engineering drawings, SPMT route, deck and line loads, bollard loads and verified transfer limits at 3,000, 4,000 and 5,000 tonnes.

[Source 69](#au-src-69)

Whyalla · Node hall · Not known

No available, zoned, unencumbered waterfront parcel at Whyalla was documented. The steelworks site is encumbered: OneSteel Manufacturing has been in administration since 19 February 2025 and $1.9 billion of the $2.4 billion Commonwealth and South Australian package is reserved for upgrades and new infrastructure to be settled with a new owner who does not yet exist.

[Source 70](#au-src-70)

Whyalla · Electrical load · Not known

No South Australian network planning document could be read. ElectraNet's transmission annual planning report page returns HTTP 404 and the 2026 TAPR PDF returned an HTML document rather than the report on 2026-08-23\. The Commonwealth and State package earmarks infrastructure spending under a future owner but publishes no connection voltage, works, capacity, cost or lead time.

[Source 70](#au-src-70)

Whyalla · Workforce · Remediable

Whyalla has a documented regional heavy-industry base - the steelworks employs 1,100 workers and supports more than 2,000 indirectly, produces 75 per cent of Australian structural steel and is the only domestic producer of long steel products - and the named, costed instrument is the $6 million Jobs Matching and Skills Hub inside the $100 million of immediate on-the-ground support in the $2.4 billion package. Diligence still owes an annual occupation-level demand and supply model with committed defence, steel, energy and infrastructure demand deducted.

[Source 70](#au-src-70)

 8 of the 23 sites clear every gate. The other 15 sit below the rule, grouped by the gate that removed them, with the electrical load gate first. The numbers beside each site are this page's numbered sources. A failed gate rests on two of them, the finding and an independent corroboration. Select any gate mark to read its note. 

3 

## Chapter 3\. Why fifteen sites have no score 

Fifteen sites leave before scoring, nine of them on the electricity gate. They are not all weak ones: Port Kembla and Civmec Tomago clear every other gate.

Port Kembla and Civmec Tomago clear four of the five gates. Both have water deep enough for the flip within tow range, and both pass the workforce gate, which only eight of the 23 sites do. Both fall on the fifth. Transgrid's 2021 revenue proposal includes an allowance of A$259 million for the Hunter renewable energy zone, where Tomago sits, triggered by more than 1,000 MW of new generation.[17](#au-src-17)17 [Transgrid 2023-28 preliminary revenue proposal](https://www.transgrid.com.au/media/kc0jhnnj/2023-28-preliminary-revenue-proposal%5F5-oct-2021.pdf), Transgrid, 5 October 2021. That allowance is for hosting generators and offers no headroom to a factory. Port Kembla sits in the Illawarra, where EnergyCo's declared zone is also a generation zone under the Electricity Infrastructure Investment Act 2020.[18](#au-src-18)18 [Illawarra Renewable Energy Zone](https://www.energyco.nsw.gov.au/renewable-energy-zones/illawarra-renewable-energy-zone), EnergyCo NSW, accessed 23 August 2026. No document shows room for a factory's load at either site, so both are unknown.

Mackay is unknown for a similar reason. Powerlink's 2025 planning report lists A$34 million of works at Alligator Creek. It cites condition risk in 132 kV primary plant dating from 1982, due for replacement by December 2030.[19](#au-src-19)19 [Transmission Annual Planning Report 2025](https://www.powerlink.com.au/sites/default/files/2025-12/Transmission%20Annual%20Planning%20Report%202025.pdf), Powerlink Queensland, December 2025. The 70 MW in that entry is existing load kept supplied, not new capacity on offer. No Powerlink document identifies 50 MW as available at Mackay or Hay Point by 2027, and none says the pathway is closed, so the verdict is unknown, not fail.

Bunbury is the only one of the four that fails outright. Western Power's Transmission System Plan 2025 dates Clean Energy Link East Stage 1 to 2029 at the earliest and places the Kemerton project about 20 km inland. Neither is at the port. The plan lists the Bunbury Harbour zone substation with 65 MW of planning capacity, already at 120% utilisation and rising to 144%.[11](#au-src-11)11 [Transmission System Plan 2025 (Draft)](https://www.westernpower.com.au/495bb8/siteassets/documents/nom/transmission-system-plan-2025-draft.pdf), Western Power, March 2026. A second publisher, the Western Australian Government, says the same in its SWIS Transmission Plan.[20](#au-src-20)20 [SWIS Transmission Plan](https://www.wa.gov.au/media/155887/download?inline=), Government of Western Australia, October 2025. A large load at Bunbury must connect at transmission level, or not at all.

Three sites fail on water. Karratha has no flip polygon within reach: Dampier Marine Park runs from under 15 m to 70 m deep with an average of 22 m, and the Port of Dampier's declared depths span 3.6 m to 20.7 m.[21](#au-src-21)21 [Dampier Marine Park](https://parksaustralia.gov.au/marine/parks/north-west/dampier/), Parks Australia, accessed 23 August 2026. Whyalla sits at the head of an enclosed gulf. Its nearest Commonwealth-mapped 120 m water is the escarpment in Western Kangaroo Island Marine Park, roughly 600 km away by sea.[22](#au-src-22)22 [Western Kangaroo Island Marine Park](https://parksaustralia.gov.au/marine/parks/south-west/western-kangaroo-island/), Parks Australia, accessed 23 August 2026. Osborne fails on that same escarpment, reached out of Gulf St Vincent from an inner harbour capped at 9.3 m.[23](#au-src-23)23 [Port Adelaide](https://www.flindersports.com.au/port-adelaide/), Flinders Port Holdings, accessed 23 August 2026.

Three more fail on load. Fremantle's named remedy, Clean Energy Link Metro 2, is set for 2036, and its timing is under review. Albany's zone substation has 60 MW of planning capacity, running at 103% utilisation in year one and 133% by year ten; it is fed radially from Muja, with no Clean Energy Link project serving the Great Southern.[11](#au-src-11)11 [Transmission System Plan 2025 (Draft)](https://www.westernpower.com.au/495bb8/siteassets/documents/nom/transmission-system-plan-2025-draft.pdf), Western Power, March 2026. Esperance is not on the interconnected system at all.[15](#au-src-15)15 [Esperance Hybrid Power System](https://pacificenergy.com.au/project/esperance-power-station-renewables-hub/), Pacific Energy, accessed 23 August 2026.

Three fail on the hall, and in each case the obstacle is legal, not physical. North of Osborne, the Australian Submarine Agency's preferred construction yard commits more than 100 hectares. The South Australian Minister for Planning approved it on 4 December 2025 and the Commonwealth on 19 February 2026.[24](#au-src-24)24 [Osborne Submarine Construction Yard](https://www.asa.gov.au/projects/osborne-submarine-construction-yard), Australian Submarine Agency, 25 February 2026. The Australian Maritime College's Newnham campus is zoned for tertiary education.[25](#au-src-25)25 [Launceston LPS, Particular Purpose Zone, University of Tasmania Newnham Campus](https://www.launceston.tas.gov.au/files/assets/public/v/1/document-resources/agenda-and-minutes/agendas/2013-2022-archive/2019/5-september-2019/council-agenda-agenda-item-15.3-attachment-1-appendix-18-transitioning-ppzs-5-september-2019.pdf), City of Launceston, 5 September 2019. Victoria Dock has a 20 m wall-height cap, a 15 m berth setback and a significant heritage listing.[26](#au-src-26)26 [Port of Melbourne planning scheme, Victoria Dock Precinct](https://planning-schemes.app.planning.vic.gov.au/Port%20of%20Melbourne/histories/VC292/ordinance/16186723), Victorian Department of Transport and Planning, 10 September 2025.

Hobart, Portland and Eden leave because the documents say nothing either way. That tells you about the documents, not the sites.[27](#au-src-27)27 [Annual Planning Report 2025](https://www.tasnetworks.com.au/config/getattachment/cc67a45e-647e-4012-a5d7-efa631a8968c/tn-apr-2025.pdf), TasNetworks, October 2025.[28](#au-src-28)28 [2025 Victorian Annual Planning Report](https://www.vicgrid.com.au/%5F%5Fdata/assets/pdf%5Ffile/0039/769098/2025-victorian-annual-planning-report.pdf), AEMO Victorian Planning, November 2025.[29](#au-src-29)29 [Harbour Master's Directions: Eden](https://www.portauthoritynsw.com.au/sites/default/files/2025-05/Harbour%20Masters%20Directions%20Eden.pdf), Port Authority of New South Wales, 12 May 2025. Eight sites remain, and every gap across them is named and costed.

1. [Transgrid 2023-28 preliminary revenue proposal](https://www.transgrid.com.au/media/kc0jhnnj/2023-28-preliminary-revenue-proposal%5F5-oct-2021.pdf), Transgrid, 5 October 2021\.
2. [Illawarra Renewable Energy Zone](https://www.energyco.nsw.gov.au/renewable-energy-zones/illawarra-renewable-energy-zone), EnergyCo NSW, accessed 23 August 2026\.
3. [Transmission Annual Planning Report 2025](https://www.powerlink.com.au/sites/default/files/2025-12/Transmission%20Annual%20Planning%20Report%202025.pdf), Powerlink Queensland, December 2025\.
4. [SWIS Transmission Plan](https://www.wa.gov.au/media/155887/download?inline=), Government of Western Australia, October 2025\.
5. [Dampier Marine Park](https://parksaustralia.gov.au/marine/parks/north-west/dampier/), Parks Australia, accessed 23 August 2026\.
6. [Western Kangaroo Island Marine Park](https://parksaustralia.gov.au/marine/parks/south-west/western-kangaroo-island/), Parks Australia, accessed 23 August 2026\.
7. [Port Adelaide](https://www.flindersports.com.au/port-adelaide/), Flinders Port Holdings, accessed 23 August 2026\.
8. [Osborne Submarine Construction Yard](https://www.asa.gov.au/projects/osborne-submarine-construction-yard), Australian Submarine Agency, 25 February 2026\.
9. [Launceston LPS, Particular Purpose Zone, University of Tasmania Newnham Campus](https://www.launceston.tas.gov.au/files/assets/public/v/1/document-resources/agenda-and-minutes/agendas/2013-2022-archive/2019/5-september-2019/council-agenda-agenda-item-15.3-attachment-1-appendix-18-transitioning-ppzs-5-september-2019.pdf), City of Launceston, 5 September 2019\.
10. [Port of Melbourne planning scheme, Victoria Dock Precinct](https://planning-schemes.app.planning.vic.gov.au/Port%20of%20Melbourne/histories/VC292/ordinance/16186723), Victorian Department of Transport and Planning, 10 September 2025\.
11. [Annual Planning Report 2025](https://www.tasnetworks.com.au/config/getattachment/cc67a45e-647e-4012-a5d7-efa631a8968c/tn-apr-2025.pdf), TasNetworks, October 2025\.
12. [2025 Victorian Annual Planning Report](https://www.vicgrid.com.au/%5F%5Fdata/assets/pdf%5Ffile/0039/769098/2025-victorian-annual-planning-report.pdf), AEMO Victorian Planning, November 2025\.
13. [Harbour Master's Directions: Eden](https://www.portauthoritynsw.com.au/sites/default/files/2025-05/Harbour%20Masters%20Directions%20Eden.pdf), Port Authority of New South Wales, 12 May 2025\.

4 

## Chapter 4\. How the score is built 

The weights are my judgement of what a factory needs, not the company's. They are printed here so you can disagree with the arithmetic.

Each surviving site gets a mark from 0 to 5 on ten dimensions, with weights that add to 100\. Workforce has 20 points and grid headroom 15\. Channel and flip site have 12.5 each, and fabrication precedent, land and regulatory have 10 each. Habitability has 5, with state support and federal funding at 2.5 each.

Marine access and fabrication capacity take 45 points of the total, electricity and people take 35, regulatory and habitability take 15, and public money takes 5\. That split is my judgement, and the company has published none of its own.

To calculate a site's total, multiply each weight by its mark, divide by five, and add the ten results. A site that scores 5 on everything gets 100, and Bell Bay's ten marks come to 69.0 under these weights.

The top four sites are within 4.5 points of each other, so a different weighting would reorder them. I did not run a sensitivity analysis on the weights. If you think workforce deserves 30 points, you can re-run the sum from the matrix below, where every mark is printed and every note names its document. Or drag workforce to 30 in the exhibit underneath and watch the order change. The weights cannot change the gate table above, though. A site that fails a gate, or is unknown on one, has no score to weight.

Workforce and grid headroom decide 35 of the 100 points

 Marks out of 5 on ten weighted dimensions for the eight scored sites, column width proportional to weight · Source: Score, note and source per cell, site screening record 

Mark out of 5 weakest 012345 strongest 

Swipe to compare all ten dimensions

__Weighted score out of 100 for the eight sites that clear all five gates, on ten weighted dimensions.__
| Site                                  | Rank      | Total | land                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                     | channel                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                            | fab. precedent                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           | flip site                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                | state                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                | federal                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                  | workforce                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                     | grid headroom                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         | regulatory                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                        | habit­ability                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                            |
| ------------------------------------- | --------- | ----- | -------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- | -------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- | ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ | -------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- | ---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- | -------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- | ----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- | ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- | --------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- | ------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ |
| Weight                                | no weight | 100   | 10                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                       | 12.5                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                               | 10                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                       | 12.5                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                     | 2.5                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                  | 2.5                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                      | 20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                            | 15                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                    | 10                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                | 5                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                        |
| Bell Bay                              | 1         | 69    | Bell Bay · Land · 4 of 5 TasPorts maps industrial development land beside a major industrial estate and seven berths, but gives no parcel title, zoning or constraint record. [Source 30](#au-src-30): Bell Bay port information, TasPorts.                                                                                                                                                                                                                                                                                                                                                              | Bell Bay · Channel · 3 of 5 AusBathyTopo provides a 250 m depth model for regional screening, but no Tamar-specific proof of tow turns, traffic, clearance or weather windows. [Source 74](#au-src-74): AusBathyTopo 250m (Australia) 2023 Grid, Geoscience Australia.                                                                                                                                                                                                                                                                             | Bell Bay · Fabrication precedent · 4 of 5 The port adjoins an industrial estate with Bell Bay Aluminium, OneSteel, Temco and Sims Metal, but the page does not show serial offshore-module output. [Source 30](#au-src-30): Bell Bay port information, TasPorts.                                                                                                                                                                                                                                                                                                                                                                                                         | Bell Bay · Flip site · 4 of 5 The 250 m depth grid supports a regional deep-water search from Bell Bay, but it does not certify either a primary or backup 120 m flip polygon. [Source 74](#au-src-74): AusBathyTopo 250m (Australia) 2023 Grid, Geoscience Australia.                                                                                                                                                                                                                                                                                                                                   | Bell Bay · State support · 3 of 5 Tasmania offered A$12.6 million to support up to 6,000 learners in 2025, but the programme gives Bell Bay no negotiated delivery package. [Source 31](#au-src-31): Making training more affordable to deliver a skilled workforce, Tasmanian Government.                                                                                                                                                                                                                                                                                                                                                                                                           | Bell Bay · Federal funding · 2 of 5 NRFC priorities include transport, renewables and industrial manufacturing, but the page records no Bell Bay eligibility decision, value or offer. [Source 76](#au-src-76): Our priority areas, National Reconstruction Fund Corporation.                                                                                                                                                                                                                                                                                                                                                                                                                                                                            | Bell Bay · Workforce · 4 of 5 The A$12.6 million programme can support up to 6,000 Tasmanian learners; it does not quantify Bell Bay trades after committed demand or housing limits. [Source 31](#au-src-31): Making training more affordable to deliver a skilled workforce, Tasmanian Government.                                                                                                                                                                                                                                                                                                                          | Bell Bay · Grid headroom · 3 of 5 TasNetworks costs an A$135 million George Town upgrade with a new Bell Bay substation for new load, but gives no factory capacity reservation. [Source 12](#au-src-12): TasNetworks Annual Planning Report 2024, TasNetworks.                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                       | Bell Bay · Regulatory · 3 of 5 TasPorts documents an operating bulk and container port beside an industrial estate, but not the factory, marine, environment or autonomy approvals. [Source 30](#au-src-30): Bell Bay port information, TasPorts.                                                                                                                                                                                                                                                                                                                                                                                 | Bell Bay · Habitability · 2 of 5 The statewide training programme does not document Bell Bay housing, schools, health, airport access or executive relocation conditions. [Source 31](#au-src-31): Making training more affordable to deliver a skilled workforce, Tasmanian Government.                                                                                                                                                                                                                                                                                 |
| Kwinana and Cockburn Sound            | 2         | 66    | Kwinana and Cockburn Sound · Land · 4 of 5 Five AMC precincts on Western Australian Government land in Perth's premier industrial corridor, with significant land reserved for high-tech industry and the Marine Industry Technology Park adjacent, backed onto the Kwinana Industrial Area. No parcel-level title, zoning, contamination or Native Title record was sourced, and the Kwinana strip carries heavy industrial neighbours. [Source 33](#au-src-33): Australian Marine Complex - About, DevelopmentWA.                                                                                      | Kwinana and Cockburn Sound · Channel · 3 of 5 Sheltered Cockburn Sound with no bridge, lock or air-draft limit, but the Stirling and Calista Channels are capped at 230 m LOA, 32.5 m beam and under 10.6 m draft on DUKC, and the Woodman, Jervoise and Medina Channels at under 8.5 m draft, inside a working bulk and liquids port with anchorage and passing restrictions. [Source 8](#au-src-8): Fremantle Port Authority Port Information Guide 2025, Fremantle Port Authority.                                                              | Kwinana and Cockburn Sound · Fabrication precedent · 4 of 5 Western Australia's key shipbuilding and sustainment industrial precinct sits immediately north with heavy load-out infrastructure, a floating dock and transfer system, and the Kwinana strip itself carries Alcoa alumina, BP refinery and bulk-handling jetties with 50,000 t to 140,000 t design displacements. The Kwinana quay line itself has no delivered heavy load-out record. [Source 33](#au-src-33): Australian Marine Complex - About, DevelopmentWA.                                                                                                                                          | Kwinana and Cockburn Sound · Flip site · 4 of 5 Perth Canyon Marine Park at 120 m to 5,000 m, 19 km west of Rottnest Island, with South-west Corner Marine Park as a backup. Both are Commonwealth marine parks requiring an authorisation, and no navigation-grade polygon has been surveyed. [Source 6](#au-src-6): Perth Canyon Marine Park, Parks Australia.                                                                                                                                                                                                                                         | Kwinana and Cockburn Sound · State support · 4 of 5 Western Power's Transmission System Plan fixes CEL Kwinana Stages 1 and 2 and Western Power names Kwinana a key industrial area for reinforcement, inside a State programme funded by $1.6 billion provided plus a $1.4 billion Clean Energy Fund. DevelopmentWA holds the industrial land. No negotiated package exists for this project. [Source 11](#au-src-11): Transmission System Plan 2025 (Draft), Western Power.                                                                                                                                                                                                                        | Kwinana and Cockburn Sound · Federal funding · 1 of 5 The Future Made in Australia production tax credits reach only renewable hydrogen at $2 per kilogram and 31 critical minerals at ten per cent of processing and refining costs from 2027-28 to 2039-40\. A marine manufacturing and data-centre hub is outside both heads, and no other Commonwealth production-side instrument was found. [Source 34](#au-src-34): Future Made in Australia production tax credits pass the Senate, Department of Climate Change, Energy, the Environment and Water.                                                                                                                                                                                              | Kwinana and Cockburn Sound · Workforce · 2 of 5 The same Perth metropolitan trades pool as Henderson, absorbed by a precinct that will support in the order of 10,000 high-skilled jobs, against a named offset of $11.4 million over three years for the Western Australian Defence Industry Pathways Program. No occupation-level net position exists. [Source 14](#au-src-14): New investment in skills paves the way for AUKUS workforce, Minister for Defence.                                                                                                                                                           | Kwinana and Cockburn Sound · Grid headroom · 4 of 5 CEL Kwinana Stage 1 is a Fixed project for 2030 that Western Power states addresses reliability of supply issues in the Kwinana area, with Stage 2 in 2033, and total SWIS generation capacity is planned to rise from about 6,700 MW to 13,500 MW across the study period. No available megawatts at a specific Kwinana connection point, works cost, contribution or energy price is published, and constraints bind at peak demand today. [Source 11](#au-src-11): Transmission System Plan 2025 (Draft), Western Power.                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                       | Kwinana and Cockburn Sound · Regulatory · 3 of 5 Cockburn Sound is a sensitive marine environment now under Commonwealth site characterisation across the region, which will build the environmental and marine baseline. A flip polygon in Perth Canyon Marine Park needs a Parks Australia authorisation, and no port, planning, EPBC or autonomous-operation approval exists for this project. [Source 6](#au-src-6): Perth Canyon Marine Park, Parks Australia.                                                                                                                                                               | Kwinana and Cockburn Sound · Habitability · 4 of 5 Perth's premier industrial corridor about 30 km south of the city, with metropolitan airports, schools, health services and universities within reach. Housing pressure from the Defence precinct build is the main risk and no housing supply or cost data was sourced. [Source 33](#au-src-33): Australian Marine Complex - About, DevelopmentWA.                                                                                                                                                                   |
| Hastings                              | 3         | 65    | Hastings · Land · 3 of 5 OTRA is a 25-hectare industrial waterfront site with storage land, but its Ramsar boundary and parcel constraints remain material. [Source 36](#au-src-36): Victorian Renewable Energy Terminal project location, Port of Hastings Corporation.                                                                                                                                                                                                                                                                                                                                 | Hastings · Channel · 4 of 5 The 250 m national depth model supports regional screening, but gives no Hastings route proof for clearance, turns, traffic or weather windows. [Source 74](#au-src-74): AusBathyTopo 250m (Australia) 2023 Grid, Geoscience Australia.                                                                                                                                                                                                                                                                                | Hastings · Fabrication precedent · 3 of 5 VRET plans a primary offshore-wind assembly port with reinforced pavement; the page also says no existing Victorian port has this capability. [Source 36](#au-src-36): Victorian Renewable Energy Terminal project location, Port of Hastings Corporation.                                                                                                                                                                                                                                                                                                                                                                     | Hastings · Flip site · 4 of 5 AusBathyTopo supports a regional deep-water search outside Western Port, but does not certify primary and backup 120 m flip polygons. [Source 74](#au-src-74): AusBathyTopo 250m (Australia) 2023 Grid, Geoscience Australia.                                                                                                                                                                                                                                                                                                                                              | Hastings · State support · 4 of 5 Victoria budgeted A$150 million for investment and A$5.3 million for advanced manufacturing, but the source gives Hastings no package terms. [Source 79](#au-src-79): 2025-26 Victorian State Budget released, Victorian Department of Jobs, Skills, Industry and Regions.                                                                                                                                                                                                                                                                                                                                                                                         | Hastings · Federal funding · 2 of 5 NRFC priorities include transport, renewables and industrial manufacturing, but the page records no Hastings eligibility decision, value or offer. [Source 76](#au-src-76): Our priority areas, National Reconstruction Fund Corporation.                                                                                                                                                                                                                                                                                                                                                                                                                                                                            | Hastings · Workforce · 4 of 5 Victoria budgeted A$459.3 million for skills and A$5.3 million for advanced manufacturing, but gives no Hastings net workforce or housing model. [Source 79](#au-src-79): 2025-26 Victorian State Budget released, Victorian Department of Jobs, Skills, Industry and Regions.                                                                                                                                                                                                                                                                                                                  | Hastings · Grid headroom · 2 of 5 The Cranbourne PACR selects a fourth 150 MVA transformer costing A$62.9 million for reliability, but it gives Hastings no factory connection offer. [Source 37](#au-src-37): Cranbourne RIT-T project assessment conclusions report, Australian Energy Market Operator.                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                             | Hastings · Regulatory · 2 of 5 The OTRA concept borders the Western Port Ramsar site and remains under environmental assessment, so material approval impacts remain unresolved. [Source 36](#au-src-36): Victorian Renewable Energy Terminal project location, Port of Hastings Corporation.                                                                                                                                                                                                                                                                                                                                     | Hastings · Habitability · 4 of 5 The state budget documents jobs and training funds, but no Hastings housing, schools, health, airport or executive-access evidence to substantiate a 4. [Source 79](#au-src-79): 2025-26 Victorian State Budget released, Victorian Department of Jobs, Skills, Industry and Regions.                                                                                                                                                                                                                                                   |
| Gladstone                             | 4         | 64.5  | Gladstone · Land · 4 of 5 GPC is building a 2.8 km reclamation bund to create usable industrial land for heavy industry and OSOM cargo, with final plans approved in 2025. [Source 38](#au-src-38): Northern Land Expansion Project, Gladstone Ports Corporation.                                                                                                                                                                                                                                                                                                                                        | Gladstone · Channel · 3 of 5 The 250 m national depth model supports regional screening, but gives no Gladstone harbour proof for tow distance, turns, traffic or weather windows. [Source 74](#au-src-74): AusBathyTopo 250m (Australia) 2023 Grid, Geoscience Australia.                                                                                                                                                                                                                                                                         | Gladstone · Fabrication precedent · 5 of 5 NLEP is designed for heavy industry and 85-100 m OSOM turbine blades and towers, but the page does not prove serial offshore-module fabrication. [Source 38](#au-src-38): Northern Land Expansion Project, Gladstone Ports Corporation.                                                                                                                                                                                                                                                                                                                                                                                       | Gladstone · Flip site · 3 of 5 AusBathyTopo supports a regional deep-water search beyond Gladstone, but does not certify close, operable primary and backup 120 m polygons. [Source 74](#au-src-74): AusBathyTopo 250m (Australia) 2023 Grid, Geoscience Australia.                                                                                                                                                                                                                                                                                                                                      | Gladstone · State support · 3 of 5 Queensland funds A$5.06 million in manufacturing training and A$201.1 million for four TAFE centres, but names no Gladstone site package. [Source 85](#au-src-85): Fresh look for Manufacturing Skills Queensland, Queensland Government.                                                                                                                                                                                                                                                                                                                                                                                                                         | Gladstone · Federal funding · 2 of 5 NRFC priorities include transport, renewables and industrial manufacturing, but the page records no Gladstone eligibility decision, value or offer. [Source 76](#au-src-76): Our priority areas, National Reconstruction Fund Corporation.                                                                                                                                                                                                                                                                                                                                                                                                                                                                          | Gladstone · Workforce · 4 of 5 Queensland reports 180,000 manufacturing workers and funded training, while also citing a skills shortage and giving no Gladstone net-demand model. [Source 85](#au-src-85): Fresh look for Manufacturing Skills Queensland, Queensland Government.                                                                                                                                                                                                                                                                                                                                            | Gladstone · Grid headroom · 2 of 5 Powerlink costs the Gladstone Project at A$1.788 billion, but reports no confirmed new-load commitments and no reserved site connection. [Source 19](#au-src-19): Transmission Annual Planning Report 2025, Powerlink Queensland.                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                  | Gladstone · Regulatory · 2 of 5 NLEP received EIS approval in 2020 and final plans in 2025, with environmental monitoring required; factory and autonomy approvals are not covered. [Source 38](#au-src-38): Northern Land Expansion Project, Gladstone Ports Corporation.                                                                                                                                                                                                                                                                                                                                                        | Gladstone · Habitability · 3 of 5 The Queensland statement covers manufacturing training only; it gives no Gladstone housing, schools, health, airport or relocation evidence. [Source 85](#au-src-85): Fresh look for Manufacturing Skills Queensland, Queensland Government.                                                                                                                                                                                                                                                                                           |
| Henderson (Australian Marine Complex) | 5         | 63.5  | Henderson (Australian Marine Complex) · Land · 3 of 5 40 ha of fully serviced laydown and assembly area plus reserved industrial land on Western Australian Government land at the AMC, under an open-access policy and a heavy-high-wide road link. Against that, the Commonwealth is consolidating a Defence precinct over the same shipyard and its master plan is not public, so parcel availability is contested and no title, zoning or contamination record was sourced. [Source 39](#au-src-39): Australian Marine Complex Common User Facility, Defence West, Government of Western Australia.  | Henderson (Australian Marine Complex) · Channel · 3 of 5 No bridge, lock or air-draft limit, and a protected harbour dredged to 10 m, but the Jervoise Channel that serves the AMC is limited to 230 m LOA, 32.5 m beam and under 8.5 m draft, and the outbound Success and Parmelia Channels to 275 m LOA, 46 m beam and under 13 m draft on dynamic under-keel clearance, inside a busy commercial port with anchorage and passing rules. [Source 8](#au-src-8): Fremantle Port Authority Port Information Guide 2025, Fremantle Port Authority. | Henderson (Australian Marine Complex) · Fabrication precedent · 5 of 5 The AMC is one of only two naval shipbuilding locations in Australia and Western Australia's key shipbuilding and sustainment industrial precinct, operating since 2003 across shipbuilding, fabrication, support and technology precincts, with heavy load-out berth infrastructure, a fabrication hall and 200 t crane, a floating dock and transfer system and significant laydown serving marine, defence, energy and resources. [Source 33](#au-src-33): Australian Marine Complex - About, DevelopmentWA.                                                                                   | Henderson (Australian Marine Complex) · Flip site · 4 of 5 Perth Canyon Marine Park at 120 m to 5,000 m, 19 km west of Rottnest Island, is the closest documented deep polygon to any site in this screen, with South-west Corner Marine Park (to 6,400 m) as a backup. Both sit inside Commonwealth marine parks with National Park, Habitat Protection and Multiple Use zones, so operating there needs a Parks Australia authorisation, and no navigation-grade polygon has been surveyed. [Source 6](#au-src-6): Perth Canyon Marine Park, Parks Australia.                                          | Henderson (Australian Marine Complex) · State support · 4 of 5 The Western Australian Government owns and manages the AMC through DevelopmentWA's Industrial Lands Authority and runs the Common User Facility under an open-access policy at competitive rates, with a contracted facility manager. It also signed a Cooperation Agreement with the Commonwealth in October 2024 covering the precinct for the next decade and beyond. No package is negotiated for a marine manufacturing hub. [Source 40](#au-src-40): Henderson Defence Precinct, Department of Defence.                                                                                                                         | Henderson (Australian Marine Complex) · Federal funding · 2 of 5 The Commonwealth is spending at this site - $12 billion of early works against about $25 billion of total infrastructure, plus a $127 million planning commitment - which shows appetite, but the money is Defence infrastructure for Defence use. The Future Made in Australia production tax credits reach only renewable hydrogen and 31 critical minerals, so no production-side Commonwealth instrument applies to a marine manufacturing hub. [Source 40](#au-src-40): Henderson Defence Precinct, Department of Defence.                                                                                                                                                         | Henderson (Australian Marine Complex) · Workforce · 2 of 5 The offset is real but small against the demand: $11.4 million over three years for the Western Australian Defence Industry Pathways Program inside a nearly $150 million AUKUS skills package, against a precinct that will absorb in the order of 10,000 high-skilled jobs and a national shortfall of at least 70,000 welders by 2030 that Weld Australia estimates. No occupation-level net position for the Perth metropolitan trades pool exists. [Source 14](#au-src-14): New investment in skills paves the way for AUKUS workforce, Minister for Defence. | Henderson (Australian Marine Complex) · Grid headroom · 3 of 5 CEL Kwinana Stage 1 is a Fixed project for 2030 that Western Power says addresses reliability of supply issues in the Kwinana area, with Stage 2 in 2033, inside a programme funded by $1.6 billion provided plus a $1.4 billion Clean Energy Fund. Against that, the TSP records constraints arising at peak demand in the Kwinana load area today and publishes no available megawatts at a Henderson connection point, no cost contribution and no energy price. [Source 11](#au-src-11): Transmission System Plan 2025 (Draft), Western Power.                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                     | Henderson (Australian Marine Complex) · Regulatory · 3 of 5 AECOM is under contract to Defence to run site characterisation across the Cockburn Sound region to establish the baseline engineering, environmental and marine data for future infrastructure planning and regulatory approvals, which de-risks the approvals path. Against that, Cockburn Sound is a sensitive marine environment, a Perth Canyon polygon needs a Parks Australia authorisation, and no port, planning, EPBC or autonomous-operation approval exists for this project. [Source 40](#au-src-40): Henderson Defence Precinct, Department of Defence. | Henderson (Australian Marine Complex) · Habitability · 4 of 5 The AMC sits in Perth's premier industrial corridor 23 km south of the city, with metropolitan airports, schools, health services and universities within reach. Defence itself notes the precinct will need housing, schools, services and supporting transport infrastructure, so the same growth that supplies the workforce also tightens local housing. [Source 33](#au-src-33): Australian Marine Complex - About, DevelopmentWA.                                                                    |
| Geelong                               | 6         | 59    | Geelong · Land · 3 of 5 Corio Quay has sheds, workshops, utilities, fencing and carparks, but the page does not establish a vacant secure parcel or its tenure and expansion rights. [Source 41](#au-src-41): Corio Quay precinct, GeelongPort.                                                                                                                                                                                                                                                                                                                                                          | Geelong · Channel · 2 of 5 The 250 m national grid can screen depth, but gives no port-specific proof of Corio Quay's tow distance, turns, weather window or disruption. [Source 74](#au-src-74): AusBathyTopo 250m (Australia) 2023 Grid, Geoscience Australia.                                                                                                                                                                                                                                                                                   | Geelong · Fabrication precedent · 3 of 5 Corio Quay handles project cargo plus steel and timber break-bulk, but the operator records no serial module fabrication, large lifts or quality system. [Source 41](#au-src-41): Corio Quay precinct, GeelongPort.                                                                                                                                                                                                                                                                                                                                                                                                             | Geelong · Flip site · 3 of 5 AusBathyTopo provides regional depth screening for the Port Phillip route, but does not certify close primary and backup 120 m flip polygons. [Source 74](#au-src-74): AusBathyTopo 250m (Australia) 2023 Grid, Geoscience Australia.                                                                                                                                                                                                                                                                                                                                       | Geelong · State support · 3 of 5 Victoria budgeted A$150 million for investment, including A$50 million regionally, but the source gives Corio Quay no programme terms or owner. [Source 79](#au-src-79): 2025-26 Victorian State Budget released, Victorian Department of Jobs, Skills, Industry and Regions.                                                                                                                                                                                                                                                                                                                                                                                       | Geelong · Federal funding · 2 of 5 NRFC priorities include transport, renewables and industrial manufacturing, but the page records no Geelong eligibility decision, value or offer. [Source 76](#au-src-76): Our priority areas, National Reconstruction Fund Corporation.                                                                                                                                                                                                                                                                                                                                                                                                                                                                              | Geelong · Workforce · 4 of 5 Victoria budgeted A$459.3 million for skills and A$5.3 million for defence and advanced manufacturing, but gives no Geelong net labour model. [Source 79](#au-src-79): 2025-26 Victorian State Budget released, Victorian Department of Jobs, Skills, Industry and Regions.                                                                                                                                                                                                                                                                                                                      | Geelong · Grid headroom · 2 of 5 AEMO identifies Geelong line limits from summer 2025-26 and A$73.6-173.6 million options, but reserves no 50-150 MW site connection. [Source 42](#au-src-42): Western Metropolitan Melbourne Reinforcement project specification consultation report, Australian Energy Market Operator.                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                             | Geelong · Regulatory · 3 of 5 GeelongPort documents active berths and supporting infrastructure, but the page sets out no planning, marine, environmental or autonomy approval path. [Source 41](#au-src-41): Corio Quay precinct, GeelongPort.                                                                                                                                                                                                                                                                                                                                                                                   | Geelong · Habitability · 4 of 5 The state budget documents jobs and training funds, but no Geelong housing, schools, health, airport or executive-access evidence to substantiate a 4. [Source 79](#au-src-79): 2025-26 Victorian State Budget released, Victorian Department of Jobs, Skills, Industry and Regions.                                                                                                                                                                                                                                                     |
| Burnie/Heybridge                      | 7         | 56.5  | Burnie/Heybridge · Land · 3 of 5 TasPorts maps freight yards, workshops and storage beside four Burnie berths, but does not establish a factory parcel's title, zoning or expansion rights. [Source 75](#au-src-75): Port of Burnie information, TasPorts.                                                                                                                                                                                                                                                                                                                                               | Burnie/Heybridge · Channel · 4 of 5 AusBathyTopo supplies a 250 m national depth model for regional route screening; it does not certify Burnie's tow turns, clearance or weather window. [Source 74](#au-src-74): AusBathyTopo 250m (Australia) 2023 Grid, Geoscience Australia.                                                                                                                                                                                                                                                                  | Burnie/Heybridge · Fabrication precedent · 3 of 5 Burnie handles over five million tonnes of freight and about 45% of Tasmania's containers, proving industrial logistics but not serial offshore fabrication. [Source 75](#au-src-75): Port of Burnie information, TasPorts.                                                                                                                                                                                                                                                                                                                                                                                            | Burnie/Heybridge · Flip site · 4 of 5 The 250 m depth grid supports a regional search for deep water off Burnie, but it does not certify a primary or backup 120 m flip polygon. [Source 74](#au-src-74): AusBathyTopo 250m (Australia) 2023 Grid, Geoscience Australia.                                                                                                                                                                                                                                                                                                                                 | Burnie/Heybridge · State support · 3 of 5 Tasmania offered A$12.6 million to support up to 6,000 learners in 2025, but the programme is statewide and gives Burnie no site package. [Source 31](#au-src-31): Making training more affordable to deliver a skilled workforce, Tasmanian Government.                                                                                                                                                                                                                                                                                                                                                                                                   | Burnie/Heybridge · Federal funding · 2 of 5 NRFC priorities include transport, renewables and industrial manufacturing, but the page records no Burnie eligibility decision, value or offer. [Source 76](#au-src-76): Our priority areas, National Reconstruction Fund Corporation.                                                                                                                                                                                                                                                                                                                                                                                                                                                                      | Burnie/Heybridge · Workforce · 2 of 5 The A$12.6 million grant can support up to 6,000 Tasmanian learners, but it gives no Burnie trade supply, committed-demand or housing model. [Source 31](#au-src-31): Making training more affordable to deliver a skilled workforce, Tasmanian Government.                                                                                                                                                                                                                                                                                                                             | Burnie/Heybridge · Grid headroom · 2 of 5 TasNetworks costs a Burnie-Hampshire upgrade for new generation or load at A$174 million; it does not reserve 50-150 MW for this site. [Source 12](#au-src-12): TasNetworks Annual Planning Report 2024, TasNetworks.                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                       | Burnie/Heybridge · Regulatory · 3 of 5 TasPorts identifies an operating deep-water cargo port and a port procedures manual, but not the full factory, marine, environment or autonomy approval path. [Source 75](#au-src-75): Port of Burnie information, TasPorts.                                                                                                                                                                                                                                                                                                                                                               | Burnie/Heybridge · Habitability · 2 of 5 The statewide training grant addresses course cost only; it gives no Burnie evidence on housing, schools, health, air access or executive relocation. [Source 31](#au-src-31): Making training more affordable to deliver a skilled workforce, Tasmanian Government.                                                                                                                                                                                                                                                            |
| Darwin (East Arm Wharf)               | 8         | 54    | Darwin (East Arm Wharf) · Land · 3 of 5 The ship lift and its hard stand sit on Northern Territory Government land in the East Arm precinct of Darwin Harbour, between the Marine Supply Base at the Port of Darwin and the multi-user barge ramp facility at the Marine Industry Park, inside a $515 million funded marine industrial precinct, so a parcel in a purpose-built marine estate is obtainable. No cadastral parcel, title, tenure, zoning, contamination or Native Title record was sourced. [Source 44](#au-src-44): Darwin Shiplift Project, Northern Australia Infrastructure Facility. | Darwin (East Arm Wharf) · Channel · 3 of 5 East Arm Wharf is a four-berth multi-user facility along 865 m of continuous quay line inside Darwin Harbour with pilotage and harbour control, and no bridge, lock or air-draft limit on the way out. Against that, Darwin has a large tidal range and a November to April cyclone season, and no engineering tow-route or weather-window study exists. [Source 73](#au-src-73): East Arm & Fort Hill Wharf Overview, Darwin Port.                                                                     | Darwin (East Arm Wharf) · Fabrication precedent · 3 of 5 Darwin has a working marine services base at East Arm - the Marine Supply Base, the multi-user barge ramp facility, two stevedore operators and mobile harbour cranes - and the $515 million ship lift is being built to serve coastal shipping, offshore petroleum, fishing, pearling, Defence and the Australian Border Force, which the financier expects to expand the ship building, repair and maintenance industry. No serial offshore or ship-module fabrication, large-lift or steel-flow record exists. [Source 44](#au-src-44): Darwin Shiplift Project, Northern Australia Infrastructure Facility. | Darwin (East Arm Wharf) · Flip site · 2 of 5 Oceanic Shoals Marine Park lies about 150 km north-west of Darwin and reaches 500 m, so water at or beyond 120 m exists inside a single open-water tow, but the park averages 87 m over 71,743 square kilometres and no polygon has been located or surveyed. It is a Commonwealth marine park with National Park, Habitat Protection, Multiple Use and Special Purpose (Trawl) zones, so operating there needs a Parks Australia authorisation, and no backup polygon is identified. [Source 46](#au-src-46): Oceanic Shoals Marine Park, Parks Australia. | Darwin (East Arm Wharf) · State support · 4 of 5 The Northern Territory Government put $215 million of its own money into the $515 million ship lift, on its own land, under a statutory open-access and common-user pricing arrangement, and its Darwin-Katherine Electricity System Plan names zero-emissions data centres and low-emissions advanced manufacturing as the industrial growth the electricity plan is built to serve, aligned to the Territory Economic Reconstruction Commission's $40 billion economy goal. Delivery ownership is clear. No package is negotiated for this project. [Source 44](#au-src-44): Darwin Shiplift Project, Northern Australia Infrastructure Facility. | Darwin (East Arm Wharf) · Federal funding · 3 of 5 The Northern Australia Infrastructure Facility lent up to $300 million over 23.5 years to the Northern Territory Treasury Corporation for exactly this class of marine industrial infrastructure, with a published $924 million public-benefit assessment and a contractual close, so an applicable Commonwealth instrument with documented eligibility, value and conditions demonstrably reaches this site and region. Against that, the Future Made in Australia production tax credits reach only renewable hydrogen and 31 critical minerals, and no application or offer exists for this project. [Source 44](#au-src-44): Darwin Shiplift Project, Northern Australia Infrastructure Facility. | Darwin (East Arm Wharf) · Workforce · 2 of 5 The ship lift is forecast to deliver 287 jobs and to consolidate Darwin as the hub for marine maintenance and servicing in northern Australia, which is a named, costed base to build on. Against that the base is small, no regional heavy fabrication or module workforce is documented, and no occupation-level demand and supply model for the Northern Territory net of committed defence, resources and infrastructure demand was found. [Source 44](#au-src-44): Darwin Shiplift Project, Northern Australia Infrastructure Facility.                                     | Darwin (East Arm Wharf) · Grid headroom · 3 of 5 The Darwin-Katherine Electricity System Plan is a funded ten-year Northern Territory Government programme - 320 MW of new solar by 2030, 110 MW and 600 MWh of storage batteries, 100 MW of high spec security batteries, about 80 MW of new thermal generation, and a Renewable Energy Hub of 180 to 230 MW connected on the existing Channel Island to Hudson Creek 132 kV line without uprating it for about $80 million of transmission connection cost - and its own high-demand scenario is explicitly built on data centres and large industrial loads growing the system fourfold to 1 GW. Against that, Darwin-Katherine is a stand-alone system with no interconnection, the plan dates from 2021 and its Ready 2021-23 stage is past, and no available megawatts, connection voltage, firm capacity, curtailment or energy price at an East Arm connection point is published. [Source 47](#au-src-47): Darwin-Katherine Electricity System Plan: Cleaner, more affordable and secure energy system by 2030, Northern Territory Government / Power and Water Corporation. | Darwin (East Arm Wharf) · Regulatory · 3 of 5 A statutory open-access and pricing arrangement already governs common-user access to the ship lift, and the facility was financed on a published public-benefit test, so the port and access path is clear. Against that, a flip polygon in Oceanic Shoals Marine Park needs a Parks Australia authorisation, and no EPBC referral, Northern Territory planning approval, marine ecology assessment or autonomous-operation approval exists for this project. [Source 44](#au-src-44): Darwin Shiplift Project, Northern Australia Infrastructure Facility.                        | Darwin (East Arm Wharf) · Habitability · 3 of 5 East Arm is a serviced multi-user industrial port precinct about 15 km from Darwin, a capital city with an international airport, schools, health services and a university, and the wharf already supports two stevedore operators and a resident marine services workforce. No housing supply and cost, schools, health, commute-time or research-partner data was sourced, and the Territory labour market is the smallest in the country. [Source 73](#au-src-73): East Arm & Fort Hill Wharf Overview, Darwin Port. |

Each mark from 0 to 5 has its own shade, shown in the key above. Column widths follow the weights, down to a minimum that keeps the narrowest columns legible. Select a mark to read its note and source. 

Land

Parcel, title, zoning and the constraint record.

Channel

Tow turns, traffic, clearance and weather windows.

Fabrication precedent

Heavy modules already delivered at the site.

Flip site

A certified primary and backup 120 m flip polygon.

State support

A negotiated state package, not a general programme.

Federal funding

A named federal instrument with a value or an offer.

Workforce

Trades available after committed demand and housing limits.

Grid headroom

Capacity a network operator can reserve for the factory.

Regulatory

Factory, marine, environment and autonomy approvals.

Habitability

Housing, schools, health and air access for the cohort.

The top four change places under small changes to the weights

 The eight scored sites re-ranked live under weights the reader sets, each starting at the report's figure; a hollow mark is where the site sat under the report's weights · Source: Score per cell, site screening record; weights from chapter 4 until the reader moves them 

Bell Bay leads with 69.0\. The report's order holds.

Bell Bay leads with 69.0\. The report's order holds.

Set the weights without dragging

land

10

channel

12.5

fab. precedent

10

flip site

12.5

state support

2.5

federal funding

2.5

workforce

20

grid headroom

15

regulatory

10

habitability

5

Drag a handle to change one weight; the other nine hold and the total rescales to 100\. The accent dots are the report's five shortlisted sites. Reset returns the report's weights. 

5 

## Chapter 5\. The eight, in order 

Fifteen points separate the first site from the last. No site is strong on everything, and for each of the eight one document matters most.

### The two at the top

Bell Bay scores 69.0 out of 100, the highest of the eight. Land and fabrication both get a 4, because it is a working industrial estate. TasPorts maps development land there beside seven berths, with Bell Bay Aluminium, OneSteel, Temco and Sims Metal as neighbours.[30](#au-src-30)30 [Bell Bay port information](https://wpp.tasports.com.au/bell-bay-port-information), TasPorts, accessed 23 August 2026. Its lowest marks are habitability and federal funding, at 2 each. On habitability, the only Tasmanian programme in evidence is a statewide A$12.6 million training grant, which says nothing about housing, schools or air access at Bell Bay.[31](#au-src-31)31 [Making training more affordable to deliver a skilled workforce](https://www.premier.tas.gov.au/latest-news/2024/september/making-training-more-affordable-to-deliver-a-skilled-workforce), Tasmanian Government, 7 September 2024. The document that matters most is TasNetworks' conclusions report of 16 October 2026\. It prefers a A$370.6 million network upgrade at George Town: a new substation with 550 MVAr of reactive support, triggered when 210 MW or more of new load commits.[13](#au-src-13)13 [Meeting Network Planning Requirements at George Town, project assessment conclusions report](https://www.tasnetworks.com.au/planning-and-projects/major-projects/meeting-network-planning-requirements-at-george-town), TasNetworks, 16 October 2026. Firmus's 288 MW campus, approved at Bell Bay on 25 August and now under appeal, exceeds that trigger on its own, which would make a factory the second load on the same works.[32](#au-src-32)32 [Firmus 288-megawatt AI data centre at Bell Bay receives George Town Council approval](https://www.abc.net.au/news/2026-08-25/firmus-ai-bell-bay-receives-george-town-council-approval/107074336), ABC News, 25 August 2026. Commissioning by 2030 is not certain.

Kwinana scores 66.0, and its grid mark of 4 is the highest in the screen. Land, fabrication, state support and habitability all get a 4, across five Australian Marine Complex precincts held on Western Australian Government land in Perth's industrial corridor.[33](#au-src-33)33 [Australian Marine Complex, About](https://developmentwa.com.au/projects/industrial-and-commercial/australian-marine-complex/about-the-amc), DevelopmentWA, accessed 23 August 2026. Federal funding gets a 1, the lowest mark in the matrix, because the Future Made in Australia production tax credits cover only renewable hydrogen and 31 critical minerals.[34](#au-src-34)34 [Future Made in Australia production tax credits pass the Senate, Department of Climate Change, Energy](https://www.dcceew.gov.au/about/news/future-made-australia-production-tax-credits-pass-senate), the Environment and Water, 12 February 2025. The grid mark rests on Western Power's Transmission System Plan 2025\. That plan lists Clean Energy Link Kwinana Stage 1 as a fixed project with an earliest entry of 2030 to address supply reliability in the Kwinana area. Western Power's project page now targets 2029, subject to funding and approvals.[11](#au-src-11)11 [Transmission System Plan 2025 (Draft)](https://www.westernpower.com.au/495bb8/siteassets/documents/nom/transmission-system-plan-2025-draft.pdf), Western Power, March 2026.[35](#au-src-35)35 [Clean Energy Link Kwinana Strengthening](https://letstalkpower.westernpower.com.au/kwinana-strengthening), Western Power, accessed 31 October 2026. Neither document publishes available megawatts at any Kwinana connection point.

### Three within a point and a half

Hastings scores 65.0, with 4s for channel, workforce, state support and habitability. Regulatory gets a 2, and the reason is in the terminal's own paperwork. In its project location record for the Victorian Renewable Energy Terminal, the Port of Hastings Corporation describes a 25 hectare industrial waterfront at the Old Tyabb Reclamation Area and states that no existing Victorian port has this capability. The same record puts the parcel against the Western Port Ramsar boundary and inside an environmental assessment.[36](#au-src-36)36 [Victorian Renewable Energy Terminal project location](https://renewableenergyterminal.com.au/about/project-location), Port of Hastings Corporation, accessed 23 August 2026. Grid headroom also gets a 2\. The nearest costed work is a fourth 150 MVA transformer at Cranbourne, priced at A$62.9 million and bought for supply reliability, not for a factory.[37](#au-src-37)37 [Cranbourne RIT-T project assessment conclusions report](https://aemo.com.au/consultations/current-and-closed-consultations/cranbourne-rit-t-project-assessment-conclusions-report), Australian Energy Market Operator, accessed 23 August 2026.

Gladstone scores 64.5 and shares the highest fabrication mark in the screen, a 5\. The port is creating about 109 hectares of new industrial land behind a 2.8 km reclamation bund built for heavy industry and out-of-gauge cargo of 85 to 100 m.[38](#au-src-38)38 [Northern Land Expansion Project](https://gpcl.com.au/ports-and-trade/major-projects/northern-land-expansion/), Gladstone Ports Corporation, accessed 23 August 2026. Regulatory and grid headroom both get a 2\. The decisive document is Powerlink's 2025 planning report, which costs the Gladstone project at A$1.788 billion in real 2025 dollars. That is the largest load-driven network build behind any site here, but the report records no confirmed new-load commitments and no connection reserved for anyone.[19](#au-src-19)19 [Transmission Annual Planning Report 2025](https://www.powerlink.com.au/sites/default/files/2025-12/Transmission%20Annual%20Planning%20Report%202025.pdf), Powerlink Queensland, December 2025. Reef-linked approvals and a long harbour route hold the marine marks down, despite an industrial base as strong as any of the eight.

Henderson, at the Australian Marine Complex, scores 63.5 and has the only quay pass among the 23 sites. The quay pass comes from the Fremantle Port Authority's Port Information Guide 2025, which rates Australian Marine Complex berths 1 and 5 at 3,000 t design displacement and declares the heavy lift berth at 12.6 m.[8](#au-src-8)8 [Port Information Guide 2025](https://www.fremantleports.com.au/docs/default-source/annual-report-case-study-videos-2023/fpa-port-information-guide-2025.pdf?sfvrsn=55215337%5F1), Fremantle Port Authority, 2025. That rating describes the vessels the berths can take. A transfer at the base design weight is my inference, and nobody has tested it. Fabrication gets a 5\. Workforce gets a 2\. The score note puts the precinct at about 10,000 high-skilled jobs, alongside a national shortfall of at least 70,000 welders by 2030 attributed to Weld Australia.[14](#au-src-14)14 [New investment in skills paves the way for AUKUS workforce](https://www.minister.defence.gov.au/media-releases/2023-05-16/new-investment-skills-paves-way-aukus-workforce), Minister for Defence, 16 May 2023. The spot-check of the same skills release for the Osborne row found no welder figure, so that number rests on no document in the record. Land gets a 3, because the Commonwealth master plan for the precinct is not public and the line between Defence land and tenant land has not been drawn.[39](#au-src-39)39 [Australian Marine Complex Common User Facility, Defence West](https://directory.defencewest.wa.gov.au/company/australian-marine-complex/), Government of Western Australia, accessed 23 August 2026.[40](#au-src-40)40 [Henderson Defence Precinct](https://www.defence.gov.au/business-industry/industry-capability-programs/continuous-naval-shipbuilding-sustainment-enterprise/henderson-defence-precinct), Department of Defence, accessed 23 August 2026.

### The three below the shortlist

Geelong scores 59.0, and its channel mark of 2 is the lowest marine mark at any scored site. Corio Quay is a working precinct with berth depths of 11.0 to 12.3 m and a 14.4 t axle limit; its largest listed door is 12 m by 6.5 m. That is a long way from a hall that can pass an 80 m node.[41](#au-src-41)41 [Corio Quay precinct](https://geelongport.com.au/port-operations/corio-quay-precinct/), GeelongPort, accessed 23 August 2026. Its grid case rests on AEMO's March 2025 consultation report for the Western Metropolitan Melbourne Reinforcement. The report prices four options between A$73.6 million and A$173.6 million in real 2024 dollars, at plus or minus 50%. They would lift network capacity from 2,700 MW towards 3,500 MW, with earliest commissioning between late 2028 and late 2030.[42](#au-src-42)42 [Western Metropolitan Melbourne Reinforcement project specification consultation report](https://web.archive.org/web/20250808071933/https://aemo.com.au/-/media/files/initiatives/western-metropolitan-melb-reinforcement/western-metropolitan-melbourne-reinforcement-project-specification-consultation-report.pdf?la=en), Australian Energy Market Operator, March 2025. That consultation is the first stage of a regulatory test, not a committed investment.

Burnie/Heybridge scores 56.5\. Only Hastings matches its marine marks, with channel and flip site both at 4: Bass Strait's deep water lies straight off a port that declares 11.4 m at Berth 7 and a 10.0 m corridor and turning circle.[43](#au-src-43)43 [Port of Burnie declared depths by sector](https://tasports.com.au/volumes/documents/HMI-Burnie/EXT-HMI-24-31-Port-of-Burnie-declared-depths-sectors-Issued-14.05.2024-valid-until-Cancelled.pdf), TasPorts, 14 May 2024. Workforce, grid headroom and habitability all get a 2, which makes its lower half the thinnest of the eight. On the grid, TasNetworks' 2024 planning report costs North West Transmission Developments Stage 1 at A$1,144 million and records the A$151.9 million of Stage 1 early works the regulator approved in March 2025\. It ties delivery to Marinus Link Stage 1, not to any date this factory would choose.[12](#au-src-12)12 [Annual Planning Report 2024](https://www.tasnetworks.com.au/Documents/Manual-documents/Planning-and-upgrades/APR/TasNetworks-Annual-Planning-Report-2024), TasNetworks, October 2024.

Darwin, at East Arm Wharf, scores 54.0 and comes last of the eight. Its federal funding mark of 3 is the highest in the screen, earned on a Northern Australia Infrastructure Facility loan of up to A$300 million over 23.5 years.[44](#au-src-44)44 [Darwin Shiplift Project](https://www.naif.gov.au/our-projects/nt-government-darwin-shiplift-project/), Northern Australia Infrastructure Facility, accessed 23 August 2026. The 5,500 t ship lift covers the whole design range, but it is still a construction project with staged operation in 2027, so the quay gate reads remediable, not pass.[45](#au-src-45)45 [Darwin Ship Lift Facility](https://www.cloughgroup.com/projects/darwin-ship-lift-facility), Clough, accessed 23 August 2026. Flip site gets a 2, because Oceanic Shoals Marine Park reaches 500 m but averages 87 m, and no flip polygon has been located.[46](#au-src-46)46 [Oceanic Shoals Marine Park](https://parksaustralia.gov.au/marine/parks/north/oceanic-shoals/), Parks Australia, accessed 23 August 2026. The grid mark rests on the Darwin-Katherine Electricity System Plan of 2021\. It commits 320 MW of new solar by 2030 and a 180 to 230 MW renewable energy hub on the existing Channel Island to Hudson Creek 132 kV line, in a system with no interconnection to any other.[47](#au-src-47)47 [Darwin-Katherine Electricity System Plan](https://www.powerwater.com.au/%5F%5Fdata/assets/pdf%5Ffile/0024/130497/darwin-katherine-electricity-system-plan-web.pdf), Northern Territory Government and Power and Water Corporation, 21 May 2021.

1. [Bell Bay port information](https://wpp.tasports.com.au/bell-bay-port-information), TasPorts, accessed 23 August 2026\.
2. [Making training more affordable to deliver a skilled workforce](https://www.premier.tas.gov.au/latest-news/2024/september/making-training-more-affordable-to-deliver-a-skilled-workforce), Tasmanian Government, 7 September 2024\.
3. [Firmus 288-megawatt AI data centre at Bell Bay receives George Town Council approval](https://www.abc.net.au/news/2026-08-25/firmus-ai-bell-bay-receives-george-town-council-approval/107074336), ABC News, 25 August 2026\.
4. [Australian Marine Complex, About](https://developmentwa.com.au/projects/industrial-and-commercial/australian-marine-complex/about-the-amc), DevelopmentWA, accessed 23 August 2026\.
5. [Future Made in Australia production tax credits pass the Senate, Department of Climate Change, Energy](https://www.dcceew.gov.au/about/news/future-made-australia-production-tax-credits-pass-senate), the Environment and Water, 12 February 2025\.
6. [Clean Energy Link Kwinana Strengthening](https://letstalkpower.westernpower.com.au/kwinana-strengthening), Western Power, accessed 31 October 2026\.
7. [Victorian Renewable Energy Terminal project location](https://renewableenergyterminal.com.au/about/project-location), Port of Hastings Corporation, accessed 23 August 2026\.
8. [Cranbourne RIT-T project assessment conclusions report](https://aemo.com.au/consultations/current-and-closed-consultations/cranbourne-rit-t-project-assessment-conclusions-report), Australian Energy Market Operator, accessed 23 August 2026\.
9. [Northern Land Expansion Project](https://gpcl.com.au/ports-and-trade/major-projects/northern-land-expansion/), Gladstone Ports Corporation, accessed 23 August 2026\.
10. [Australian Marine Complex Common User Facility, Defence West](https://directory.defencewest.wa.gov.au/company/australian-marine-complex/), Government of Western Australia, accessed 23 August 2026\.
11. [Henderson Defence Precinct](https://www.defence.gov.au/business-industry/industry-capability-programs/continuous-naval-shipbuilding-sustainment-enterprise/henderson-defence-precinct), Department of Defence, accessed 23 August 2026\.
12. [Corio Quay precinct](https://geelongport.com.au/port-operations/corio-quay-precinct/), GeelongPort, accessed 23 August 2026\.
13. [Western Metropolitan Melbourne Reinforcement project specification consultation report](https://web.archive.org/web/20250808071933/https://aemo.com.au/-/media/files/initiatives/western-metropolitan-melb-reinforcement/western-metropolitan-melbourne-reinforcement-project-specification-consultation-report.pdf?la=en), Australian Energy Market Operator, March 2025\.
14. [Port of Burnie declared depths by sector](https://tasports.com.au/volumes/documents/HMI-Burnie/EXT-HMI-24-31-Port-of-Burnie-declared-depths-sectors-Issued-14.05.2024-valid-until-Cancelled.pdf), TasPorts, 14 May 2024\.
15. [Darwin Shiplift Project](https://www.naif.gov.au/our-projects/nt-government-darwin-shiplift-project/), Northern Australia Infrastructure Facility, accessed 23 August 2026\.
16. [Darwin Ship Lift Facility](https://www.cloughgroup.com/projects/darwin-ship-lift-facility), Clough, accessed 23 August 2026\.
17. [Oceanic Shoals Marine Park](https://parksaustralia.gov.au/marine/parks/north/oceanic-shoals/), Parks Australia, accessed 23 August 2026\.
18. [Darwin-Katherine Electricity System Plan](https://www.powerwater.com.au/%5F%5Fdata/assets/pdf%5Ffile/0024/130497/darwin-katherine-electricity-system-plan-web.pdf), Northern Territory Government and Power and Water Corporation, 21 May 2021\.

6 

## Chapter 6\. Two yards that already do this 

One of the two yards has nine dry docks and a spar hull on its record. The other has a pair of 30,000-tonne cranes and a regulator's finding about its welds.

HD Hyundai's Ulsan yard runs nine dry docks. The 2026 offering circular states that figure twice and counts HD Hyundai Mipo's four docks separately following Mipo's merger into HHI on 1 December 2025.[48](#au-src-48)48 [Offering Circular, U.S.$1,550,000,000 Zero Coupon Exchangeable Bonds due 2031](https://links.sgx.com/FileOpen/HD%20Korea%20Shipbuilding%20and%20Offshore%20Engineering%20Co%20Ltd%5FFinal%20OC%20%28bannerless%203-31-2026%29.ashx?App=Prospectus&FileID=69866), HD Korea Shipbuilding & Offshore Engineering, 31 March 2026. Under a Technip Energies consortium contracted in 2012, the yard delivered the Aasta Hansteen spar hull, 50 m across and 198 m long with 146,000 tonnes of displacement.[49](#au-src-49)49 [Aasta Hansteen sea spar, case study](https://www.ten.com/en/case-studies/aasta-hansteen), Technip Energies, accessed 23 August 2026.

Tuas Boulevard in Singapore is the benchmark for lifting a hull in one piece. The owner's 2022 annual report records a new pair of gantry cranes with a 30,000-tonne lifting capacity and a 100 m hook height on about 1.52 million square metres of long-lease waterfront. The report does not say whether that capacity is for each crane or for the pair, so I do not restate it as a combined figure.[50](#au-src-50)50 [Sembcorp Marine Annual Report 2022](https://www.seatrium.com/assets/reports/Sembcorp-Marine%5FAR2022.pdf), Sembcorp Marine (now Seatrium), 1 April 2023. The yard's named offshore record includes the Johan Castberg hull, the Vito and Whale units, and Deepwater Atlas and Titan.[50](#au-src-50)50 [Sembcorp Marine Annual Report 2022](https://www.seatrium.com/assets/reports/Sembcorp-Marine%5FAR2022.pdf), Sembcorp Marine (now Seatrium), 1 April 2023. Norway's safety regulator investigated that same Johan Castberg hull and found that the yard's experience was primarily in shipbuilding, recording inadequate welding quality and extensive repairs.[51](#au-src-51)51 [Equinor, Johan Castberg: investigation of the reasons for the challenges faced in constructing hull and equipment](https://www.havtil.no/en/supervision/investigation-reports/2021/order-to-equinor-following-investigation-of-the-johan-castberg-project/), Havtil (Petroleum Safety Authority Norway), 1 June 2021.

Korea's cash grant is narrow. Invest KOREA restricts it to foreign investment in new shares at 30% or more, excluding long-term loans, and no category on its eligible list covers a factory for wave-energy compute nodes.[52](#au-src-52)52 [Cash Grants, Eligible Businesses](https://www.investkorea.org/ik-en/cntnts/i-375/web.do), Invest KOREA (KOTRA), accessed 23 August 2026. Singapore's Pioneer Certificate is discretionary and runs for five years; it is accounted for separately and carries an explicit clawback.[53](#au-src-53)53 [Pioneer Certificate Incentive and Development and Expansion Incentive](https://www.edb.gov.sg/content/dam/edb-zh/downloads/brochures/PC%20and%20DEI%20Brochure.pdf), Singapore Economic Development Board, 1 January 2022.

Against yards like Ulsan and Tuas Boulevard, the main report puts the Australian premium at about 40% and 30 months for a first node, and about 20% and 15 months for a series of 20 nodes. Those figures come from RAND's study of Australian naval shipbuilding and the audited delay to HMAS Hobart.[54](#au-src-54)54 [Minister for Defence, release of the RAND Corporation report](https://www.minister.defence.gov.au/media-releases/2015-04-16/minister-defence-release-rand-corporation-report), Department of Defence, 16 April 2015.[55](#au-src-55)55 [Auditor-General Report No.19 2020-21, 2019-20 Major Projects Report, Air Warfare Destroyer Build](https://www.anao.gov.au/sites/default/files/Auditor-General%5FReport%5F2020-2021%5F19%5FPDSS%5Fair%5Fwarfare%5Fdestroyer%5Fbuild.pdf), Australian National Audit Office, 30 November 2020. Only the series case falls inside the target of 30% and 18 months. The schedule half of that case is my extrapolation, not something RAND found.

1. [Offering Circular, U.S.$1,550,000,000 Zero Coupon Exchangeable Bonds due 2031](https://links.sgx.com/FileOpen/HD%20Korea%20Shipbuilding%20and%20Offshore%20Engineering%20Co%20Ltd%5FFinal%20OC%20%28bannerless%203-31-2026%29.ashx?App=Prospectus&FileID=69866), HD Korea Shipbuilding & Offshore Engineering, 31 March 2026\.
2. [Aasta Hansteen sea spar, case study](https://www.ten.com/en/case-studies/aasta-hansteen), Technip Energies, accessed 23 August 2026\.
3. [Sembcorp Marine Annual Report 2022](https://www.seatrium.com/assets/reports/Sembcorp-Marine%5FAR2022.pdf), Sembcorp Marine (now Seatrium), 1 April 2023\.
4. [Equinor, Johan Castberg: investigation of the reasons for the challenges faced in constructing hull and equipment](https://www.havtil.no/en/supervision/investigation-reports/2021/order-to-equinor-following-investigation-of-the-johan-castberg-project/), Havtil (Petroleum Safety Authority Norway), 1 June 2021\.
5. [Cash Grants, Eligible Businesses](https://www.investkorea.org/ik-en/cntnts/i-375/web.do), Invest KOREA (KOTRA), accessed 23 August 2026\.
6. [Pioneer Certificate Incentive and Development and Expansion Incentive](https://www.edb.gov.sg/content/dam/edb-zh/downloads/brochures/PC%20and%20DEI%20Brochure.pdf), Singapore Economic Development Board, 1 January 2022\.
7. [Minister for Defence, release of the RAND Corporation report](https://www.minister.defence.gov.au/media-releases/2015-04-16/minister-defence-release-rand-corporation-report), Department of Defence, 16 April 2015\.
8. [Auditor-General Report No.19 2020-21, 2019-20 Major Projects Report, Air Warfare Destroyer Build](https://www.anao.gov.au/sites/default/files/Auditor-General%5FReport%5F2020-2021%5F19%5FPDSS%5Fair%5Fwarfare%5Fdestroyer%5Fbuild.pdf), Australian National Audit Office, 30 November 2020\.

Ulsan is the repeatability benchmark: HD Hyundai's yard runs nine large dry docks after the 2025 Mipo merger and built the Aasta Hansteen spar hull, 146,000 tonnes of displacement. An Australian site buys that dock, crane, and supplier depth as new enabling capital, and pays a first-article learning penalty Ulsan has already paid.

Tuas Boulevard is the single-piece integration benchmark: 30,000-tonne gantry capacity lets a complete mega-block leave the yard in one lift. It is also the caution: Norway's regulator found inadequate welding quality there on the Johan Castberg hull. No Australian public document yet proves a 5,000-tonne single-piece load-out.